    A Stepped Spillway Preceded by aSupercritical Flow Channel

    aro u y rau c ng neer

    Sacramento District Corps of Engineers

    June 14, 2011

    US Army Corps of Engineers

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    2/37

    -

    BUILDING STRONG2

  • 7/29/2019 Design of Stepped Spillway

    3/37

    BUILDING STRONG3

  • 7/29/2019 Design of Stepped Spillway

    4/37

    Dam SafetyDam Safety

    Capacity

    Capacity

    Flood Protection D/S Levee Capacity Flood Protection D/S Levee Capacity

    160,000 cfs Lower Outlets 25,000 cfs160,000 cfs Lower Outlets 25,000 cfs

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    5/37

    Main DamMain Dam

    Structure

    Structure

    illwillwChute

    Chute

    pproacChannel

    pproacChannel

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    6/37

    Chute

    Chute

    Stepped

    Chute

    Stepped

    ChutetillintillinBasin

    Basin

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    7/37

    CORPS CONSTRUCTED DAM IN 1950S

    DAM TURNED OVER RECLAMATIONHYDROPOWER AND WATER SUPPLY

    RECENTY HISTORY CORPS

    REDUCTION CAPABILITY OF DAM;

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    8/37

    CORPS MODS TO MAIN DAM PROJECT

    USBR FUSE PLUG SPILLWAY INCL

    DAM EMBANKMENT AND FOLSOM

    CORPS BEST ALT FOR MODS PROJ

    AUX SPWY WITH SUBMERGED GATE;SAME ALIGNMENT AS FUSE PLUG

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    9/37

    PMF Q = 320K CFS; FC DESIGN Q =

    LIMITED SPACE FOR AUXILIARY; 6 34 23

    SUBMERGED (BY 100 +) TAINTER;

    CHUTE WIDTH = 169; HIGH UNIT Q

    q = 800 (DES) AND 1900 (PMF) CFS/FT

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    10/37

    2100 LONG CONCRETE LINED,

    BASED ON ROCK LINE RESULTED IN

    V = 67 FPS FOR 135k CFS & 80 /SEC

    320OF CHUTE

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    11/37

    Stepped Spillway inSupercritical Spillway Chute

    (135,000 cfs)

    (320,000 cfs)

    c s

    78 ft/sec - Max

    ,

    84 ft/sec - Max

    3.7 - Froude #

    10.8 ft - Depth

    . -

    23.2 ft - Depth

    BUILDING STRONG11

  • 7/29/2019 Design of Stepped Spillway

    12/37

    STEPPED CHUTE U/S OF A STILLING

    CONVENTIONAL PARABOLIC DROP /

    COMPARATIVE COSTS.

    BASED ON A PARABOLIC DROP EQ.

    STEP HEIGHTS VARY FROM ABOUT0.8 AT U/S END TO 3 (MOST ARE 3)

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    13/37

    Stepped Spillway inSupercritical Spillway Chute

    Y=0.02*X+0.000472406*X2S=0.02

    1V:2.483555158H

    Stilling

    BUILDING STRONG13

  • 7/29/2019 Design of Stepped Spillway

    14/37

    INTERACTION OF STEPS AND BASIN

    ABRASION OF STEPS NEED FOR ADDED AERATION

    LOADINGS FOR STRUCTURAL DESIGN

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    15/37

    MODELS HELPADDRESS CONCERNS

    USBR 1:48 SCALE PHYSICAL MODEL

    USBR CFD (FLOW-3D) ALDEN LABS CHECK OF CFD RESULTS

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    16/37

    BUILDING STRONG16

  • 7/29/2019 Design of Stepped Spillway

    17/37

    BUILDING STRONG17

  • 7/29/2019 Design of Stepped Spillway

    18/37

    BUILDING STRONG18

  • 7/29/2019 Design of Stepped Spillway

    19/37

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    20/37

    SAFL 1:26 SCALE MODEL

    BUILDING STRONG20

    = ,

  • 7/29/2019 Design of Stepped Spillway

    21/37

    BUILDING STRONG21

    Q = 135,000 cfsQ = 135,000 cfs

  • 7/29/2019 Design of Stepped Spillway

    22/37

    Q = 322,000Q = 322,000 cfscfs

    BUILDING STRONG22

  • 7/29/2019 Design of Stepped Spillway

    23/37

    Profile of Stepped Spillway

    340

    Velocit Profile

    280

    300

    320

    @ Step 0 Velocity Profile@ Step 32

    240

    260

    tio

    n,

    feet

    V l i Pr fil

    180

    200Eleva

    @ Step 61

    120

    140

    160

    BUILDING STRONG23

    31+00 32+00 33+00 34+00 35+00 36+00 37+00 38+00 39+00 40+00

    Station, feet

  • 7/29/2019 Design of Stepped Spillway

    24/37

    135 000 CFS VELOCITIES10

    12

    8

    Step 0_5

    Step 0_4

    Step 0_3

    Step 0_2

    Step 0_1

    6

    Depth

    (ft)

    ep _

    Step 32_4

    Step 32_3

    Step 32_2

    Step 32_1Step 61_5

    4

    Step 61_4

    Step 61_3

    Step 61_2

    Step 61_1

    0

    2

    BUILDING STRONG

    35 45 55 65 75 85 95 105 115

    Velocity (ft/sec)

  • 7/29/2019 Design of Stepped Spillway

    25/37

    ,25

    Step 0_5

    Ste 0 4

    20

    _

    Step 0_3

    Step 0_2Step 0_1

    Step 32_5

    Step 32_4

    15

    Depth

    (ft) Step 32_3

    Step 32_2

    Step 32_1

    Step 61_5

    Step 61_4

    10ep _

    Step 61_2

    Step 61_1

    0

    BUILDING STRONG

    40 50 60 70 80 90 100 110 120 130 140

    Velocity (ft/sec)

  • 7/29/2019 Design of Stepped Spillway

    26/37

    SAFL ENERGY LOSS

    Discharge

    EnergyLoss

    SpillwayEnergy Loss

    Stilling Basin

    Energy Loss

    22,508 93% - -

    - -

    113,049 83% - -

    ,158,249 78% - -

    BUILDING STRONG26

    301,710 67% 34% 33%

  • 7/29/2019 Design of Stepped Spillway

    27/37

    ENERGY LOSS

    CONFIRMATIONS

    USBR CFD MODEL

    :

    CFD MODEL AT ALDEN LABS

    ANALYTICAL COMPS ABOUT 10% LOWERTHAN OTHERS

    MODELS WERE CLOSE.

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    28/37

    Design Flow (135,000 cfs)

    Velocity (ft/s)

    Pressure (psi)

    BUILDING STRONG28

  • 7/29/2019 Design of Stepped Spillway

    29/37

    Design Flow (135,000 cfs)

    Velocity (ft/s)

    Pressure (psi)

    BUILDING STRONG29

  • 7/29/2019 Design of Stepped Spillway

    30/37

    Design Flow (135,000 cfs)

    Velocity (ft/s)

    Pressure (psi)

    BUILDING STRONG30

  • 7/29/2019 Design of Stepped Spillway

    31/37

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    32/37

    Test section for atmospheric

    work on laboratory floor.

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    33/37

    PIV data (large steps-slope

    0.4)Step 4 velocity Step 14 velocity

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    34/37

    = .

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    35/37

    = .

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    36/37

    INTERACTION OF STEPS AND BASIN

    BUILDING STRONG

  • 7/29/2019 Design of Stepped Spillway

    37/37

    MODELING

    NOT FULLY ADDRESSED - -

    NEED FOR ADDED AERATION

    BUILDING STRONG