details project reportenvironmentclearance.nic.in/.../online/tor/0_0_10...details project report for...

51
1 DETAILS PROJECT REPORT FOR IRON ORE PELLETIZATION PLANT (CAPACITY-2X1200 TPD) (2X0.4) 0.8 MILLION TPA VILLAGE: PARAGHAT TEHSIL: MASTURI DISTRICT: BILASPUR CHHATTISGARH SUBMITTED BY M/s RASHI STEEL AND POWER LIMITED BF-1,FIRST FLOOR, RAJIV PLAZA OPP.AXIS BANK- BILASPUR, (CHHATTISGARH) 495001 email [email protected]

Upload: others

Post on 28-May-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

1

DETAILS PROJECT REPORT

FOR

IRON ORE PELLETIZATION PLANT

(CAPACITY-2X1200 TPD)

(2X0.4) 0.8 MILLION TPA

VILLAGE: PARAGHAT

TEHSIL: MASTURI DISTRICT: BILASPUR

CHHATTISGARH

SUBMITTED BY

M/s RASHI STEEL AND POWER LIMITED BF-1,FIRST FLOOR, RAJIV PLAZA

OPP.AXIS BANK- BILASPUR, (CHHATTISGARH) 495001

email [email protected]

Page 2: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

2

INTRODUCTION

PROJECT AT A GLANCE

The Rashi Steel And Power Limited is going for installation of 2xO.4 = 0.8 Million

TPA Palletization Plant, keeping in view the present demand of Steel Plant. The

proposed Steel plant of Rashi Steel And Power Limited is located at Patwari Halka

No. - 38 Village : Paraghat Tehsil - Masturi and DistrictBilaspur, in Chhattisgarh

State.

Name of the Company M/s Rashi Steel and Power Ltd.

BF-1, First Floor, Opp. Axis Bank

Rajiv Plaza-Bilaspur,

PIN - 495001 (Chhattisgarh)

email [email protected]

Phone: 07752-408405

Factory Office Village : Paraghat

Post Office : Jairamnagar

Tehsil : Masturi

District : Bilaspur, (C.G.)

Name of the Directors Sh. Mahesh Gupta

Sh. Rakesh Jindal

Sh. Amar Agrawal

Sh. Ashok Kumar Agrawal

Sh. Ashok Agarwal

Project Cost 15,000.00 Lakhs (150 Cr.)

Page 3: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

3

Product & Production Capacity:

Project Prouduct Existing Proposed Total

2 x 0.4 Million TPA Palletization Plant

Pallet NIL 2x1200TPD 0.80 Million TPA

Location of the Plant : At - Paraghat Village

Tehsil : Masturi

District· Bilaspur, (C.G.)

Coordinates details

Point: A N220 01’ 54.3’’ E820 19’ 23.6’’

Point: B N220 02’ 08.2’’ E820 19’ 25.5’’

Point: C N220 02’ 09.2’’ E820 19’ 42.1’’

Point: D N220 01’ 52.0’’ E820 19’ 38.1’’

Total Land Area : 34.12 Acres

Land for Green Belt : 11.25 Acres (33%of total land area)

Working Days : 330 Days

Raw Materials :

(1) Palletization Plant :

(A) Iron Ore fines - 8,71,200TPA - From open market.

(B) Coal - 22,440TPA - From open market and SAIL.

(C) Bentonite - 11,880 TPA - From open market.

(2) Producer Gas Plant:

(A) Coal - 46200 TPA - From open market and SECL.

Page 4: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

4

Water Requirement

(A) Source : From Bore well and River

(B) Annual Requirement : 1,32,000 KL per Annum (400.00 KLD)

(C) Rainwater harvesting : Will be provided to recharge the ground

water. D.G. Set : 02 Nos. (Less than 500 KVA)

Power Requirement : Source - Chhattisgarh State Electricity

Board (CSEB), Bilaspur District.

(A) Pellet Plant - 4000 KVA

Solid/Hazards Waste & it's Disposal : No Hazardous waste was

generated

(A)Palletization Plant : Iron Ore Fine Dust: 343 TPD /1,13,256 TPA)

Reused in Palletization Plant

Page 5: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

5

PROJECT COST ESTIMATED PROJECT COST:

(ii) Factory Building & Civil Works etc. 3800.00

(iii) Plant & Machinery 7750.00

(iv) Pollution Control Devices 1100.00

(v) Electrical Installation 580.00

(vi) Misc. Fixed Assets 120.00

(vii) Preliminary and Preoperative Expenses 030.00

(viii) Deposits 070.00

Sub-Total 14000.00

Margin Money for Working Capital 1000.00

Grand -Total 15000.00

MEANS OF FINANCE

PARTICULARS AMOUNT IN

LACS

(i) Land & Site Development and 550.00

Infrastructure

PARTICULARS AMOUNT IN

LACS

(i) Share Capital 5160.00

(i i) Unsecured Loan 2640.00

(iii) Tearm Loan 7200.00

Grand-Total 15000.00

Page 6: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

6

OVERVIEW OF THE COMPANY

Preamble: Steel a basic commodity for all industrial activities, quantum of its

consumption is considered an index of industrial prosperity. Since

independence, there has been a substantial growth in the steel sector in India

from 1.5 Million Tons in 1950-51 to about 31 Million Tons at present. Additional

Steel making capacity of about 8 to 10 Million TonsNear exists in the

secondary steel sector. Further, with nearly 20% of the world population,

India's contribution is only of the order of 3.4% of world steel production.

Hence, short term and long term strategies are necessary in planning the

development of the steel industry in the country to improve the level of per

capita steel consumption. It is expected that with the measures taken by Govt.

of India for promotion consumption of iron and steel and expected growth of

Indian economy the requirement of steel will significantly increase and

accordingly the domestic manufacturing capacity needs to be increase.

Considering the potential of iron and steel in India and the experience gained

by the group in this sector, M/s RASHI STEEL AND POWER LTD (RSPL) has

decided to install pallet plant in the state of Chhatisgarh.

Brief Profile: Promoters of the company belong from erudite families of Raipur.

The management of the company believes that "Successful operation,

performance and long term viability of any business depends on a continuous

sequence of sound decision made individually or collectively by the

management team. Everyone of this decisions ultimately causes for better or

worse, an economic impact on the business. In essence, the process

managing any enterprise amounts to making an on going series of economic

choices, every time trading off costs or benefits."

The brief Bio-data of the promoters are given below:

Shri Ashok Agrawal, Promoter/Director

Shri Ashok Agrawal, S/o Late Gajanand Agrawal hails from an illustrious and

prominent family of Chhattisgarh. He is extremely hard working, dynamic and

intelligent businessman. Ashok Agrawal has gained business experience in

last 15 years and presently Director of many companies like Rukmani

Infrastructure Pvt. Ltd., Hotel ANS international Ltd. And also partners in Dadu

Buiders and Developers. Having sharpened his business acumen in the above

referred company, he is being taken in as promoter director in the new venture

of the family.

Page 7: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

7

Mr. Rakesh Jindal, Promoter / Director

Mr. Rakesh Jindal, aged 46 Years, is a Chartered Accountant. He is a

seasoned professional of steel sector and has rendered more then 20 years of

valuable service at Jindal Steel & Power Ltd. (JSPL) in the capacity of V.P.

(Commercial). During his tenure he had handled commercial aspects of various

projects of JSPL. He is quite respectable at higher level in JSPL. He brings with

him immense experience which would be of great help to the company.

Mr. Amar Agrawal, Promoter / Director

Mr. Agrawal, aged 47 years, is a B Com. Graduate. His business interest varies

from Ferro Alloys, Power, and Infrastructure to Logistics etc. He is the key

strategist for the new venture i.e. Integrated Steel Plant. He has extensively

traveled to USA, China & Middle East, Africa etc. He is known for his foresight

ness and resourcefulness. He is presently successfully running a 15 MW

thermal power plant at Raigarh (CG).

Mr. Mahesh Gupta, Promoter / Director

Mr. Gupta, aged 43 years is an Engineer- Mechanical has very vast experience

in Power and Steel Sector. He has good knowledge of the technology for

making steel through sponge iron. He has rendered his services in various

organizations in last 17 years. His last service with Scania Steel & Power Ltd.,

Raigarh as a General Manager, Technical & Production.

Shri Ashok Agrawal, Promoter/ Director

Shri Ashok Agrawal, aged about 43 years is a graduate in commerce, he is

involved In a business of real estate from last 15 years and manufacturing of

cement capsules from last 5 years. His responsibility in this unit to supervise the

production and maintenance of the plant. Since his vast experience in the field

and wide contacts shall have good supports to the unit.

As mentioned above the promoters and key personal are experienced,

energetic and resourceful men with good links. The promoters are also

financially stable and will be able to execute the project successfully and in

specified time and run it profitably and smoothly in future too.

Page 8: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

8

LIST OF DIRECTOR’S

M/s RASHI STEEL AND POWER LTD.

a)

SL. NO. 1 2 3 4 5

DESIGNATION DIRECTOR DIRECTOR DIRECTOR DIRECTOR DIRECTOR

NAME MAHESH

GUPTA

RAKESH

JINDAL

ASHOK KUMAR

AGRAWAL

AMAR

AGRAWAL

ASHOK KUMAR

AGRAWAL

FATER NAME Lt. GIAN

CHAND GUPTA

Lt. ANAND

SURUP

Lt. JAGMOHAN

DAS AGRAWAL

Shri

SATYANARAYAN

AGRAWAL

Lt. GAJANAND

AGRAWAL

CITIZENSHIP INDIAN INDIAN INDIAN INDIAN INDIAN

PAN NO AFEPG0838D ACHPJ2881P ADLPA9437H ADPPA3753Q ACHPA9792L

PASSPORTNO J0219069 H5763011 G7859009 G1014283 G2258565

MOBILE NO 09993520981 07752-408405 07752-408405 07752-408405 07752-408405

EMAIL ID maheshgp70@

yahoo.co.in

rakeshjindal88

@gmail.com

bilaspur@mail.

com

amar.rrenergy@

gmail.com

ashokkumaragrawal@

live.com

ADDRESS

House No. 25,

Ring Road No

2, Mahima

Vihar, Bilaspur

District:

Bilaspur (C.G.)

B-1 Jindal

Nagar, Jindal

Steel & Power

Ltd.

sh-63,

Chhendipada

Road, Nisa,

Jindal Nagar

Post Office,

Angul-759111

Piteshwar

P/34B, Jain

Mandir Road

Kranti Nagar

Bilaspur, C.G.

495001

District:

Bilaspur (C.G.)

krishna vihar,

dhimrapur

chowk,

raigarh-496001

District: Raigarh

(C.G.)

House No. 10/45,

Dabhra Road, Kharsia

496661, Chhattisgarh

District: Raigarh (C.G.)

ADDRESS DETAILS

Corporate Office: Registered Office: Site Office:

M/s Rashi Steel and Power Ltd. M/s Rashi Steel and Power Ltd. M/s Rashi Steel and Power Ltd.

BF-1, First Floor, Rajiv Plaza A-184, First Floor, Meera Bagh Village: Paraghat/Beltukri

Opposite Axis Bank, New Delhi, 110087 Near Lilagar River Bridge,

Bilaspur C.G. 495001 Tehsil Masturi ,Post Off: Jairamnagar,

District: Bilaspur C.G.

Page 9: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

9

PROJECT DESCRIPTION

SALIENT FEATURES OF THE SITE SITE LOCATION

The Rashi Steel and Power Limited is going for installation of 2xO.4 = 0.8 Million

TPA Palletization Plant, keeping in view the present demand of Steel Plant. The

proposed Steel plant of Rashi Steel And Power Limited is located at Patwari Halka

No. - 38 Village: Paraghat Tehsil - Masturi and District - Bilaspur, in Chhattisgarh

State.

The project location is well connected by road and rail. The nearest railway station

is Bilaspur, which is at a distance of 22 km from the site. The nearest airport is

Raipur and sea port is Paradeep - Orissa.

The site was selected based on the following factors

• Nearness to source of main raw materials . r

• Location of consumer center

• Availability of sufficient stretch of land

• Convenient Rail & Road links (plant located near SH)

• Perennial & adequate sources of water supply

• Availability & closeness to source of adequate power supply .

There are no ecological sensitive places like national park, Sanctuary, biosphere

reserves, heritage site, archeological monuments, defense installation, health

resorts, scenic beauty, etc. around 10 kms of the site. There is no route of

migratory animals within the project site.

METEOROLOGICAL DATA

Maximum dry bulb temperature Minimum dry bulb temperature Design dry bulb

temperature Design wet bulb temperature Max. Relative Humidity

Maximum dry bulb temperature : 48 Deg C

Minimum dry bulb temperature : 12 Deg C

Design dry bulb temperature : 35 Deg C

Design wet bulb temperature : 28 Deg C

Max. Relative Humidity : 85 % Min. Relative Humidity : 50 % Design Relative Humidity : 65%

Page 10: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

10

WIND AND SEISMIC DATA

Basic wind speed : As per IS 875

Seismic zone : Zone II As per IS 1893

DETAILS

The Rashi Steel And Power Limited is going for installation of 2xO.4 = 0.8 Million

TPA Palletization Plant, keeping in view the present demand of Steel Plant. The

proposed Steel plant of Rashi Steel And Power Limited is located at Patwari

Halka No. - 38 Village: Paraghat Tehsil - Masturi and District - Bilaspur, in

Chhattisgarh State.

Details of Land - Total avaible Land is 34.12 Acres

The proposed Steel Plant is at National Highway connecting Raipur, Bilaspur NH-

200. A connecting road from the plant site to the highway has been constructed

by State Govt.

LAND AREA STATEMENT

(Total Land Area = 34.12 Acres)

I S.NO. PARTICULARS

AREA in Acres

1 Built up area - 07.00

2 Roads and Drains 05.00

3 Greenbelt and greenery 11.25

4 Parking 01.87

5 Temporary Dump Yard 05.00

6 Open area 04.00

Total Land Area 34.12 Acres

Rail

Project site is connected via S.E.C. Railway line between Raipur and

Rourkela, which is main line between Mumbai and Howrah.

Page 11: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

11

Airport

The nearest civilian airport is at Mana, Raipur, and the capital of

Chhattisgarh at about 120 Km from the plant site.

IMPORTANCE OF PROJECT TO REGION & COUNTRY

Our country has been progressing very fast requiring inter alias, high

production of steel. Steel plays a very important role in improving the economic

condition of any country. Thus, the project will improve the economic condition

of the country to a great extent.

As a result of the proposed project various facilities like educational,

medical and other tangible benefits will enhance in the area. Thus, the project

will greatly improve the economic condition of the area.

JUSTIFICATION OF PROJECT

The project is situated at Paraghat Village; there are no ecologically

fragile areas.

Page 12: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

12

PELLETISATION PLANT (2 X 0.4 MilLION TPA CAPACITY)

INTRODUCTION

The proposed 2 x 0.4 Million TPA Pelletisation Plant will be established based

on the requirement of the raw material for the present established plant.

Considering the scenario in the state and projected requirement of MIs RSPl is

setting up of a 2 x 0.4 Million TPA pelletisation plant. Adequate land is available

for the project. For plant cooling, services and potable water requirement, the

source of water will be from ground water. Product of the proposed plant will be

sold to local market of Sponge Iron Plant and later on for self consumption in

the proposed plant.

M/s RSPL will be implementing the project through loan requirements from

financial institutions and internal accruals and investments from promoters. The

plant. will be executed through package wise system and unit is proposed to be

commissioned in 12 months from zero date.

M/s RSPL is doing in house Engineering & execution as Promoters are

experienced in power sector and has done many projects. M/s RSPL Limited

Engineers will prepare the project report for proposed project.

The DPR covers:-

• Reasons for selection of site.

• Details of clearances and approval.

• Availability of various facilities.

• Technical details of plant & equipment.

• Availability of water, fuel, transportation of water fuel.

• Methodology for evacuation of power.

• Total project cost.

• Financial structure & financial modeling.

Page 13: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

13

PROPOSED PROJECT: 0.8 (2 x 0.4) Million TPA Pelletisation Plant

DETAILS OF SITE SELECTION

Considerations for selection of site

A power station requires a number of basic inputs such as land, fuel, water

etc. for setting up of power station and is primarily governed by the following

basic considerations:

a) Availability of land

b) Rail/road accessibility

c) Availability of fuel and proximity to source

d) Availability of water and proximity to source

e) Load demand and proximity to the grid

f) Environmental consideration

g) Suitability of the land from topography and geological aspects These

factors have been found very favorable to establish and operate the

project.

Land & Site Details & Availability of Facilities

:)

Land selected for this project is coming under Paraghat village, Masturi -Block,

Bilaspur, CG. Required land is already in the possession of M/s Rashi Steel

And Power Limited. Nearest town is Masturi which is around 10 kms from the

project site. Nearest Railway station is Bilaspur which is around 22 kms from

the project site. Commercial Airport is Raipur and

nearest port is Vishakapattanam.

Availability of Land

Adequate land is available in project site. The site terrain is generally plain

requiring minimum efforts to grade them. The land is currently not in use and

there are no inhabitants requiring rehabilitation or resettlement. The topsoil is

clayey soil. Suitable foundation, based on soil investigation results, will be

adopted. Entire land is under the possession of the company.

Page 14: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

14

Details of Land : 34.12 Acres Khasra No. and area is enclosed as issued by

revenue department.

a) Accessibility

The site is around 7 kms from National highway-connecting Raipur to Bilaspur

NH 200 . Bilaspur is at a distance of 22 kms from the proposed site. As such

there is no problem in accessibility and transportation of heavy equipment to

site by road.

b) Finished Product:

In Bilaspur area sponge Iron plant is situated about 25 km. radius from RSPl

plant site, which is at a distance of around 25 km by road. Finished product of

pelletisation plant will be utilized in the sponge iron division as raw material.

later on in own Sponge Iron plant which is under consideration.

c) Water Requirement

Requirement of raw water is estimated as 400 m3/day only. The required water

will be from surface water i.e. from near by River and ground water also.

d) Power Requirement The power requirement for the plant will be around 4 MW.

e) Environmental Consideration

The land for the proposed pelletisation plant site is already in possession of MIs

Rashi Steel And Power Limited. The site will be developed based on the

recommendations of the state environmental authorities, as well as the

guidelines of MOEF. Suitable provisions will be incorporated in the design of

buildings, structures, and selection of equipment so that there are no adverse

effects due to emissions, noise, and contamination of soil, water and air.

Page 15: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

15

PELLETISATION PLANT (2 X 0.4 MILLION TPA CAPACITY) Manufacturing Process of Pelletisation Plant

The grinding process is adopted to improve granularity constitution of

concentrated iron ore and make material fully blended and grinded so that it

can be suitable for palletizing. The sophisticated disc palletizer is adopted to

reduce circulating load and improve utilization efficiency.

The characteristic of grate-annular cooler production process is as follows:

(1) Drying and preheating roasting and cooling proceed in grate kiln and

annular cooler respectively so its equipment is sample and reliable and

product quality is even.

(2) The equipment of roasting system with high adaptability to raw material

can be individually controlled and flexibly regulated.

(3) The consumption of fuel is low and power low as well.

The advanced air flow system is adopted, which fully reclaim-and utilize

sensible heat of high-heat flue gas from annular cooler reduce heat rate of

pellet with maximum utilization of heat energy. The main production process is

controlled by PLC with high automatically. Exhaust gas with dust is purified

and discharged by static de-duster to protect environment. Returned material

and dust arrested are sent to stock yard and damp mill so as to resources can

be fully re-utilized.

PRODUCTION FLOW AND WORKSHOP CONSTITUTION:

Main Workshop:

The main workshop of this pellet production line stockyard proportioning room

drying room damp mill room pelletizer room grate oven building (including

screening and distribution of green pellets), rotary kiln annular cooler air flow

system spillage return system (including spillage lifting) fuel preparation room.

Page 16: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

16

Stockyard and Proportioning System

A stockyard has storage capacity sufficient amount of concentrated iron

ore. Concentrate iron ore piled open in the stock yard and is delivered to a

receiving bin by the help of shovel cars. It is then extracted from the bottom

part of the bin with the help of vibrating feeder, and then transported into

proportioning bunkers by a reversible belt conveyer. There are two

bentonite receiving bin in the stock yard and 4 proportioning bunkers for

concentrate iron ore. The bentonite is charged by man. The four nos. of

concentrate proportioning bunkers can store iron ore for 8 hour usage. Two

bentonite bin with the capacity of 15 m3 can store usage. Under these

concentrate bunkers, belt scales are equipment for feed proportioning and

by means of frequency speed control of the belt, feed amount of

concentrate iron ore can be regulated. Under the bentonite bin, a weighing

machine is mounted for batching. The speed ratio is controlled by

computer.

Drying Room:

This is a drum like structure of dimension 3x20 m for drying purpose.

Mixture of proportioned concentrate and bentonite is sent to drier drum for

the purpose of heating and drying with the help of flue gas with temperature

of 700°C supplied by a combustion furnace. After heating the end gas with

a temperature of 1200°C is discharged through the chimney. The initial

water content of the mixture is about 11.0% and after drying it comes to

7.0~8.0%.

The dried mixture is then discharged through a chute to a belt conveyer, and

then transported to damp grinding room. The drier has normal processing

capacity of 90 tons per hour.

Grinding Room:

In normal state, the dried blended mix is distributed to belt conveyor by disc

Page 17: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

17

feeder and conveyed to a blended bin located at damp mill room by belt

conveyer. Then it is filled into the damp mill through a charging conveyer for

mixing, homogenizing and grinding. The grinded material is transferred to a

pallefizin9 belt and then to a blending bin at palletizer house.

Palletiser House:

Dimension of palletiser house covers 15x34.4 m2• The mixture is sent to upper

part of the pelletiser house by belt conveyor then separately discharged to three

bins with level gauges. Each blended mix bin has an effective content of 60 m3

under them tight type belt conveyor are laid respective to 36.0 m disk palletiser.

The speed of tight type belt conveyor can be regulated by a frequency variable

controller, and their speed is matched with that of disk palletizer. Each palletiser

has a production capacity of 50 T/hr. Generally during normal operation two

sets are in operation and the third one is on standby. During palletizing an

amount of water is added to the mixture so that it can have optimal water

content for palletizing. Green pellets from the palletizer are collected and

shipped to screening and distribution system through palletisation belt.

Grate Oven Building:

The green pellets screening & distribution system is composed of spillage

return conveyor. The shaking conveyor evenly distributes the green pellets

transferred by palletisation belt to the conveyor oversize ball roll screen. The

oversize green pellets (>16mm) on the screen are gathered by return conveyer

and transferred to blending bin in palletizer house for re-palletizing. The green

pellets below 16mm in size are transferred to the roller conveyer screen by the

frequency controlled wide belt. Through these two screens, green pellets

between 8-16mm in size are distributed onto receiving area of the oven,

However the pellets below 8mm under the roller conveyer screen are gathered

by return conveyer for re-palletizing.

Grate oven

The plant building for grate oven covers 14 x 59 m2 and the effective width and

length of grate oven is respectively 2.8m and 36m, the depth of pellets

Page 18: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

18

distribution on the grate oven bed is 120-180mm. The grate oven is divided into

four chambers from inside with whole preheating section I, II.

Blast drying section I

In this section circling hot air is at about 150°C. Mixed air is blast through pellet

bed, so that circulating hot air at dewatered and get dried. The main heat

source is wasting heat from section III of annular cooler. The air can be give out

directly a lot of steam and mini-dust.

Downdraft drying section

In this section circling hot air at about 300°C mixed with air is downdrafted

through pellet bed so that the green pellets are dried further. The main heat

source is wasting hot air from preheating section I, II. The wasting hot air collect

main pipes in the side blast box and the give through static de-duster, main

draught fan and chimney.

Preheating section I

The hot air from annular cool section II connects the preheating section I by hot

air pipe. The lacking heat is supplies by hot air from preheating section II to get

the hot air temperature of 900°C.

This preheats the pellet from the downdraft section. The wasting hot air is

collected by collecting main pipe in the side blast box and into h) Preheating section II

In the preheating section II, pellets are further heated under hot air of 1100°C,

at the same time partially become hardened. These partial hardened pellets

can bear the impact of drifting-down from grate oven to rotary kiln, and will not

break during rotation of the kiln. Heat sources in this section comes from hot

flue of the kiln tail, end the lacking heat is supplied hood of the section, a flue

and a relief valve are fixed for the lacking heat is supplied hood of the section,

a flue or additional burner. Over the top part of furnace hood of the section, a

flue and a relief valve are fixed for baking furnaces and emergency operation.

Page 19: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

19

Green pellets dried and preheated totally about 28 minutes, with enough

strength, are sent into the rotary kiln by way of a shovel and a chute at tail end

of the kiln.

Rotary kiln

The kiln is supported by 2 lintel girders. Compound precast bricks and high

strength heat insulation castable are resistance to wear and thermal insulation,

which can decrease temperature of the kiln's surface and extend its working

life.

The preheated pellets are loaded at feed end of rotary kiln by a shovel and

chute. A special designed collapsible spray gun is mounted at kiln discharge.

Combustion intensity and flame profile can be regulated by means of extension

and contraction of the collapsible spray gun as well as adjustment of blast

volume. Roasting temperature in the kiln is 13001350 °C and rotating speed

and position of the kiln can be controlled. The discharge hood is sealed by a

device, which is protected by a structural cooling blower.

Annular cooler

The baked and roasted pellets from rotary kiln, fall into the receiving bin

(capacity-50m3) of annular cooler through the kiln discharge hood. And then

leveled off on pellets cars of the annular cooler by help of a roller pusher and

cooled by air blast. Its processing capacity is 80t/h, while its cooling time is

around 45 minutes at a normal depth of 680-760 mm of pellets. The annular

cooler is divided into three cooling sections, each equipped with cooling fans,

partition wall and the receiving bin.

The fume hood of the cooler is divided into four areas. In the area i.e. blowe air

to chills the pellets and its heated to 1000-1100°C then directly returns to the

rotary kiln through the kiln discharge hood over the receiving bin and the

parallel fume duct. This hot fume is used to increase temperature and oxygen

content of kiln and change the flame profile from the spray gun. In the second

area, i.e. section II cold blasted and further cools the section I at the same time.

Page 20: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

20

The temperature increases to 400-600°C then is right led to drying section I of

the grate oven via a hot air pipe, for further drying and preheating of green

pellets. In section II & IV, the pellets should be cooled to 1500°C and collected

by a buffer bin and then sent out by a heat resistant belt conveyer. Air

temperature in cooling section III is 35000C and is introduced to Drying

Section. Air temperature in cooling section is at 90-100 °C and fume is directly

freed through the chimney of the annular cooler. Blast volume of blowers is

automatically adjusted by a throttle installed in the blast inlet, which is used to

control hot air temperature, so that the most part of heat volume recovered

from pellet cooling can be utilized for palletizing production process.

Air flow system

The air flow system of roasting system including: cool blower hot air circling

and hot air disposal. Circling cool air is the main air source. The air cool the

hot pellets, on the annular cooler and become hot. This hot air from annular

cooler section 1 is used as the second air of rotary kiln and lead to rotary kiln

through hot air pipe directly.

The hot air from annular cooler section II lead to great oven preheating

section I. 'Hot air circling' is the process in which waste hot air grate oven

preheating section I, II to blower drying section and downdraught drying is that

wasting hot air of downdraught drying section give out through static de-

duster and main draught fan and chimney. The dust content off wasting hot air

is less than 50mg/Nm3, the dust collected by multi-cyclone and static de-

duster is returned to damp mill room through spillage system.

The materials conveyer by spillage includes dust collected by process de-

duster and environment de-duster, dust collected by grate oven dust box,

broken and Jacking pellet collected by lower grate bed lacking pellet under

scriber plate, dust collected by charging & discharge end of rotary kiln. The

spillage will regrind in damp mill room through scrape and heat-resistant belt

conveyer and make ball again. Dust lacking pellets, broken pellets are

collected from side blast boxes. Lower grate bed and end funnels, then sent

to a duty vibration sieve for grading. Over 8mm pellets will be delivered to the

Page 21: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

21

kiln charge chute by a heat resistant bucket elevator .

Fuel:

The various types of fuels like liquid, solid and gaseous fuels are available as

a heating source in industrial use. The selection of right type of fuel depends

on various factors such as availability, storage, handling, pollution and landed

cost of fuel. Keeping the pollution status of proposed Pelletisation plant, Coal

Gas has been selected as heating fuel in the process. The knowledge of the

fuel properties helps in selecting the right fuel for the right purpose and

efficient use of the fuel.

Storage of Coal I Furnace Oil

Coal will be stored in covered shed with pucca platform. Bag filter will be provided to

control the fugitive emission.

It can be potentially hazardous to store furnace oil in barrels. A better practice is to store it

in cylindrical tanks, either above or below the ground. Furnace oil, that is delivered, may

contain dust, water and other contaminants.

The sizing of storage tank facility is very important. A recommended storage

estimate is to provide for at least 10 days of normal consumption. Industrial

heating fuel storage tanks are generally vertical mild steel tanks mounted

above ground. It is prudent for safety and environmental reasons to build bund

walls around tanks to contain accidental spillages.

As a certain amount of settlement of solids and sludge will occur in tanks over

time, cleaning should be carried out at regular intervals annually for fuels. A

little care should be taken when oil is decanted from the tanker to storage tank.

All leaks from joints, flanges and pipelines must be attended at the earliest.

Fuel oil should be free from possible contaminants such as dirt, sludge and

water before it is fed to the combustion system.

The physical properties and chemical composition of the raw material and fuel

used in production, and those of finished product must be checked in

Page 22: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

22

accordance with those items list.

The following are the major raw material required for the manufacturing of

Iron Ore Pellets.

1) Raw Material- Hematite Iron Ore fines 2) Binding Material - Bentonite.

3) Coal.

RAW MATERIAL DETAILS

The following are the major raw material required for the manufacturing of iron ore

Pellets.

1) Raw Material- Hematite/Magnetite Iron Ore fines

2) Binding Material - Bentonite.

3) Fuel- Coal

Iron Ore fines: Fe (T) : 64 ± 1% Si02 : 0.85 Max. Al2O3 : 1.80 Max. S : 0.01 Max. P : 0.05 Max. Size : 200 mesh

Bentonite:

Si02 : 66.70%

AI203 : 28.30%

CaO : 1.50%

MgO : 3.50%

H20 : 5.00%

Coal: Fixed carbon : 45% plus.

Volatile matter : 35% plus.

Ash : 35 to 45%.

Sulphur : 0.1 max.

G.C.V : 3500 (k.cal/kg)/min

Ash fusion temperature: 2000 °C/1600 °C (min)

Size : 0 to 300mm/200mm.

Page 23: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

23

Moisture : 10 to 15 % max.

Raw Material Requirements

Unit Raw Material

Raw Material Required Per Day (T)

Raw Material Required Per Month(T)

Raw Material Required Per Annum 330 Days (T)

Pelletization Plant (2x1200 TPD)

Iron Ore Fines

2640 72600 871200

Bentonite 36 990 11880 Coal 68 1870 22440

Material Balance (Iron Ore Pelletization Plant)

Solid Waste Details & Management Plan (Iron Ore Pelletisation)

There is no as such Solid Waste Generated, because the waste

generated is reused as input with fresh charge.

Power Requirement:

Total Power requirement for the Pelletisation plant will be around

4.00 MW

Manpower Requirement:

Total Manpower requirement for Iron Ore Pelletisation Plant will be

90 persons.

Input Output Iron Ore Fines 1.1000 Tons B.F. Sinter 1.0 Tons Coal 0.02883 Tons Input Return Fine

Dust 0.143 Tons

Betonite 0.0150 Tons Total Input 1.143 Tons Total Output 1.143 Tons

Page 24: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

24

TYPICAL FLOW DIAGRAM OF IRON ORE PELLETIZING PLANT

Page 25: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

25

TECHNICAL ASPECTS CIVIL WORKS:

This proposed project envisages various civil works related to complete plant

apart from other facilities like construction of road, culverts, rest house, canteen,

water works etc. Further there is no past history of flood in the area. The project

also provides, in view of socio economic development of the surrounding

areas/villages, construction of roads, culverts, Primary health centre, School,

Community Hall, Water works etc as per requirement.

SOIL FOUNDATION SYSTEM

Detailed geo-technical investigation in the area of the proposed plant shall be

carried out by contractor before the execution of the project. It is assumed that

normal soil conditions will be encountered in the proposed area. Accordingly,

all major foundations will require pile foundations.

MAIN PLANT BUILDING CIVIL AND STRUCTURAL:

Roof of hall, de-aerator bay, bunker building and control tower shall be

provided with colour coated metal deck sheet over which an RCC layer shall

be provided. For all other areas cast-in-situ RCC slabs I metal decking shall be

provided based on the type of framing arrangement adopted. Roof of hall roof

skylight with leak proof polycarbonate with anodized aluminum frame of

approved colour shall be provided with for Natural Light. Intermediate floors of

all building including building shall be provided with cast-in-situ RCC

slab/gratings floors.

Control Room area shall have Brick wall on external face, over which un-

insulated single Metal Cladding shall be provided. ESP, Control Room Building,

Air Washer Building and all other facilities buildings shall be of RCC I Steel

frame structure within-fill Brickwork I Insulated Metal Cladding.

ARCHITECTURAL CONCEPTS

Layout of the plant area shall have definite hierarchy of road network ;

Page 26: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

26

depending upon its usage, aesthetic, visual sensibilities for creating road vistas,

focal points, building back drops, building frames. General layout shall be

evolved taking over the basis of landform & local climate and due consideration

shall be given to orientation & wind direction. Overall emphasis shall be on

developing eco-friendly architecture, merging with the nature with its own

sustainable energy management systems .

STRUCTURAL STEEL WORKS MAIN POWER HOUSE:

This shall be multi span-framed structure consisting of structural steel columns,

beams and trusses. The building shall be braced in longitudinal direction and

moment resistant in transverse direction.

CHIMNEY

A reinforced concrete I MS chimney of 60 m height with steel liner shall be

provided for the project. The liner shall essentially be constructed from

structural steel and shall be of the hung type (with multiple point liner support

systems). The liners shall be provided with resin bonded wool type thermal

insulation. The portion of the liners projecting above the chimney roof,

however, shall be constructed of stainless steel liners over the roof slab of the

chimney. Internal platforms shall be provided for enabling access to various

elevations of the stack and to provide support to the steel liner. External

platforms shall also be provided.

COOLING WATER SYSTEM:

The proposed CW pump house shall have five numbers CW pumps (4

working and 1 standby). The substructure shall be of M-25 Grade of RCC. The

superstructure shall be of structural steel framework in-filled with brick

cladding and I or with RCC framework in-filled with brick cladding.

The water is pumped from the pump house to the condenser through steel

lined concrete r encased pipe for each unit. Hot water from condenser shall

also be conveyed through a similar pipe of same size to induced draught

cooling towers.

Page 27: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

27

The cooling towers (2 Nos.) shall be of induced draught type, which includes

cooling water basin made up of RCC of grade M 25 with suitable foundation

system.

The cold water discharge from cooling tower shall flow by gravity to the CW

pump house fore bay through RCC open channel. The concrete grade for the

open channel shall be M25. All gates, stop logs and trash racks shall be of

structural steel, which shall be hot double dip galvanized and I or epoxy

painted.

A firewater tank and pump house shall be provided. Superstructure of the pump

house shall be of ReC with in-filled brick masonry a panel wall. Foundation for

firewater tanks shall also be provided.

CRUSHER HOUSE

Crusher house shall be of structural steel with permanently colour coated steel

sheet cladding. Floors and roof slabs shall be of RCC. Crushers shall be

supported on RCC deck slab, which in turn will rest on Vibration Isolation

System consisting of springs & dampers. IPS flooring has been considered for

floors.

AUXILIARY' ANCILLARY BUILDINGS D.G. SET BUILDING:

A single storey D.G. Set building of suitable area and height is envisaged to

be constructed for this plant,

EFFLUENT TREATMENT PLANT

Water required in this process is totally consumed and no waste water is

generated from the process. Water required for dust suppression at handling

plant will also evaporate which leads to zero generation of waste water.

ROADS, DRAINS & SEWERAGE ROADS:

All roads for the complete plant area shall be provided. All works related to

maintain continuity of road system shall be constructed in addition to approach

roads to different buildings' facilities related to storage, equipment areas where

Page 28: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

28

access is necessary from inspection and operation and maintenance point of

view as well as functional point of view.

DRAINS

Drains shall be constructed on both sides of roads. In a well planned manner as

well as integrated with the existing drain facilities overall grid system of main

drains l artillery drains are to be provided , designed to dispose off by gravity to

the main drain.

SEWERAGE

R.C.C. concrete pipes' C.1. pipes shall be used for sewage disposal and t or to

be extended to the existing system to match the future requirement. Extended

aeration type permanent sewage treatment plant shall be provided for

treatments of sewage disposal system including Central Monitoring Basin

(CMB) as per applicable local bylaws l environmental standard l conditions of

State and l or Central authorities.

AUXILIARY STEAM SYSTEM

Boiler will be provided with two auxiliary PRD stations i.e., high capacity and

low capacity PRDS taking their steam tap-offs from MS line and CRH line

respectively. The high capacity auxiliary PRDS will be designed so as to meet

total auxiliary steam requirement 'of one (1) unit plus start up requirement of

other unit. Low capacity auxiliary PRDS will be sized for normal requirement of

its own unit.

Auto -changeover between the low and high capacity aux. PRDS stations

depending on the station auxiliary steam requirement is also envisaged. Each

unit will have its own auxiliary steam header whereas for station services a

common station auxiliary steam header is also proposed. A high temperature

station auxiliary steam header taking its tap off from the auxiliary PRD station

before the de-superheater will also be provided, to take care of the mill fire

fighting and air heater soot blowing.

Page 29: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

29

ELECTROSTATIC PRECIPITATOR

ESP with high efficiency will be used to limits the outlet emission to 50 mg/Nm3

and will be designed and modified later as per the desired requirement.

ESP transformer rectifier sets will use high fire point oil as the cooling medium.

The dust collection hoppers at all strategic locations will have a minimum

storage capacity of eight (8) hours. The hoppers will have heating

arrangements to prevent ash sticking to the sloping sides and down pipes.

Level indicators to indicate and trip the ESP in case of high ash levels in the

ash hoppers, which will jeopardize the safety of ESP otherwise.

ENVIRONMENTAL & EFFICIENCY CONSIDERATIONS

In order to meet the environment norms and maintain the sustained efficiency of

ESP, it shall be adequately designed with sufficient margins for all operating

conditions. The Electrostatic Precipitator Management System (EPMS) in

conjunction with opacity monitor shall continuously monitor and maintain the

optimum energy level to achieve higher efficiency of ESP. For obtaining the

sustained high efficiency and availability of other equipment, it shall be

designed for low NOx formation by adopting the appropriate burners, high

efficiency at part load, flexibility to fuel within the range specified, quick startup

and two shift operation capability, adequately sized furnace for burning and low

flue gas velocities to minimize erosion.

WATER SYSTEM & PLANT UTILITIES: WATER PRETREATMENT

PLANT

It is proposed to construct raw water pump house near CW pump house. Raw

water pumps shall be provided to feed to water pretreatment plant before using.

The pre-treatment plant would be designed to remove suspended/colloidal

matter in the raw water.

FIRE PROTECTION SYSTEM

A comprehensive fire detection and protection system is envisaged for the

complete plant. This system shall generally be as per the recommendations of

Page 30: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

30

TAC (INDIA)/IS: 3034 & NFPA - 850. The system shall have various types of

protection systems at each required stages. Complete Instrumentation and

control system for the entire fire detection and protection system shall be

provided for proof safe operation of the complete system.

AIR CONDITIONING SYSTEM

Air conditioning system shall be provided for all those areas, which require close

control of environment conditions and shall cover the following areas:

Main plant area

Control rooms

Control equipment rooms

Telecommunication rooms

Microprocessor, Computer and programmers rooms

Data Storage rooms

UPS Rooms

Instrumentation Laboratory and Steam & water analysis rooms

Conference room

Shift Charge Engineer's room

AVR Room and inverter room.

Generator Exciter panels room (if applicable)

Relay rooms

Required areas in Administrative building.

Control room, water and fuel analysis room, instruments room, ESP etc.

Page 31: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

31

VENTILATION SYSTEM

Ventilation system shall be designed to supply fresh outdoor air and shall be

selected for maintaining inside conditions for those areas where close control of

temperature is not required, but nevertheless have a stipulated maximum

temperature.

CONTROL & INSTRUMENTATION SYSTEMS:

The function of the Control & Instrumentation System would be to aid the

operator in achieving safe and efficient operation of the units, resulting in cost

effective power generation with optimum fuel consumption and reduced

emission levels. The C&I system would be of the type which normally relieves

the operator of continuous duties and would take pre-planned corrective actions

in case of process drift or if unsafe trends or conditions develop in any regime of

operation viz., startup, shutdown, normal working and emergency conditions.

The design of C&I system would be such as to permit on-line localization,

isolation and rectification of fault in the minimum possible time.

DDCMIS SYSTEM

In line with current practices, microprocessor based digital control, monitoring &

Information System would be provided for the safe, reliable and efficient

operation of the equipments and their auxiliaries.

POWER SUPPLY SYSTEM (UPS SYSTEM)

To provide AC & DC power supplies to various C&I systems under SG, TG &

BOP C&I systems, following power supply has been envisaged in line with

present practices.

i. Uninterrupted Power Supply (UPS) system to feed AC load system,

backup secondary instruments, communication system, etc. The UPS

would consist of chargers, inverters, batteries and distribution boards.

EMERGENCY POWER SUPPLY SYSTEM:

For the safe shutdown of the plant under emergency conditions, i.e. in case of

Page 32: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

32

total power failure, diesel generating sets shall be installed for lighting, essential

air conditioningl ventilation and all auxiliaries necessary for baring operation of

main turbines. One no. DG set of suitable capacity has been envisaged for

each unit. One 415V emergency AC board would be provided for each unit.

This emergency board will normally be fed from the associated 415V AC unit

switchgear and DG set will fed power to it in case of AC failure. One No. stand

by DG, common for both the units shall be provided. Cable interconnections

shall be provided from DG to respective unit emergency switchgear.

STATION LIGHTING SYSTEM

Adequate lighting arrangement shall be made for the entire power plant area,

employing distribution boards and lighting panels. Lighting fixtures would be of

HPSV and fluorescent type for AC lighting and of incandescent type for D.C.

lighting. Normal lighting of the plant will operate with the station AC supply.

About 200/0 of these fixtures will also have arrangement for being fed from

Emergency A.C. supply on failure of station A.C. supply. Emergency D.C.

lighting, which will normally be off, would be provided for all strategic locations

in the main plant area and balance of plant area.

COMMUNICATION SYSTEM

For effective communication within and outside the plant, an

intercommunication system will be provided and distributed throughout the

plant. The major components of the system are:

a) EPABX and intercom

b) Telephone system (P&T lines)

c) Public address system

CONSTRUCTION POWER

The construction power required for the construction of the power plant wiI be

derived from the nearest CSEB's 33 kV source as per the requirement in a

Page 33: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

33

phased manner.

PUBLIC ADDRESS SYSTEM

Public Address (PA) system provides two channel voice communication with

"paging" and "private" modes. It consists of central control cabinet;

microphones, handset stations, loud speakers and amplifiers for transmitting of

acknowledging messages distributed at all important locations within the plant

area.

ENVIRONMENTAL POLLUTION CONSIDERATION

Every industry creates pollution up to certain extent. Raw material handling,

finished product handling industrial process becomes sources of pollution.

Environmental considerations, therefore, have a major bearing in the planning of

any project.

SOURCES OF POLLUTION

The major sources of pollution from a project can be classified under the following

heads:

Pollutants in the waste gases namely, suspended particulate matter (SPM),

sulphur dioxide, NOx, Carbon Monoxide & Hydrocarbons (HC) etc

Fugitive dust generated during solid fuel handling and processing.Fugitive dust

generated during conveying, storage and disposal etc.

Thermal pollution

Noise pollution

Waste water and sewage

The various measures proposed to mitigate the impact of these pollution sources

on the environment are discussed below:

Page 34: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

34

POLLUTION CONTROL MEASURES AIR POLLUTION

High efficiency electrostatic precipitators (ESPs) will be installed to limit the

particulate emission to 50 mg/Nm3 in line with the State Govt. Policy. To facilitate wider

dispersion of remaining particulates and gaseous pollutants (SO2 and NOX), a chimney of

suitable height will be provided. The chimney will be provided with personal

access for monitoring of stack emissions.

For control of fugitive dust emissions within and around the raw material handling and

finished product handling areas, dust extraction and suppression systems would be

provided. Dust suppression system shall be installed at all requisite points in the plant.

WATER POLLUTION

An effluent management scheme, consisting of collection, treatment,

recirculation and disposal of effluents, shall be implemented in order to optimize

the make up water requirement as well as liquid effluent generation. The details

of water system for the project is described as follows:

• Neutralization of D.M. plant regeneration waste and disposal through;

Central Monitoring Basln.

• Recirculation type C.W. system with induced draft cooling towers, with

C.W. blow down from cold water side to ensure that there is no thermal

pollution.

• Filling firewater storage tanks.

NOISE POLLUTION

The major noise generating sources are those pumps, fans, handling plant etc.

from where noise is continuously generated. Acoustic enclosures shall be

provided wherever required to control the noise level below 75 dB (A). Wherever

it is not possible technically to meet the required noise levels, the personal

protection appliances shall be provided.

Page 35: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

35

SOLID WASTE MANAGEMENT

The solid waste management scheme for solid waste generated from project

shall involve collection, supply to entrepreneurs for utilization, promoting solid

waste utilization and safe disposal.

ENVIRONMENTAL MANAGEMENT PLAN CONSTRUCTION PHASE Air Environment

The installation of plant during construction phase would result in the increase of

SPM concentrations due to fugitive dust. Frequent water sprinkling in the vicinity of

the construction sites would be undertaken and will be continued after the

completion of plant construction, as there is scope for heavy truck mobility. It will be

ensured that both gasoline and diesel powered vehicles are properly maintained to

comply with exhaust emission requirements.

Noise Environment

There will be marginal increase in noise levels during construction phase, which is

temporary. No construction activities are planned during night time, which may

contribute to the existing baseline.

Water Environment

During construction, provrston for infra-structural services including water supply,

sewage, drainage facilities and electrification will be made. The existing toilet

facilities will be available for the workers to allow proper standards of hygiene.

These facilities are connected to a septic tank and soak pits. Waste water drainage

system of the plant is well connected to the sewerage channel.

Land Environment

Generally cutting of herbaceous vegetation, during the construction phase results in

Page 36: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

36

the loosening of the top soil. There is no such removal of vegetation in the proposed

site. Further plantation measures would help in preventing soil erosion.

Any hazardous material required for constructional activity will be sorted as per

safety norms. Further construction site will be provided with suitable toilet and

treatment facilities etc for maintaining hygienic conditions.

Socio-economic Environment

Any construction activity will benefit the local population in a number of ways. The

company management shall give preference to local people through both direct and

indirect employment. It shall provide ample opportunity to the locals to up-lift their

living standards by organizing events that propagate mutual benefits to all, such as

health camps, awareness campaigns, donations to poorer sections of society and

downtrodden. Educational needs of the region should be improved by encouraging

the workers to allow their children to attend schools. Sufficient funds shall be

allocated for these and other emergency needs. Compensation packages to the kin

of those workers who loose I disable their working ability due to any accident.

Safety and Health

Adequate space will be provided for construction of temporary sheds for

construction workers for rest purpose. M/s. Vandana Global Limited. Raipur will

supply potable water for the construction workers. The safety department will

supervise the safe working of the contractor and their employees. Work spots will be

maintained clean, provided with optimum lighting and enough ventilation to eliminate

dust/fumes. A comprehensive Occupational Health and Safety management plan is

put in place to address any sort of eventuality.

OPERATIONAL PHASE Air Environment

The dust generated from the various conveyors points, crushing etc, will be

controlled by covering the conveyor belt and approaching the transfer points

Page 37: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

37

and then installing one centralized dust extraction system which extract all the

dust from various points. These dust later be trapped by ESP .

Noise Environment

The following are the noise control measures proposed to be undertaken in the

proposed plant.

• Provision of acoustic dampeners in foundations and insulators at high noise

producing equipments and machnies,

• A thick greenbelt will be developed all around the plant boundary to act as

noise attenuator.

• In addition personnel working near high noise level generating sources will

be provided with ear muffs.

• Proper and suitable acoustic barrier will also be provided around areas

generating high noise to maintain noise levels below 90 dB (A).

• Effective preventive maintenance and vibration measurement of all rotating

equipment will help in the improvement of plant life and also noise

reduction.

• Automatic door enclosures for control room and laboratory etc

Water and Wastewater Management

An effluent management plan will be implemented with collection, treatment,

recirculation and disposal of effluents. Rain water will is collected and

recharged through a recharge tank .

• Storm rain water drainage will be routed through a silting tank, for arresting

of silt. Rain water will be used during the rains for the purpose of the plant

water requirement.

Page 38: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

38

An independent plant affluent drainage system is proposed to ensure that

plant effluent doesn't contaminate storm water drains. After individual

treatment of effluents, these will be disposed off through a central monitoring

basin. Efficient operation of various treatment schemes will be ensured to

conform quality of treated effluents to relevant discharge standards.

The sewage from plant will be directed to STP. The capacity of STP will be

adequate and the treated effluent would be either utilised for plantation

purposes or will be discharged.

Storm Water Management

Underground sewers are preferable to collect the storm waters, storm waters

of open road drains are often misused as open sewers for the discharge of

industrial and domestic wastewater and as well as dumps for disposal of solid

wastes. Further more, it creates obstacle to the access of industries.

In general, the storm water run-off is often polluted through dust, garbage and

unprotected solid wastes. Hence, primary treatment in setting tanks is

essential in order to minimize the pollution to a significant level before the

disposal of these waters into natural environment.

Rainwater Harvesting

Underground sewers are preferable to collect the storm waters, storm waters

of open road drains are often misused as open sewers for the discharge of

industrial and domestic wastewater and as well as dumps for disposal of solid

wastes. Rainwater Harvesting technique will be adopted by the industry as per

guideline of the MoEF and CGWB.

Solid Waste Management

The disposal of solid waste is planned by utilising safe and scientific procedures its

handling, storage and disposal activities. Solid waste generated will be disposed

safely through a well planned handling and cisposal management plan.

Page 39: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

39

Few measures are further elaborated below, which would promote sustainable

development in this expansion activity.

i. Water blanket will be maintained over material heaps, and other dust

ii. Thick green belt will be developed all around the periphery of the plant and

some free areas within the premises so as to reduce the pollution and improve

the aesthetics of the area.

iii. Adoption of good house-keeping measures shall be the company's

commitment for a pollution free environment. One of the measures that is

proposed by the company is to install a separate electric energy meter for

monitoring the electrical consumption of ESP and its statistics shall be made

available on monthly basis for any energy audits in future.

Green Belt Development

The plan for attenuation of the noise and air pollutant levels includes design for

plantations around the plant boundary, roadside, office buildings and stretches

of open land. The vegetation for the attenuation of air pollution shall be most

needed in the areas where ground level concentrations of the pollutant are to

be highest. 33% plantation will be carried out, by consultation with DFO

Bilaspur of State Forest Department according to guideline of MoEF and

CPCB.

Occupational Safety & Health Management

The proponent will provide all necessary provisions stipulated under The

Factories Act. In addition a Safety committee has been formed and manned by

equal participants from Management and Workers. Personnel Protection

equipment (PPE) is being issued to each worker. Other safety equipments shall

be used according to the nature of job involved. A detailed structure of risk

analysis is already presented in previous sections in this chapter.

Page 40: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

40

POST OPERATIONAL MONITORING PROGRAM

Regular monitoring of pollutants in different environmental disciplines like air,

water, noise etc will be conducted for proposed units and the data will be

regularly submitted to Chhattisgarh Environmental Conservation Board.

INSTITUTIONAL SET-UP

The post operational monitoring program will be under the supervision of the

Environmental Management Group (EM G) at the project site. The EMG at site

will interact with state Environment Conservation Board for all environmental

related issues during operation of the station.

STATUTORY CLEARANCES

A comprehensive study is in process to prepare Environmental Impact

Assessment report for this project. After receipt for No Objection Certificate

from Chhattisgarh Environmental Conservation Board, Ministry of

Environmental & Forests will be approached for obtaining Environmental

Clearance. This will be in accordance with the procedure laid down in the EIA

Notification 2006 and its subsequent amendments.

PERFORMANCE GUARANTEES

The plant and facilities will be designed, engineered, manufactured, tested,

erected and commissioned ensuring compliance to international standards

and incorporating state of the art technology. Quality assurance programs will

be implemented meticulously to ensure high quality for the equipments and

systems. At every stage right from the selection of raw materials till

conductance of performance guarantee tests, inspection shall be carried out

at every stage of manufacture and tests such as type tests and routine tests

will be carried out on the components, equipment and systems so as to

ensure that the plant will give integrated optimal performance. While it is not

the intent to elaborate all the inspection, testing and performance guarantee

Page 41: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

41

tests involved, the following specific guarantees will be adhered to:

a. Design of plant and equipment as per Indian and or international

applicable standard like ISO, ASME, ASTM, IEC, DIN, JIS standards

etc.

b. Establishment of equipment ratings as per the detailed design through

international acceptable test procedures.

c. To comply with the applicable statutory rules and regulations.

d. To follow the stipulated health, safety and environmental requirements

e. Compliance of all applicable environmental codes, standards and

regulations in vogue as on date including.

o Particulate emission within 50 mg/Nm3 under all conditions.

o Sulphur emission within the prescribed limits of CPCB norms.

o To maintain effluent discharge within permissible limit.

PERFORMANCE MONITORING SYSTEM

The operation of this project will be optimized by following the performance

monitoring system. This system covers organizational structure and clear

definition of responsibilities of all key personnel detailed analysis of 0 & M

problems. It also covers the system of daily reporting and periodic review and

monitoring. The following important aspects will be covered during the periodic

review.

a. Review of actual performance of each unit vis-a-vis targets and norms for key

operating parameters.

b. Review of specific O&M problems of the project and progress of corrective

actions.

c. Review of external constraints like material supply problems, power

Page 42: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

42

problems and related difficulties.

d. Review of flnanclal performance.

e. Review of house keeping standard.

f. Review of performance to meet environmental standards. g.

Review of safety program.

MAINTENANCE PHILOSOPHY

With a view to build up to required expertise and institute the best maintenance

practices, initially for the first few years, major overhauls and maintenance of

major equipments will be carried out directly by the respective equipment

manufacturers or their licensed representative. The overhaul and maintenance

procedures will then be tuned suitably to have an optimal customized

maintenance system for the equipment and systems covered under the plant.

The maintenance procedure aims at maximizing the availability of generating

units while ensuring minimum maintenance cost and safety of plant and

personnel.

HUMAN RESOURCE DEVELOPMENT

This chapter deals with assessment of manpower required for the proposed plant:

Looking to the automation with advanced technology, the manpower would be

quit limited. The estimated manpower requirement is indicated as below.

TRAINING

Depending on the level and experience of O&M staff, training programs will be

designed and implemented by contractor in association with O&M contractor and

the owner. The covered includes the following:

- The Training at manufacturer's works

- Training at operating plants in India and abroad where similar equipment are in

Page 43: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

43

operation.

- Maintenance training.

- Simulator training.

- Workshops.

In high-tech areas including environment monitoring etc., special training

programs will be arranged for imparting right exposure and building up expertise.

TRAINING POLICY:

An appropriate training policy would be adopted at the outset aiming to fulfill the

main objectives of improving the organizational efficiency & effectiveness as a

whole and also to maintain a high technological status and develop an

understanding of the importance of cooperation & teamwork.

AFFORESTATION

The project envisages a good quantum of afforestation glvmg it the highest

priority to maintain as a pollution free area as far as possible. Afforestation and

green belt development activities would be implemented in a massive way for

which specific land is also separately proposed. Extensive plantation program will

be commenced right from the procurement of the land so that the trees are

appreciably grown up till the plant is commissioned.

Green belt has been considered to be one of the major components of

Environment Maintenance Practice (EMP). The site preparation does not need of

felling trees as the site is covered with negligible bushes and shrubs and is

already within existing plant premises. However, the industry will develop green

belt which will further enhance environmental quality through; mitigation of fugitive

emissions, attenuation of noise levels, balancing Eco-environment, consumption

of treated effluent prevention of soil erosion, and creation of aesthetic

environment. It is proposed to develop green belt/forestation for about 330/0 of

land.

Page 44: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

44

Factors for selection of plant species for green belt development; fast growing,

perennial and ever green, thick canopy cover, large leaf area index, resistant to

specific air pollutants, preferably indigenous, will maintain regional ecological

balance and soil and hydrological conditions of the region. The species to be

planted will be selected based on the available land soil quality and the quantum

of water available. The following aspects would be considered in the placement of

plants.

(i) Trees growing up to two meters or more in height with thick canopy cover

and perennial foliage will be planted around the installation.

(ii) Planting of trees will be done is rows (minimum three rows) while planting

trees care will be taken so that the green envelop would conceal the installation

when observed from outside the premises. For preventing the horizontal

dispersion pollutants if any, the trees planted in alternative row will fall in straight

line.

(iii) Trees will be planted on roadside for vehicular traffic emissions.

(iv) Sensitive species like magnifera indica will be planted in patches along the

entire green belt to work as an indicator of pollution potential.

SOCIO-ECONOMIC DEVELOPMENT:

The project provides full opportunity for local people/village to get employment

directly or indirectly and helps in the up-liftment of socioeconomic status of the

area, which is one of the most essential factors. The project envisages

involvement of social activities of the surrounding community by planning

betterment of neighboring social conditions through awareness and welfare

programs that will ensure improved relations. The commitment of management

includes upIiftment of social, health, basic needs of drinking water supply and

provision of educational facilities. Many of the beneficiaries of such programs

shall include own employees as well. Goodwill of the local population can never

be ignored. The channels employed may vary either through direct contact or by

means of local organizations. Another important fact of social environment

identified by the project proponents is a green appearance; hence the

Page 45: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

45

management will develop a green belt towards aesthetic beautification, as the

same is necessary to be considered as a responsible, social neighbor.

PROJECT MANAGEMENT

Project management covering various aspects of the project will be implemented

following appropriate systems for which experienced Personal and suitable

management tools specially developed for the purpose will be deployed. The

project management activities are ammged in phases and accordingly project co-

ordination procedures will be developed in association with contractor.

Computerized systems with advanced software will he followed for materials

management, cost control, budgetary control, finance management, scheduling,

resource allocation, monitoring etc. An integrated project management and

control system is envisaged for the project planning, scheduling, monitoring and

control. This system encompasses all areas of engineering management,

contract, management, construction and commissioning management. This

system would envisage development of a master network, which is the overall

program of the project.

This is based on Project work systems classification. It identifies the key

milestone dates for each work system in the areas of engineering, procurement,

manufacturing, dispatch, construction, erection testing and commissioning.

PROJECT CONTRACTING

The main features of the project contracting followed by VVL would be as

follows:

All the plant and works involved in this project including detailed design,

engineering, procurement, construction, testing and commissioning of the plant

to a performance specification consistent with International standards, and in

accordance with the current Indian Legislation will be carried out by a single

contractor. This approach minimizes contractual interfaces,shortens project

implementation time scale and places design and contraction risks with the

party best able to manage them. Detailed engineering co-ordination and sub-

Page 46: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

46

contracting activities are all simplified and shortened.

ENGINEERING MANAGEMENT

The project engineering activities will be planned to schedule within the time

frame specified for the engineering milestones in the master network schedule.

The contractor will obtain the approval of the Owner/Owner's Engineer

regarding compliance of criteria for selection, sizing of all equipment, systems,

design margins, design calculations, control philosophy, etc. before proceeding

with detailed engineering designs and manufacture. This will ensure a good

design and installation ensuring high efficiency, operability, availability,

reliability, maintainability etc. Periodic reviews will be conducted to evaluate

progress and take corrective actions to meet said targets and quality. For any

delays likely to occur, corrective action will be identified and advance action will

be taken to meet the project schedule. Project monitoring tool will enable such

preventive measures.

QUALITY MANAGEMENT

The Quality Management will be implemented through various system and

procedure, which shall follow the model of ISO 9000. The apex document for

the Quality Management shall be a Quality program which shall cover system

& procedure for various activities which may have effect on Quality like design

control, document and data control, document and data control, process

control inspection and testing,corrective and preventive actions, quality audit,

control of document and records etc.

This Quality program will include detailed quality control plans for major

equipment & services and it will ensure that the equipment & services under

the scope of contract whether manufactured or performed within the

contractor's works or subcontractor's works or at site, are in accordance with

the contract specification, codes and standards, statutory requirements, etc.

Page 47: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

47

CONTRACTOR

The contractor will have dedicated team headed by a Project Manager who

will be the chief coordinator for the Project, and will be responsible for the

project execution. The project ream of Contractor will have sufficient

technical personnel for various areas like engineering, procurement,

execution, quality, finance etc. to co-ordinate all matters pertaining to the

Project.

In addition the contractor will maintain a site organization headed by a site

construction manager for all site operations. The organization at site will cover

various levels of experts for execution of all works in the areas of Mechanical.

Electrical, Control & Instrumentation, Quality Assurance etc., during

construction, erection and commissioning of the Project.

The Civil works contractor will carry out all civil works required for the project

including all detailed design work. However EPC contractor will carry out the

basic design.

HEALTH, SAFETY AND ENVIRONMENT

The maintenance of a healthy and safe working environment regarded as a

major mutual objective for management and employees at all levels. We

believe that every accident can be prevented and aim to achieve the highest

possible standard in safety and health with an ultimate goal of zero accidents.

To achieve the above objective, construction management will encompass a

comprehensive health, safety and environment management systems, which

includes followings major activities.

• Ensuring all safety features in the equipment, system and layout in the

design stage itself.

• Identification of all site hazards and assessment of risks.

• Safety meetings, safety training and safety drills.

• Safety inspections and auditing.

Page 48: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

48

• Preparation of site emergency plans I Disaster Management Plan.

• Safe storage and handling of hazardous materials .

• Clearing and disposal of all combustible wastes generated at site.

• Arrangement of fire protection system and maintenance.

• Inspection and maintenance of all electrical installation.

• Usage of Safety equipments.

• Accident reporting and analysis procedures.

• Establishment of first aid post with necessary facilities. _

• Health screening and recording system.

The Construction management system will include development of a

comprehensive environmental management plan in the construction phase of

the project. This will deal with both planned and unplanned occurrences.

Specific areas of control during construction and commission will include

correct disposal of any wastewater, control of oil spills, control of noise

emission, control of dust emission etc. . The contractor will be responsible

through various measures including appropriate provisions in the contract, for

discharging their safety obligations. Area covered under construction safety

includes various areas of civil construction, mechanical erection, electrical etc.

RAIN WATER HARVESTING

Rashi Steel and Power Limited are planning to have a system of rainwater harvesting at

village Paraghat and Beltukri, district Bilaspur, Chhattisgarh. Rainwater harvesting is

primarily dependent on various site characteristics such as soil property, catchments

characteristics; rainfall characteristics, and ground water tables etc.

Page 49: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

49

There are artificial as well as natural rainwater harvesting systems. The collecting system

can be implemented for i) Individual units and ii) Centralized collection system

Scheme I: Collection of rainwater harvesting from individual building units. Rainwater

falling on other open area is to be collected, through constructed drainage system and

discharge system and discharge to surface out-fall (by passed for rainwater harvesting)

Scheme II: Construction of rainwater filter bed at centralized place where water from

individual unit as well as storm water from open area shall be diverted

The reference is hydrological data of Bilaspur from the IMD. The maximum rainfall in july

in the year of 2011-12 is 300.3 mm. The yearly rainfall is 1041 mm in 2011-12 and 1100

mm is the average rainfall in the last five year from 2008 to 2012. 1,01,700 m3 maximum

water will be collected from the rain fall in the rain water harvesting pond in a month.

Approximately 3,52,899 m3 water will be collected from the rain fall in the rain water

harvesting pond, which will fulfill the 47 days requirement of the plant.

Rain Water harvesting calculation for the proposed project

Areas Area m2 Run Off -

Coefficient

Assuming

1mm Rain

Fall( in meter)

RWH potential m3

Roof top area 203720 0.8 0.001 163

Paved Area 255690 0.6 0.001 153

Green open land 230290 0.1 0.001 23

Total Storm water Load on the site for 1 mm rain fall 339

Considering maximum rainfall in the month of july is 300 mm, So the total

storm water load

101700

Total storm water load on the site for 1041 mm rain fall 352899

101700 m3 is the maximum capacity of the rain water harvesting pond and the water which we

collect within the project premises in a month.

Page 50: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

50

PROJECT FINANCIAL, COST ESTIMATION ETC.

ESTIMATE OF PROJECT COST

The cost of the palletisation plant of proposed project is estimated on

the basis of the prevailing prices and rates and the estimation is for, the

installation of pallet facilities described in the earner sections with air and

water pollution control equipments. The estimates are derived by dividing the

total quantum of work into three categories, viz., civil works, electrical system

equipment & mechanical equipment no provision for escalation is considered.

The cost of the Iron Ore Palletisation Plant covers all the costs associated

with the construction of the plant, and includes the civil construction cost, cost of

equipment for production, cost of auxiliaries utilities. The total project cost is

arrived at by adding to this cost, the pre operative expenses inclusive of

project design and engineering, sa-t-up and training expenses, interest during

construction and the margin money to meet the working capital requirements. The

table given below gives the details of the Project Works Civil, Mechanical and Electrical

Cost estimate and the overall project cost estimate.

PROJECT COST

PARTICULARS

AMOUNT IN LACS

(i) Land & Site Development Infrastructure 550.00

(ii) Factory Building & Civil Works etc. 3800.00

(iii) Plant & Machinery 7750.00

(iv) Pollution Control Devices 1100.00

(v) Electrical Installation 580.00

(vi) Misc. Fixed Assets 120.00

(vii) Preliminary and Preoperative Expenses 030.00

(ix) Deposits 070.00

SUB TOTAL 14000.00

Margin Money For Working Capital 1000.00

Grand Total 15000.00

Page 51: DETAILS PROJECT REPORTenvironmentclearance.nic.in/.../Online/TOR/0_0_10...details project report for iron ore pelletization plant (capacity-2x1200 tpd) (2x0.4) 0.8 million tpa village:

51

MEANS OF FINANCE

PARTICULARS AMOUNT IN LACS

(i) Share Capital 5160.00

(ii) Unsecured Loan 2640.00

(iii) Term Loan 7200.00

Grand Total 15000