development perspective of transport system in latvia
DESCRIPTION
Development perspective of transport system in Latvia. Andulis Židkovs Deputy State Secretary. East – West corridor. Latvia as a natural bridge in Euro - Asian traffic. Wide railway network links Latvia with Russia, CIS and Asia. Baltica - Transit. Cargo volumes increase every year. - PowerPoint PPT PresentationTRANSCRIPT
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Development perspective of transport
system in Latvia
Andulis ŽidkovsDeputy State Secretary
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
East – West corridor
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Latvia as a natural bridge in Euro-Asian traffic
Wide railway network links Latvia with Russia, CIS and Asia.
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Baltica - Transit
Next step - to prolong to China
Cargo volumes increase every year
1297
4364
6949
1013
9
2174
9
0
5000
10000
15000
20000
25000
2003 2004 2005 2006 2007
TEU
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Importation to EU via Latvia
CHINA
LATVIA
Release for free circulation. Only customs duty should be paid. VAT
is postponed to final receiver
EU
VAT is applied as for regular
EU transaction (stated only
in company's VAT report)
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
LATVIA
LATVIA
Value Added Activities
EU
Customs duty 5%
Customs duty 5%
Customs duty 15%
3%-5%
CHINAAssembling, labeling and other value
added activities
EUborder
5% to 7% off from “PRICE
X”
“PRICE X”
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Rail Baltica
1st stage:reconstruction of the existing infrastructure
Helsinki
Tallinn
Riga
Vilnius
Warszawa
Tapa
Tartu
Valga
Jelgava
JoniškisŠiauliai
Gaiži?naiKaunas
Kazl? R?da
Suwalki
SokolkaBialystok
Kaliningrad
Poland
Belarus
Lithuania
Latvia
Estonia
Sweden
Finland
Russia
Russia
Ukraine
Marijampol?(Intermodal Terminal)
Kaišiadorys
The end point of cross-border sectionNew construction TEN-T LT Reconstruct LTUpgrading TEN-T LT
-
Valka
Valmiera
Meitene
Upgrading TEN-T LV
Upgrading TEN-T EE
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
* Predicted values
DYNAMIC INCREASE IN PASSENGER FLOW
622 647
1 878 035
3 200 000
18 000 000
711 753
10 000 000
5 500 000
2 495 020
1 060 426633 322574 356
2000 2001 2002 2003 2004 2005 2006 2007* 2009* 2012* 2015*
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
More than 60 direct destinations
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
TERMINAL EXPANSION - 2008/2010
DEVELOPMENT OF RIGA INTERNATIONAL AIRPORT
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Road construction projects 2001 – 2013 (including scheduled PPP projects
Jelgava
R IG A
A-3
A-4
A-5
A-6A-8
Bauska
A inazi
A-2
Kekava
Adazi
G auja
Skulte
Svetc iem s
Iecava
G rencta le
Ogre
Saulkrasti
A-12
Jekabpils
Koknese
S lokaPrieda ine
IecavaVaraklani
A-1
A-1
E22
E67
E67
RezekneA -12
A -13
Ludza
Preili
Vilan i
Terehova
PPP 2007-2013
CF 2007-2013
CF 2005-2007
ISPA
2001-2004
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
PPP Pilot Project E77 section Riga Bypass – Senite
Project: 4 lane express road
PPP model: DBFO (Design-Built-Finance-Operate)
Contract: Service Contract
Repayment: Availability Fee
Project costs: 320-350 million EUR
Project period: 3...4+20 years
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF THE REPUBLIC OF LATVIA
Contacts
www.sam.gov.lvwww.transport.lv