MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Indicators achieved in ES Structural Funds activities within the competence of the
Ministry of Transport (as at 30/04/2008)
Andulis ŽidkovsState Undersecretary
Activity 1.2.1
Activity 1.2.1: Reconstruction of infrastructure of the state 1st class roads linking the main economical centres and connect
the centres to the TEN-T network
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIAMINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
National programme: development of the state 1st class roads
is implemented
Indicators achieved during implementation of the programme:Reinforcing asphalt cover – 113.68 kmPaving of gravel roads with asphalt – 24.71 kmImprovement of bearing capacity of bridges – 9 bridgesImprovement of urban transit roads – 5.1 km
Road “Ērgļi - Jaunpiebalga - Saliņkrogs” (section Vecpiebalga - Abrupe)
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.2: Improvement of efficiency of the transport system in populated areas
Sub-activity 1.2.2.1: Optimisation of transport system organisation and traffic safety improvements in populated areas.
(Open call for project applications) (I)
Sub-activity 1.2.2.1
31 project applications under the Open Call for Project Applications No. 1 were approved (out of these - 4 agreements on implementation of projects have been terminated)
Available co-funding from the ERDF – LVL 2,000,000Repaid by 30/04/2008 – LVL 1,650,600
Problems: Beneficiaries have not become acquainted with provisions of agreements signedLack of employees to work on implementation of projects in municipalities
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIAMINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIAMINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.2: Improvement of efficiency of the transport system in populated areas
Sub-activity 1.2.2.1: Optimisation of transport system organisation and traffic safety improvements in populated areas. (Open call for project applications) (II)
154 project applications were submitted under the Open Call for Project Applications No. 2 - 65 applications were approved (out of these - 1 agreement on implementation of the project has been terminated)
Available funding from the ERDF – LVL 3,105,328;Repaid by 30/04/2008 – LVL 1,305,633.
Problems: Insufficient quality of project progress reports and SF claims prepared Inadequate procurement procedure applied for some procurements
Sub-activity 1.2.2.1
Intersection of Meža, Kurzemes and Spartaka Streets in Tukums
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Sub-activity 1.2.2.2: Improvement of traffic management,
traffic safety infrastructure and public transport
management elements in Riga city (I)
National programme: Improvement of Riga transport system in
2004 – 2006 (6 projects):
2 projects have been implemented
4 projects are being implemented
Sub-activity 1.2.2.2
Sub-activity 1.2.2.2: Improvement of traffic management, traffic safety infrastructure and public transport
management elements in Riga city (II)
Total costs – LVL 28,059,726.62
Total eligable costs – LVL 23,779,429.35
Co-funding from the ERDF – LVL 15,756,162.88 Repaid by 30/04/2008 – LVL 5,727,850.33
Problems:
• Due to the rapid increase in costs in the construction sector the
project costs have also increased;
• Timely implementation of sub-projects is impeded by the process of
obtaining land into ownership. MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.3: Improvement of see ports infrastructure and access to the see (III)
National programme
"Reconstruction and development of common hydrotechnical buildings of small ports of Latvia (2004 -2006)” (3 projects) has been implemented
Indicators achieved during implementation of the programme:
2 breakwaters reconstructed - in ports of Skulte and Mērsrags
Problems:
Increase in construction costs, as well as unforeseen works during
construction.
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.3: Improvement of see ports infrastructure and access to the see
Reconstructed breakwater in Skulte port (I)
Activity 1.2.3: Improvement of see ports infrastructure and access to the see
Reconstructed breakwater in Mērsrags port (II)
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.4: Modernisation of the rolling stock of passenger rail transport in suburbs of Riga
(I)
National programme
"Development of passenger rail transport in suburbs of Riga
in 2005 – 2013" (2 projects) Total costs – LVL 17,696,168
Total eligible costs – LVL 11,338,572
Co-funding from the ERDF – LVL 8,503,928
Repaid by 30/04/2008 – LVL 4,793,460
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.4: Modernisation of the rolling stock of passenger rail transport in suburbs of Riga
(II)
Indicator Measurement unit
Amount set in the NP
Amount achieved since 01/01/2004
% of total amount achieved since
01/01/2004
Modernised carriages of electric trains during overhaul Pcs. 69 49 71
Modernised safety systems for the front carriages of electric trains during regular repairs
Pcs. 23 23 100
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.2.4: Modernisation of the rolling stock of passenger
rail transport in suburbs of Riga
Activity 1.3.3: Development of information and
communication networks
in geographically remote areas
by expanding broadband networks of high quality
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA
Activity 1.3.3: Development of information and communication networks in geographically remote areas
by expanding broadband networks of high quality
Under the national programme "Development of high-quality broadband networks in geographically remote areas“ engineering works have been completed and now drafting of documents is being carried out.
Indicators achieved during implementation of the programme: 144 base stations have been set up
Internet will be available in 98% of the territory of Latvia