development proposal and environmental …...purpose of constructing and commissioning a covered...

124
Swift 1 Lock Way, Riverview, QLD 4303 T +61 3 93164732 [email protected] www.jbsswift.com.au Development Proposal and Environmental Management Plan Swift Australia Pty Limited Proposed Wastewater Treatment Plant – Phase 1 King Island Abattoir November 2010 ABN 14 011 062 338

Upload: others

Post on 13-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift 1 Lock Way, Riverview, QLD 4303 T +61 3 93164732 [email protected] www.jbsswift.com.au

Development Proposal and

Environmental Management Plan

Swift Australia Pty Limited

Proposed Wastewater Treatment Plant – Phase 1

King Island Abattoir

November 2010

ABN 14 011 062 338

Page 2: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 2

Contents Executive Summary 6

1. Introduction 7

1.1. Title 7

1.2. Proponent 7

1.3. Proposal Summary 7

1.4. Background 8

1.5. Legislative Context 9

1.6. Public Consultation 9

2. Assessment of Alternatives 10

2.1. Disposal options 10

2.2. Treatment options 13

2.3. Summary 16

3. Proposal Description 17

3.1. Overview of the proposed Wastewater Treatment Plant 17

3.1.1. Location 19

3.2. Wastewater Composition 19

3.3. Final Effluent Quality 24

3.4. Process Description – Abattoir Primary Treatment 25

3.5. Process Design – Covered Anaerobic Lagoon (CAL) 26

3.6. Key Design Issues – CAL 28

3.7. Operational Issues – CAL 32

3.8. Process Design – Anaerobic & Settling Ponds 33

3.9. Process Design – Polishing Ponds 37

3.10. Overall Pollutant Removal 38

3.11. Solid Waste Management 39

3.12. Air Emissions (Odour Dispersion Assessment) 40

3.13. Energy Management 41

3.14. Noise Management 41

3.15. Traffic 41

3.16. Construction and Commissioning 42

4. The Existing Environment 44

4.1. Planning Aspects 44

Page 3: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 3

4.2. Environment Aspects 44

4.3. Socio-economic Aspects 47

4.4. Alternative sites 48

5. Potential Effects and Their Management 49

5.1. Air Emissions (Odour dispersion) 49

5.2. Wastewater 50

5.3. Ground Water 50

5.4. Noise Emissions 50

5.5. Solid and Controlled Waste Management 51

5.6. Dangerous Goods 51

5.7. Greenhouse Gases and Ozone Depleting Substances 51

5.8. Visual Effects 52

5.9. Hazard Analysis and Risk Assessment 52

5.10. Fire Risk 52

5.11. Infrastructure and Off-site Ancillary Facilities 52

5.12. Environmental Management System 52

6. Monitoring and Review 53

6.1. Effluent Discharge Monitoring 53

6.2. Groundwater Monitoring 54

6.3. Reporting Requirements 54

7. Commitments 55

8. Conclusion 56

9. Abbreviations 57

10. References 57

Page 4: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 4

Table Index

Table 1 Qualitative assessment of disposal option against salient criteria 11

Table 2 Assessment of treatment Options 13

Table 3 Design Wastewater Composition 20

Table A3.1 Results of composites taken over the whole processing day, July 2010 21

Table A3.2 Results of composite grab samples taken of DAF feed during May-June 2010 21

Table A3.3 Results of composite grab samples taken of DAF feed during May-June 2010 22

Table A3.4 Results of composite grab samples taken of DAF discharge during May-June 2010 22

Table A3.5 Statistics for DAF treated samples in table A3.1 23

Table A3.6 Removals by DAF from May-June average values 23

Table 4 Expected average treated effluent composition 24

Table 5 Removal of Pollutants in DAF 26

Table 6 Design parameters for the Covered Anaerobic Lagoon 28

Table 7 Design parameters for the Aerated & Settling Ponds 34

Table 8 Design parameters for the Polishing Ponds 38

Table 9 Design pollution removal across the pond system 38

Table 10 Solid Waste Description 39

Table 11 Energy Using Apparatus 41

Table 12 New wastewater treatment plant potential odour sources 49

Table 13 Wastewater Monitoring 54

Table 14 Commitments 55

Figure Index

Figure 1 Proposed Wastewater Treatment Plant Flow Chart 18

Figure 2 Location of King Island Abattoir facility - overview 19

Figure 3 Location of King Island Abattoir facility – close up 19

Figure 4 Bio-gas Flare Design 31

Figure 5 17mm Heavy Bird Netting 35

Appendices

A1 Design Drawing – Site Boundary 58

A2 Design Drawing - WWTP 59

A3 Design Drawing – Elevation 60

B1 & B2 Design Drawing – Bird Netting 61

Page 5: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 5

C1-C4 Project Plan 63

D DPEMP Project Specific Guidelines 67

E Certificate of Title 72

F RENOIR Settling Data 75

G 7.5kW Aerator specification 76

H 5.5kW Aerator specification 79

I Heritage Report 82

J Biogas Monitoring 84

K Climate Date 86

L Odour Dispersion Assessment 87

M Soil Test Pit (1-3) Results 119

N Expected Acoustical Impact of New Aerators and Flare 122

Document History and Status Version Date Status/Comment Originator Project Manager Reviewer

1 30 March 2010 Draft for Swift / EPA Review Troy White Troy White 2 29 September 2010 First Final Draft to submitted to EPA Troy White Troy White 3 9 November 2010 Final Report to EPA / Public Comment Troy White Troy White

Page 6: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 6

Executive Summary

Introduction

This Development Proposal and Environmental Management Plan (DPEMP) has been prepared for the

purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated /

Facultative Lagoons to treat wastewater generated from the site abattoir on King Island. This DPEMP is

also intended to assist EPA Tasmania complete its assessment process, allow public review and

comment that will facilitate the development of permit conditions.

Process Description

Swift Australia is proposing to upgrade the wastewater treatment system at its King Island abattoir site.

The proposed system is designed to treat 260 KL/day (Mon-Fri) through and initial solids screen prior to

entering a 2.3ML CAL to reduce the organic loads and where the captured Biogas is flared providing

odour and GHG reductions. The wastewater enters the adjacent 2ML aerated pond where additional

organic load reduction occurs prior to flowing through a series of new settling ponds, removing the

suspended solids. The wastewater then enters a series of final polishing ponds that also has the facility to

increase the dissolved oxygen levels via a small surface aerator prior to off site release. All lagoons /

ponds will be fully lined with 1.5mm HDPE liners except in the Aerated sections where 2.0mm HDPE

liners will be used.

Exiting Environment

The proposed site is located adjacent to the abattoir on the existing title. The site has been selected to be

the most suitable due to the proximity and gentle topography of the area. Historically, this area has been

subject to year round cattle grazing and subsequently there has been no evidence of threatened flora or

fauna on the proposed site. The location of the proposed WWTP to the King Island Airport is within close

proximity and has been designed with this in mind. There is expected to be no impact on the ground

water as a result of the pond designs incorporating HDPE liners.

Potential Effects and their management

The potential effects of the proposed wastewater treatment system are expected to be a positive impact,

with identified impacts discussed and mitigation measures developed. Specifically, the close proximity of

the King Island Airport highlighted the potential issues of bird attraction (bird strike). This has been

addressed by fully enclosing all open ponds with bird netting.

Monitoring and Review

The monitoring and review program has been established to ensure the management prescriptions

described in the DPEMP project specific guidelines (Appendix B) set out by EPA Tasmania are

successfully complied with. The key aspects requiring monitoring will be final wastewater quality and

odour emissions.

Page 7: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 7

1. Introduction

1.1. Title

Swift Australia Pty Limited (Swift): Wastewater Treatment Plant - Phase 1 King Island Abattoir and

Rendering plant

1.2. Proponent

The proponent of the proposed WWTP is Swift Australia Pty Limited:

Swift Australia Pty Limited (ABN: 14 011 062 338)

1 Lock Way

Riverview

QLD 4303

The contact for this project is:

Troy White

Phone: 03 9316 4732

Email: [email protected]

1.3. Proposal Summary

Swift propose to establish an anaerobic and aerobic / facultative WWTP at the King Island Abattoir,

Morrison Avenue, Loorana, King Island 7256.

The objective of the proposed WWTP is to improve the treatment of existing wastewater generated on

site. The facility will address environmental concerns, in particular odour, aviation bird strikes and

facilitate the cessation of discharge to Porky Creek by 31 December 2012, subject to local land owner

consent and future EPA DPEMP approval of Phase 2 – Ocean Outfall. The facility is being designed to

accommodate a throughput of 260 thousand litres (260 KL) of wastewater per day.

This facility is estimated to cost $1.1 million to construct.

Page 8: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 8

1.4. Background

King Island has a population of approximately 1300 residents. There are about 85,000 head of cattle on

the island being 30% Dairy and 70% Beef. The King Island Abattoir facility was originally built by the

Tasmanian Government in the 1950’s. R.J.Gilbertsons later purchased the very basic abattoir from the

Tasmanian Government in the late 1980’s. Very little money had been spent on the plant; it had no export

license and was in poor shape. Gilbertsons started operations and loaded ¼ sides of beef into DC3’s at

the side fence direct to the airstrip beside the plant, shipping them for processing at their Victorian plants.

In 1990 the company realised the potential of the King Island name and started to produce, and promote

our great King Island brand.

JBS (Brazil) or Swift Australia Pty Ltd (Swift) purchased Australian Meat Holdings in July 2007. In May

2008, Swift acquired the Tasman Group Services business which includes the King Island site. The site

employs 85 people whom process approximately 180 head of cattle per day, 48 weeks per year. Swift

have 10 Abattoirs throughout Australia, with the King Island site contributing to approximately 1.6% of the

weekly beef processing capacity. Swift has since grown to be the largest red meat producers in Australia

investing in over $150M in capital improvements during this period. At Swift we believe our company is

close to nature and we work to do all things in a sustainable and environmentally-friendly manner. Swift is

committed to recycling waste; reducing energy and water consumption; and Greenhouse gas reductions.

In 2009, soon after a viability study, Swift made the decision to close the King Island site. Subsequently,

Swift engaged the Tasmanian Government and negotiated a loan agreement. This loan agreement was

contingent on obtaining EPA approval of Swift developing an acceptable Wastewater Management

Strategy. Swift is also committed to delivering operation improvements over and above the proposed

WWTP subject to this DPEMP. These improvements are as follows;

• Spray Chilling of carcasses;

• Green offal recoveries in the form of Omasum tripe, Honeycomb tripe, Mountain chain tripe,

and small intestines;

• Renewal and upgrading of refrigeration infrastructure, with new compressor technology,

new condensing equipment, additional blast freezing capacity, additional carton handling

and lead-out capacity, installation of hot gas defrost systems on evaporators – removing

need for water defrosts;

• Installation of chilled lidding equipment to promote King Island brand and improve

marketability of products;

• Replacement of some aged equipment;

• Proposed additional water supply from Currie racecourse bore;

• Energy efficiency improvements with heat loss reductions with application of insulation and

cladding;

• Energy heat recovery improvements from waste heat recovery from cooker vents;

• Improvements and overhauls of odour treatment biofilter for rendering odours;

Page 9: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 9

• Rebuild/replacement of aged infrastructure including carton blast chillers, water tanks, and

some other equipment;

• Breeding and stock management assistance for King Island farming sector.

1.5. Legislative Context

This proposal was referred to the Environment Protection Authority (EPA) Board in the form of a Notice of

Intent (NOI) in July 2010. The Director of EPA responded to the NOI (dated 23 July 2010) declaring the

proposal to be a Level 2 activity under the Environmental Management and Pollution Control Act 1994

(EMPCA) (see Appendix A).

As a Level 2 activity the proposal requires approval from the EPA Board. Approval is also required from

the King Island Council under the Land Use Planning and Approval Act 1993 (LUPAA). These two tiers of

assessment are undertaken concurrently and relate to different aspects of the project.

No matters of National Environmental Significance have been identified as relevant to this project and

hence referral under the Commonwealth’s Environmental Protection and Biodiversity Conservation Act

1999 (EPBCA) is not considered to be required by Swift.

The proposed development will also have to comply with a broad range of environmental and planning

legislation, guidelines, standards and policies. The details of such documents are outlined through the

relevant sections of this DPEMP.

1.6. Public Consultation

In preparing this DPEMP, Swift has pro-actively engaged with the local and state authorities and the local

community. State and local elected representatives have expressed support for the proposal, subject to it

meeting the required environmental and planning requirements.

Swift has directly engaged with neighbours of the King Island site to explain the proposal and receive

feedback. Contact with the local residents was made in person (direct ‘doorknocking’) and will be followed

up by advertisement in the daily paper. The outcome of the initial consultation process determined that all

respondents were not concerned about the proposed upgrade at the King Island Abattoir. Many

residences acknowledged that the facility has been operating in its current state for about 60 years and

couldn’t understand why such a large scale WWTP upgrade was required. Swift communicated the

overall environmental improvements and benefits of the proposed upgrade that will contribute to the

ongoing viability and success of the King Island Abattoir operations.

Page 10: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 10

2. Assessment of Alternatives

In Section 2.1, various alternate disposal routes are evaluated and the reasons for the final selection

of ocean discharge explained. In Section 2.2, three treatment alternatives are described and assessed.

2.1. Disposal Options

The various studies conducted regarding upgrading of the King Island abattoir effluent have generally

considered four options for the ultimate disposal or reuse of the treated effluent. These are:

• Release to Porky Creek (the existing situation). This is not considered to be a viable long term

solution by EPA;

• Reuse by land application;

• Reuse within the abattoir facility;

• Release to Bass Strait via ocean outfall.

A further option considered is sub-surface injection.

The critical determinants of the environmental, technical and commercial viability of each of these options

are considered in Table 1 and further comment is provided below.

2.1.1. Porky’s Creek

Porky’s Creek has been the receiving environment for the abattoir effluent for approximately 60 years.

EPA considers continued discharge to this creek unacceptable, especially since it is an ephemeral stream

with negligible natural flow in summer. The high nutrient and salt level in the treated wastewater suggest

that in the absence of any natural flow, there is insufficient mixing zone in the Creek to assist with

discharge in summer.

2.1.2. Land Reuse

Land reuse of treated effluent is the final destination for the majority of meat processing facility effluents in

Australia and in many instances provides some return through cropping. Usually high land areas are

required and these are typically defined by nutrient loading limitations. Depending on climate, some wet

weather storage volume may also be required – typically 1 – 3 months of water storage.

On King Island, the opportunity to irrigate treated wastewater is poor for a number of reasons identified in

Table 1. These include:

• Wet climatic conditions. Annual evapotranspiration averages of the order of 1,020 mm compared

to an average rainfall of 854 mm. In the average wet year, six months (April – September) of the

year have rainfall higher or similar to evapotranspiration (Appendix K). Approximately 37 ha

Page 11: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 11

would need to be irrigated to manage the annual 61 ML of wastewater (and nutrient loads would

suggest that even more land area would be needed).

Table 1. Qualitative assessment of disposal options against salient criteria

Cri

Criterion Disposal Option

Porky’s Creek Ocean outfall Land reuse Reuse in abattoir Sub-surface injection

Effluent salinity Unsuitable in long term

Acceptable

Unsuitable. SAR of 34

Unsuitable chloride of

1,800 mg/l

Unsuitable

Capacity to receive full flow

Unsuitable Acceptable Summer only

Only 10 – 20% subject to quality

issues

Summer only

Risk to Groundwater Low - moderate Negligible Very high Negligible Extreme

Risk to Aquatic flora & fauna

Moderate Low after dilution Negligible Negligible Low

The 2009 year was a 9th percentile wet year (980 mm rain) and on a monthly water balance basis almost

140 ha of land would have been needed for appropriate application (hydraulic balance basis only). At

about $10,000/ha to fit out, the average wet year land requirement of 40 ha amounts to $400,000 fit out

costs not including the pipeline to supply the irrigation headers.

• The wet winter climate would require 6 months water holding capacity (30 ML) so that winter

volumes can be held over until a positive soil water deficit for irrigation was available in soils

(typically in October). This is of the order of $400,000 to construct with the installation of

impermeable linings. The shallow water table would limit the depth of this storage and require a

large land area to be dedicated to this purpose.

• The effluent has a very high Sodium Adsorption Ratio (SAR) of ~ 34. This is probably mainly due

to a combination of brine from the hide shed leaking into the wastewater and regenerate from the

water conditioning resins.

• The groundwater is shallow and depended on by the Island community.

• Finally, due to the high nutrient level in the treated effluent, it would be necessary to grow crops

for nutrient export, rather than graze an irrigated pasture (otherwise land areas required become

infeasible). There is little demand on the island for crops and this practice would to some extent

cannibalise land used to grow the animals on which the abattoir depends.

For these reasons, land reuse is not considered commercially and technically viable.

2.1.3. Reuse in Abattoir

Currently King Island abattoir sources its incoming water from four groundwater bores. Available

measurements of bore quality indicate high quality water with relatively moderate TDS and sodium levels.

Page 12: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 12

The opportunities and legality of recycling treated water in export meat facilities was actively considered

by the industry during the severe drought in South East Queensland during the early 2000s. AQIS issued

a formal Meat Notice2 which encouraged water reuse, but unless water is rehabilitated to extremely

stringent standards (typically including reverse osmosis), it is not possible to accept it for food contact. US

regulations further require stringent separation of all human wastes from the treatment system.

Consequently, effluent treated to secondary standard may be recycled for use in non-potable

applications, including cattle yard washing, cattle washing (excluding final rinse) and other suitable

applications (e.g. wastewater screen sprays). Unfortunately, this is rarely more than 20% of total water

consumption where feedlot cattle are not being processed.

A further consideration is corrosion. The typical chloride levels in the treated water are high (1,800 mg/l).

This exceeds safe levels for most stainless steels (304, 316 grades), which suffer severe pitting at these

concentrations. The recycling of the treated water will need to consider this issue to minimise

maintenance costs.

In summary, recycling of water at King Island abattoir is not a suitable final use for more than about 20%

of water flows. Most of the treated effluent needs discharge to a suitable receiving environment.

2.1.4. Sub-Surface Injection

In some parts of Australia, treated water is injected into sub-surface aquifers, where it can be accessed at

later periods if required. The water quality needed to permit this is not technically or economically feasible

to deliver from abattoir wastewater due to the high initial nutrient and salt levels in the raw effluent and the

dependence of the Island community on the groundwater resource.

This option was considered not viable.

2.1.5. Ocean Outfall

The discharge of treated effluent into Bass Strait via the ocean outfall presents the most favourable

outcome to that of the existing outfall via Porky Creek. The local environment in the vicinity of the outfall:

• Will provide a an adequate mixing zone all year round due to consistent winds from the Southern

Ocean, large ocean waves (rarely less than 1m height on the west coast) and strong ocean

currents.

• is unlikely to be impacted by the high salinity of the effluent;

• poses negligible threat to groundwater supplies;

• provides the most practicable and technically feasible solution commensurate with protecting

environmental values.

The main challenge is the high nutrient levels in the treated discharge (Section 3.3 -Table 4).

Page 13: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 13

Due to the loss of ammonia nitrogen, by volatilisation in the polishing ponds, it is expected that nitrogen

levels will be considerably less in summer (when their discharge into the ocean might be expected to be

more biologically stimulatory due to warmer ocean temperature). In winter, the cold ocean temperatures

assist in diminishing the impact of the higher nitrogen level, especially in the near field of the outfall

diffuser.

Previous investigation into ocean outfall performed by CEE in 2009 using data extracted from the Bureau

of Meteorology ocean wave model that under typical wave and current conditions, this report estimated

that an initial dilution of 1:50 would be produced within 20 m of the diffuser, and 100:1 within 50 m. This

zone of initial dilution is expected to permit the discharge to fall within the State Policy on Water Quality

Management 1997, Emission Limit Guidelines for Sewage Treatment Plants; that discharge pollutants

into fresh and marine waters (see Section 3.3 -Table 4). In summary, ocean discharge represents the

best option for King Island abattoir.

2.2. Treatment Options

For treatment of abattoir wastewater for non-trade waste discharge disposal option, the following two

treatment trains are typically used:

• Anaerobic ponds with downstream Sequencing Batch Reactor (most commonly) or other type of

activated sludge plant;

• Anaerobic pond(s) with downstream aerated pond with subsequent sludge settling and polishing

ponds.

The features of these treatment alternatives are contrasted in Table 2.

Table 2: Assessment of Treatment Options

Page 14: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 14

2.2.1. Anaerobic Ponds

Anaerobic ponds are best practice first stage biological treatment for meat processing effluent unless land

area is constricted3. It is included in each of the treatment alternates in Table 2.

Most anaerobic ponds in meat plants in Australia have been installed without synthetic covers, since the

effluent typically contains sufficient fats and fine cellulosic material which form a natural floating crust.

There has been a reluctance to adopt the covered pond technology (CAL) due to a history of technical

issues which are caused in part by the propensity of the effluent to form a corrosive fatty acid layer under

the covers and/or crusts that block gas mains and/or discharge pipes. This was the subject of a recent

Meat & Livestock Australia (MLA) report4. However, recently the contribution of synthetic covers to odour

and carbon emission control and the potential for high energy biogas capture has made the technology

more attractive.

Johns Environmental has twenty years experience in the design of anaerobic ponds for meat plants. In

the past two years, the company has:

• Designed twin 30 ML covered anaerobic ponds for Cargill Wagga Wagga beef processing plant

(currently under construction);

• Assisted in the start up of the 20 ML covered anaerobic pond installed at AJ Bush & Sons at their

rendering facility in Beaudesert, QLD. The pond is now operating successfully.

• Designed a 10 ML covered anaerobic pond for AJ Bush Riverstone rendering plant (awaiting

approvals).

Nevertheless, the covered anaerobic lagoon technology applied to meat processing effluent remains an

emerging technology with significant uncertainties regarding longevity and operational risks. The design

proposed for King Island is designed to mitigate these risks to the fullest extent possible with current

knowledge.

2.2.2. Alternate disposal Option 1: CAL & SBR

The use of activated sludge treatment using the Sequencing Batch Reactor (SBR) variant for COD and

nitrogen removal to low levels is now well established in the industry. Swift Australia have successfully

operated twin 10 ML SBRs since the mid 90s at their large Dinmore facility in Brisbane. However in the

setting of King Island, SBR technology is inappropriate for the following reasons:

• It is technically complex to operate, especially where expert advice is distant;

• It has a high energy intensity (Table 2), partly driven by the need to achieve the required oxygen

input within 50 – 65% of the cycle time and also by the high nitrogen loads typically present in

modern integrated abattoirs with rendering plants. For comparison, modern STP BNR plants

operate at about 500 kWh / ML due to their low feed nitrogen levels. On King Island, the high cost

of electricity makes this technology highly expensive to operate.

Page 15: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 15

• It requires high maintenance and monitoring inputs to ensure that the system is properly

controlled to achieve compliance with discharge limits. Regular sludge wasting, its dewatering

and disposal are significant issues.

Consequently, this technology was not adopted by the engineering team.

2.2.3. Alternate Disposal Option 2: CAL & Aerated & Polishing Ponds

The discharge from the CAL contains a design BOD5 concentration of 450 mg/l. Stabilisation of this level

requires significant oxygen input if odour generation is to be minimised. For this reason an aerated pond

equipped with surface aeration is sensible. This pond:

• Is technologically straightforward and robust to operate;

• Guarantees sufficient oxygen input to stabilize the incoming organic load;

• Rapidly mixes the incoming anaerobic effluent into the whole pond to minimise formation of

offensive odours, which can occur in non-aerated facultative ponds downstream of anaerobic

ponds.

• Ensures intimate contact of the biological floc with the available organic load through sufficient

mixing energy to maximise degradation rates.

The main challenge for aerated ponds is managing the quantity of bacterial floc formed. If allowed to

simply exit to downstream maturation or facultative ponds, the bacterial floc settles out and can fill the

downstream pond with settled sludge. This can become odorous and reduce treatment efficiency over

time.

Active management of this sludge is recommended in modern installations. The most common means of

this is to:

• either dedicate the downstream pond to simply fill with sludge in a manner that protects

subsequent ponds. This leaves an expensive legacy in that the pond will eventually require

desludging, which is an expensive and time consuming process.

• or provide a downstream settling pond with an active sludge management system. This has been

successfully operated in technologies such as the RENOIR pond, designed by Johns

Environmental and operated successfully since 2003 at Harvey Beef, WA. The settle zone of the

RENOIR pond is a protected area in which the aerated pond discharge enters in a laminar

manner with sludge separating from the treated effluent and settling in the base of the zone. From

there, a sludge pump equipped with floor-mounted extraction piping removes the settled material

from time to time as required. The discharge from the settle zone has TSS levels at least an order

of magnitude less than the aerated pond basin (Appendix D).

Page 16: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 16

Downstream polishing ponds can then focus on disinfection and further polishing of the effluent through

the combination of long detention times in a weakly alkaline, highly oxygenated and solar irradiated

aqueous environment.

This is the preferred design for King Island abattoir.

2.2.4. Alternate Disposal Option 3: CAL & Aerated Pond & Wetlands

An alternate technology to the final polishing ponds is the use of constructed wetlands. In this option the

water exiting Polishing Pond 1 enters the wetlands for treatment. Recommended HRTs for wetlands

treating dilute effluent is of the order of 5 days. Coupled with a typical average depth of 0.5 – 0.6 m, this

requires a constructed wetland of approximately 0.25 ha surface area.

The Currie Township commissioned a wetland system in November 2005 to polish its sewage prior to

discharge. In considering and rejecting this option, the engineering team noted:

• The wetland has a 43% larger footprint than Polishing Pond 2 in the preferred option.

• Estimated costs for constructed wetlands are about $500 – 750,000 per ha and would be even

higher on King Island. The estimated cost would be at least 4-fold more than a straightforward

polishing pond (which has 3 times the treatment volume).

• Wetlands have not been widely applied to meat processing effluent in Australia and significant

technical risk would apply, especially in regard to wetland plant sensitivity to high ammonia levels

relative to sewage. Further, they rarely achieve consistently superior treatment outcomes to

polishing ponds, except perhaps for TSS.

• Controlling bird access to the wetlands to minimise risk of bird strike at the airport would be more

difficult than for polishing ponds. The bird netting recommended for the latter could not be readily

applied to wetlands with its tall aquatic plants and their need for sunlight to thrive.

• Finally, there are substantial maintenance issues with wetlands due to their diverse and dynamic

nature. They are vulnerable to clogging and overgrowth, both of which are difficult to detect other

than by failing performance and challenging to fix.

2.3. Summary

In summary, the only feasible disposal route open for consideration is the ocean outfall. Other options

cannot feasibly handle the quantity of treated water discharged.

The CAL – ponds treatment option has the optimal capital and operating cost consistent with required

final effluent quality. Other options are substantially more expensive to construct and are either expensive

and or complex to operate (Section 2.2.2 Option 1 CAL + SBR), or pose increased risks in terms of

technical implementation and potential bird strikes at the adjacent airport (Section 2.2.4 Option 3, CAL +

ponds + wetland).

Page 17: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 17

3. Proposal Description

3.1. Overview of the proposed Wastewater Treatment System

A process flow diagram outlining the proposed wastewater treatment system is provided in Figure 1.

Key features of the proposed system include:

• For the abattoir wastewater, the primary treatment remains largely the same as currently exists,

except that the obsolete Dissolved Air Flotation (DAF) plant is taken out of service. The paunch

stream continues to receive treatment through the FAN screw press, which is state-of-art for this

stream. The various waste streams are then combined and screened through the existing DODA

rotary screen to remove gross solids and reduce TSS levels.

• The screened combined wastewater is discharged by gravity into a new 2.3 ML nominal Covered

Anaerobic Lagoon (CAL). This pond removes organic matter (BOD, COD) using anaerobic

bacteria to generate methane-rich biogas which is captured by the synthetic cover over the pond.

The biogas and associated odorous compounds are collected and combusted in an adjacent

biogas flare. This destroys odour and climate-warming methane. The CAL is designed to be

highly active all year round – in large part due to the elevated operating temperatures (30 –

35oC). This ensures that much of the new excess biomass generated is discharged into the

downstream aeration pond, rather than settle out in the CAL.

• The CAL discharge flows into the adjacent new aeration pond (2 ML nominal) via a submerged

inlet to minimise odour release. In the aeration pond, aerobic bacteria further reduce the BOD

concentration to generate effluent that is expected to have negligible odour. The contents are

completely mixed by low speed surface aerators.

• The Aeration Pond discharges via a series of pipes into the new Settlement Pond (nominal

volume of 0.7 ML). Since the aeration pond generates significant levels of bacterial floc as

suspended solids, the task of the Settlement Pond is to remove these by settling. The pond is

equipped with two sludge removal pipes near the pond base, from where accumulated sludge

can be removed as required.

• The treated effluent then flows out of the Settlement Pond into two Polishing Ponds in series.

These ponds provide additional retention time to encourage disinfection of the effluent from the

combined action of sun, wind and pH, reduce organic levels further and to permit some

volatilisation of ammonia nitrogen, especially during summer. Prior to discharge from Polishing

Pond 2, a small surface aerator ensures that the dissolved oxygen levels are high prior to delivery

to Porky Creek.

• Some effluent from Polishing Pond 2 may be used for non-potable uses around the facility as

permitted.

• Phase 2 of the upgrade (subject to separate DPEMP) is expected to see the installation of a 4 km

effluent pipe transferring effluent to the ocean outfall upon project design and approvals obtained.

Page 18: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 18

More detailed process description is provided in the following sections. The treatment system is designed

to provide a robust, cost effective system requiring a minimum of operational effort and electrical and

chemical consumption to generate treated effluent suitable for odour-free disposal.

Page 19: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 19

Page 20: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 20

3.1.1. Location

The WWTP will be located at Morrison Avenue, Loorara, King Island approximately 7 km north of Currie

(see figure 1), adjacent to the airport. (Refer in Figure 2 – Arial Map)

Above: Figure 2 – Arial map showing location of site, residence and king Island Airport

Location Abattoir site (Figure 2)

King Island Airport (Figure 2)

Proposed WWTP site (Figure 3)

Above: Figure 3 – Close up of proposed site

3.2. Wastewater Composition

The wastewater stream design composition post DODA screen and DAF and prior to pond treatment are

provided in Table 3. These design values are derived from testing conducted by Swift Australia during

May – July 2010 with samples analysed by EML (Melbourne).

Page 21: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 21

Table 3: Design wastewater composition

Parameter Units

Total COD mg/l 7,250

BOD5 mg/l 3,000

TSS mg/l 2,000

O&G mg/l 120

TN mg/l 450

Ammonia-N mg/l 250

TP mg/l 45

TDS mg/l 5,200

Calcium mg/l 115

Magnesium mg/l 20

Sodium mg/l 1,500

Chloride mg/l 1,800

Sulphate mg/l 65

SAR (calculated) 34

EC μS/cm 8,500

Temp oC 30 – 35

pH 7.2

Faecal coliforms #/100 ml 2 E+06

Some observations pertinent to the pond system design include:

1. The wastewater temperature is warm and optimal for anaerobic treatment. The provision of a

synthetic cover on the anaerobic pond ensures that the pond will operate at this temperature year

round, which permits elevated rates of biological activity, The warmth anaerobic effluent also

means that the water temperature in the first aerated pond cell will also be warmer than ambient

water during winter by a small, but significant degree.

2. Oil & grease (O&G) levels are low relative to the rest of the wastewater composition. This is not

due to the operation of the existing DAF, which achieved only moderate O&G removal (~ 50%). It

is thought that the low O&G levels are due to the down-rated production speeds at King Island.

3. Nitrogen and salt (TDS, sodium and chloride) levels are elevated relative to industry norms. The

reasons are unclear. The elevated salt levels are well within the tolerance of anaerobic and

aerobic biological systems.

4. Other parameters are within normal ranges for integrated beef processing facilities.

Suitable data describing the physicochemical characteristics of the King Island abattoir wastewater were

obtained via a series of grab and composite samples taken by King Island personnel and sent for analysis

to EML laboratories in Melbourne. The data presented represent:

• Table A3.1: Results of composites taken during processing on 2 days in July 2010.

• Tables A3.2 & 3: Results of composite grab samples taken of DAF feed during May-June 2010;

• Tables A3.4 & 5: Results of composite grab samples taken of DAF discharge during May-June

2010;

• Table A3.6: Reports average removal of contaminants over the DAF.

Page 22: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 22

Table A3.1. Results from effluent composite samples taken over the whole processing day, July 2010.

Table A3.2. Results from effluent composite samples taken from the DAF feed during May - June 2010.

Page 23: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 23

Table A3.3. Statistics for Pre-DAF samples in table A3.2.

Table A3.4. Results from effluent composite samples taken of DAF treated effluent during May - June

2010

Page 24: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 24

Table A3.5. Statistics for DAF treated samples in table A1.4.

Table A3.6. Removals by the DAF from May-June average values

Note: Negative values were assigned zero removal

3.3. Final Effluent Quality

The best estimate of design final effluent quality is presented in Table 2. These values do not constitute a

guarantee of final performance, since there is significant influent variation relating to most parameters and

the pond system performance is subject to seasonal variation. The pond system design seeks to provide

a final effluent with the following properties:

1. Meet maximum emission limits for marine waters allowing for a 1:100 mixing zone dilution;

2. Odour-free after treatment and during storage in the final polishing dam;

3. Permits discharge via the ocean outfall with no visible scums, slicks or colour.

Page 25: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 25

Note that the process design assumes that ocean outfall remains EPA Tasmania preferred disposal route

for the treated effluent. There is no attempt made to treat effluent to very low levels associated with high

quality reuse or land irrigation.

Table 4. Expected average treated effluent composition

Parameter Units Final pond quality After mixing zone Maximum Limit

Summer Winter Summer Winter

BOD5 mg/l 20 40 0.2 0.4 20 TSS mg/l 100 100 1 1 30 Oil & Grease mg/l <10 <10 < 1 < 1 10 Total Nitrogen mg/l 280 400 2.8 4 15 Ammonia-N mg/l 250 350 2.5 3.5 5 Total Phosphorus

mg/l 40 40 0.4 0.4 5

Thermotolerant coliforms

cfu/100 ml

1,900 1,900 20 20 750

pH - 6.5 – 8.5 6.5 – 8.5 6.5 – 8.5 6.5 – 8.5 6.5 – 8.5 Note:

1. “Final pond quality” reflects the quality of the discharge from Polishing Pond 2;

2. “After mixing zone” allows for a 100:1 dilution in the mixing zone at the outfall discharge.

3. “Maximum limit” is taken from the State Policy on Water Quality Management 1997, Emission

Limit Guidelines for Sewage Treatment Plants; that discharge pollutants into fresh and marine

waters.

The design Total Nitrogen level in the raw wastewater is 450 mg/l (Table 3), most of this is converted to

ammonium in the CAL. The estimated final treatment ammonia levels (table 4) have been derived by

assuming a 11% loss in various mechanisms, mainly sludge deposition during winter; a further 27%

volatilised during summer via higher wastewater temperatures, pH and wind action.

As detailed in Section 2, Assessment of Alternative treatment options determined that biological nitrogen

removal via SBR was to complex and costly for King Island; as to Ammonia stripping by lime addition / pH

adjustment. Thus, dilution was accepted as the best means of disposal.

3.4. Process Description – Abattoir Primary Treatment

The existing abattoir pre-treatment system comprises three pieces of equipment.

3.4.1. FAN Screw Press

The FAN screw press is increasingly applied to dewater wet and dry dumped paunch solids for beef

processing plants. It has proven to be a reliable an robust technology for this purpose provided large and

hard gross solids are removed first. At King Island abattoir, this is done by settling of these solids in the

pre-screw press tank. There are no plans to alter this infrastructure.

Page 26: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 26

3.4.2. DODA Screen

The DODA rotary screen currently removes gross and suspended solids from the combined waste

streams. It appears to perform this task well. The screen will be moved from its current location to a new

position immediately adjacent to the CAL. The screened solids are retrieved and land spread.

3.4.3. Dissolved Air Flotation (DAF) Unit

The existing DAF is a circular device of obsolete design for meat industry wastewater. Sampling

performed during May and June 2010 found that removals of key pollutants over the DAF were poor

(Table 5). Oil & grease removal was calculated to be approximately 50%, in part the low removal is

possibly due to the low levels of this pollutant in the wastewater.

The initial intention was to upgrade this unit to improve its performance. Subsequent work to better

characterise the raw wastewater suggests that this is unnecessary. The average oil & grease

concentration in the wastewater is 180 mg/l (pre-DAF). At an average flow of 0.26 ML/day, the influent

O&G load is less than 50 kg/day.

Table 5: Removal of Pollutants in DAF

Parameter Removal

COD 15%

BOD5 0%

TSS 11%

O&G 53%

The best performance expected from a DAF treating warm abattoir wastewater is a final O&G level in the

treated effluent of about 100 mg/l. Consequently there is little likelihood of improved operation even with a

completely new unit.

The raw influent O&G load amounts to 50 kg/day, or about 60 litres of fat/day. This is equivalent to a layer

of 0.05 mm across the surface of the CAL. It has been determined that this level of O&G is not a threat to

the integrity of the CAL, especially given the low organic loading of the pond. Operation of the CAL will

include dosage of lipase enzyme treatments to control fatty crust accumulation (See Section 3.7.2).

3.5. Process Design – Covered Anaerobic Lagoon (CAL)

This section describes the design basis for a new covered anaerobic lagoon. This pond is designed to

achieve cost-effective, low energy treatment of the high organic concentrations in the raw wastewater.

Anaerobic ponds represent best practice technology for meat processing wastewater and are widely

Page 27: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 27

applied throughout the world and Australia for this purpose. They can cope with large variations in flow

and concentration with minimal reduction in performance.

It is intended to construct a synthetic cover over the CAL. This technology is still relatively new for meat

processing anaerobic ponds in Australia, but is increasingly being adopted. The technology has been

used in Australia by other industries for approximately 25 years. The advantages of a covered (synthetic)

pond include:

• Negligible odour footprint since odorous gases are captured and combusted in the biogas flare.

• Performance of the pond is not impacted by the cover;

• Significant scope 1 greenhouse emissions resulting from methane-rich biogas production are

eliminated by combustion of the gas in the flare;

• Option to capture and utilize the energy-rich biogas once flow rates and biogas quality are known.

The energy captured would power the wastewater treatment system electrical requirements.

3.5.1. Location of CAL

The CAL will be constructed on the eastern boundary of the abattoir property and to the east side of the

aerobic ponds. The close proximity of the CAL to the abattoir buildings is possible due to the use of the

cover.

3.5.2. Mode of Action

In the anaerobic pond, anaerobic bacteria break down the complex compounds in the wastewater in the

absence of oxygen to release carbon dioxide and methane as the main products of decomposition in

addition to a small increase in bacterial numbers. These products are gaseous and are released to

atmosphere. Sludge production is 10 – 20% that of equivalent aerobic treatment and tends to escape as

elevated suspended solids in the dam discharge. For this reason sludge wasting from the CAL should be

unnecessary.

3.5.3. Process Design Parameters

Key design parameters and dimensions for the CAL are given in Table 6. The dam is suitable for handling

the design abattoir flow and remains at the lower end of usual industry design values for these types of

ponds with an average Hydraulic Retention Time (HRT) of 12 days and a volumetric BOD loading rate of

0.24 kg/m3/day. These values are calculated on a 7-day basis which allows for the fact that there is

negligible weekend load since the abattoir only operates week days. These design values are based on

the pond working year-round at water temperatures between 30 – 35oC (see Table 3).

A minimum removal performance of 85% BOD removal should be achieved. This ensures that the organic

load on the downstream ponds is minimised. This ensures that the risk of odour release and aerobic

sludge formation is kept as low as possible commensurate with normal operation.

Page 28: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 28

Table 6: Design parameters for the CAL. Parameter Units Design Design Flow kL/day 260 BOD load kg/d 780 COD load kg/d 2,000 Pond depth (TWL) m 5.0 Wall batter w:h 2.5 Pond area TWL m2 1,200

Pond Volume (TWL) m3 2,300

Design HRT d 12 BOD5 Areal loading kgBOD/ha.d 7,500 Volumetric loading rate kgBOD/m3.d 0.24

Design BOD removal % 85 BOD exit mg/l 450 BOD load out kg/d 117 Freeboard (above TWL) m 0.5

Notes: HRT & loading rates are given on a 7-day basis (e.g. allowing for negligible weekend load).

TWL – top water level; HRT – hydraulic retention time.

3.6. Key Design Issues

3.6.1. Odour Minimisation

The provision of a synthetic cover across the top water surface of the CAL will ensure that any odorous

emissions are captured and combusted in the associated biogas flare. Odour emissions from the CAL

can be expected to be negligible. This is important, since otherwise prevailing winds from the westerly

quadrant would potentially carry odours across the facility and the adjacent airport.

3.6.2. Inlet/Outlet Structures

Healthy anaerobic ponds treating meat processing wastewater are generally well-mixed due to the large

gas volumes generated through organic breakdown. Stratification or short-circuiting in these systems is

rare (even where inlet/outlet placement is quite dysfunctional). For this reason simple inlet and outlet

structures are sufficient.

Consequently a single inlet and single outlet structure will be provided with suitable access points for

clearing blockages, sampling and with provision for water seals to prevent biogas escape. The inlet will

be at the north-west corner of the CAL where the DODA screen is located. The outlet will be near the

south eastern corner. The invert of the outlet structure will set the pond water depth at 5.0 metres.

3.6.3. Pond Seepage Control

Managing Pond Seepage Control, a minimum permeability of 1 x 10-9 m/s will be provided on the CAL

floor and sides to minimise escape of effluent from the CAL. The preference is for a 1.5 mm HDPE liner

Page 29: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 29

due to the high sodium content of the raw wastewater, which can be aggressive on a compacted clay

liner.

During installation of the liner, seam integrity testing will be required for every seam as welding is

completed to ensure that the seam meets quality specifications prior to installation. Subsequent damage

to the installed liner is unlikely since there is no mechanical action in the pond and the liner will be laid on

a suitably dressed sub-grade free of rocks or sharp objects that might penetrate the liner.

3.6.4. Freeboard

The CAL will maintain a freeboard of approximately 500 mm. This will be set by the outlet structure as

previously described. The large volume of the dam provides a significant safety factor. The 500 mm

freeboard allows 2 days design flow before overtopping occurs.

3.6.5. Bio-GAS Flare

The Bio-Gas Flare has been designed using the following process conditions;

• Flow rate: 25 Sm3/hr normal, 50 Sm3/hr max.

• Composition : 30%- 100% CH4

Balance CO2

H2O saturated

• Pressure : 1 bar(a)

• Temperature: Ambient (250C max.)

Swift have engaged Gasco Pty Limited’s to design fabrication and supply one (1) elevated flare for the

destruction of bio-gas as described above and shown in Figure 4. The flare will be fitted with a wind shield

to conceal the main flame body and to protect it from being blown out in strong wind. Ignition of main

flame is by way of continuous direct sparking at 1.5 second interval, powered by solar panel and a 12-volt

rechargeable gel cell pack which has capacity for continuous operation of 2 weeks in darkness. An in line

axial fan draws bio-gas from the covered pond and feed to the flare tip. The fan is also powered by a

solar power pack. A small flame arrester is fitted to prevent and arrest flashback and combustion along

the pipe work upstream. The flare is a stand-alone unit which is capable of operating for long periods

unattended, it has minimal control and does not require adjustment once commissioned. A set of

galvanized guyed-wires is used to stabilize the flare riser and wind shield. The proposed flare will convert

methane to water and carbon dioxide via combustion thus reducing the impact of greenhouse effect on

the environment. It will also destroy sulphur compounds, which are by-products in the anaerobic digestion

process; these are the chemicals responsible for the unpleasant smell in bio-gas. Destruction efficiency of

sulphur compounds and subsequent residual is affected by a combination of factors such as initial

concentration, ambient conditions and the treatment process. While it is not possible to accurately predict

Page 30: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 30

destruction efficiency or to measure this with an elevated flare, Swift will review this once a detailed

analysis of the composition of bio-gas is available and that a target destruction level is established.

Swift have submitted detailed design information to the Civil Aviation Safety Authority (Advisory Circular

139-05 – June 2007) to have this project proposal application assessed. There is expected to be no

issues with the proposed Flare as it is well below exit velocity of 4.3m/s. Confirmation from CASA is

expect mid November 2010.

The proposed equipment specifications:

• Flare Gas Flow Rate Sm3/hr: 50 max.

• Turndown Ratio: Infinite

• Riser Height m : 4 (tbc)

• Riser Size : DN40, Sch 40

• Riser Material : CS, externally painted, Gasco standard

• Wind Shield : Stainless steel 316

900 X 1500 X 3 (dia.x h x d)

• Ignition: Continuous direct sparking at 1.5 sec interval

• Power Source: Solar Panel with 12-volt rechargeable gel cell pack

Note: All figures are nominal only at this time and subject to confirmation following completion of detailed

engineering.

Figure 4: Bio-GAS Flare Design

Page 31: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 31

3.6.6. Commissioning

For commissioning, typically the CAL will be filled with water to permit the cover installation. Once the

cover and biogas train has been successfully installed, approximately 20m3 of sludge from the Currie STP

will be added to the CAL and wastewater feed from the DODA screen discharge initiated. Since the initial

CAL contents will be dilute and cool, it will take approximately 1 month for the CAL to approach normal

operating temperature and concentrations with a further month to stabilize to normal performance. During

this time, the CAL will receive constant daily inoculation of fresh anaerobic bacteria from the press

paunch liquor.

The progress of the pond can be followed by monitoring CAL outlet effluent temperature, redox (ORP),

pH, BOD5 and COD concentrations on a weekly basis. The long HRT of the pond suggests that a more

frequent monitoring is probably unhelpful. Simultaneously, the biogas volume produced gives an excellent

real time assessment of methanogenic activity.

Page 32: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 32

3.7. Operational Issues

3.7.1. Sludge Control

Anaerobic ponds achieve excellent COD removal for minimal sludge formation. It is expected that a

maximum of approximately 200 m3 of wet sludge (10% of pond volume) may accumulate annually at the

BOD loading used for the design. The remainder will be carried out in the effluent as TSS and destroyed

in the aerated pond. However, this sludge estimate is highly uncertain, and the amount may be quite less

given the reasonably long HRT.

Accumulation of sludge in the CAL is unwanted. Inspection / monitoring access points in the CAL cover

will allow adequate monitoring of any accumulation of sludge or crust in the CAL. Consequently, a settled

sludge removal system consisting of piping laid across the floor of the CAL will be installed at construction

to permit sludge withdrawal using a portable external pump or sludge truck for the task. Desludging

frequency of the CAL will be assessed depending on observations made at the time of the first desludging

(after 1 year).

3.7.2. Management of Crust Build-up under Cover

There is a risk that a crust or fat layer may accumulate over time under the cover. Insufficient experience

with this problem is available to assess the likelihood or rate of accumulation to be expected for this

installation. Where crust or fat accumulation is observed, a program of bacterial and enzyme dosing prior

to plant shutdown (typically 4 weeks in mid year) will be initiated to remedy the situation. Johns

Environmental successfully treated accumulation in a previous CAL by this method.

Page 33: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 33

3.8. Process Design – Aerated & Settling Ponds

This section describes the proposed aerated pond with the downstream settlement pond.

3.8.1. Reason for Selection

The effluent from the CAL contains sufficient biodegradable BOD concentrations (450 mg/l) that there is a

risk of local overloading in downstream facultative ponds unless sufficient aeration is provided, especially

under summer conditions when bacterial rates are highest. Consequently, the design proposes an

aerated pond to rapidly reduce biodegradable organic concentrations to low levels.

Aerated ponds are used successfully in the meat processing industry for this purpose, but one of their

major weaknesses is the large quantity of bacterial sludge generated, which tends to settle out in

downstream ponds. Desludging is expensive, especially where it is allowed to settle throughout large

ponds, and risks damage to the pond lining, which in turn can risk nutrient-rich effluent leaking into

groundwater over time. Consequently, the proposed design allows for a settlement pond immediately

downstream of the aerated pond in which the majority of the bacterial floc can settle and be removed

through purpose-built desludging pipes laid in the base of the settle pond. Short retention times are (< 3

days) are applied to this settlement pond to minimise algal growth or the development of anoxic zones.

The Settlement Pond design applied to the King Island upgrade is based on a design which successfully

settles sludge from the aerated RENOIR pond designed by Johns Environmental and operating

successfully in Western Australia on wastewater from a large beef processing facility since 2003 (See

Appendix F).

3.8.2. Mode of Action

A high concentration of aerobic bacterial flocs are grown and maintained in the Aerated Pond. The pond

is continuously aerated to permit reactions to occur which eliminate BOD from the water to the design

levels.

The mixed liquor is continuously discharged through a series of pipes into the settlement pond. The

discharge is designed to create even, gentle flow of floc-rich liquid into the quiescent environment of the

Settlement Pond, where the bacterial solids disengage from the treated effluent by settling. The clarified

effluent is then discharged into the downstream Polishing Ponds.

As required, the settled sludge can be pumped out of the Settlement Pond via the dual sludge pipes laid

at its base.

Page 34: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 34

3.8.3. Process Design

Table 7 summarizes process design values for the two ponds. The aerated pond will be well mixed

through the action of two new 7.5 kW low speed surface aerators. These ensure that the anaerobic

effluent is rapidly mixed into the pond volume. The low speed aerators provide excellent oxygen transfer

rates to ensure that odour emissions are negligible.

The relatively long HRT for the aerated pond ensures good reduction in BOD5 levels even at the low

winter water temperatures (15 – 20oC). A first order kinetic design equation calibrated from a similar

aerated pond treating abattoir effluent suggests that the exit BOD5 concentration will be of the order of

150 mg/l at 15oC. However, in practice the pond will operate at warmer temperatures due to the residual

heat from the anaerobic pond and the exit BOD5 concentration should be of the order of 100 mg/l or less

in winter, and less again in summer.

Table 7: Design parameters for the aerated & settlement ponds.

Parameter Units Aerated Pond Settlement

Pond

Number of Ponds - 1 1

Design Flow kL/day 260 260

Design hydraulic retention days 10.5 2.7

Volume @ TWL kL 2,000 700

Pond depth @ TWL m 3.5 3.5

Design organic loading (OLR) kgBOD/m3.d 0.07 -

BOD loading kg BOD5/day 130 -

Operating MLSS mg/l 2 - 500 -

Design oxygen requirement kg O2/day 195 -

Design installed aeration kW 15 -

Supply as surface aerators - 2 x 7.5 kW -

Design oxygen supply kg O2/day 360

Estd max wet sludge (5%TS) m3/yr 620

Freeboard (above TWL) m 0.5 0.5

During summer, when temperatures are warmer, there is a possibility that some nitrification may occur,

resulting in a small reduction in total nitrogen.

The Settlement Pond is designed to provide very conservative overflow rates (< 1 m3/m

2/day at half

depth) to ensure ample opportunity for settling of the bacterial floc and associated TSS from the aerated

pond. This is important, since the floc is typically very fine. It is expected that the TSS level exiting the

settlement pond will be 100 mg/l or less.

Page 35: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 35

3.8.4. Odour Control

Negligible odour is expected from the aerated and settlement ponds. On occasion there may be an

“earthy” or “lake water” smell during aeration. The treated effluent is generally odour-free. Predictive

modally has been completed in accordance with EPA guideline and discussed further in section 3.12.

3.8.5. Bird Control

Net Pro Protective Canopies have been engaged to supply and install a bird exclusion canopy as shown

in Appendix B1, which will fully enclose all open WWTP ponds. The net selected is recommended for pest

and bird exclusion with the following specifications;

• Colours: Black Shade: Black 18% (± 2%)

• Construction: Raschel Warp Knitted U/V Block: TBA

• Width: 17m Weight: 80g/m2 ± 5g/m2

• Material: HDPE Monofilament Selvedge: Reinforced

• Burst Strength: TBA

• Fire Rating: N/A

• Warranty: 10 Year Pro Rata U/V Stability 0.6% U/V Inhibitor (excluding colour fastness).

Figure 5: 17mm Heavy bird net

Page 36: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 36

3.8.6. Groundwater Protection

The aerated pond will be constructed with a 2 mm HDPE liner to minimise seepage from the ponds into

the groundwater table. This ensures a hydraulic permeability of less than 1 x 10-9 m/s). A thinner 1.5 mm

HDPE liner will be used for the Anaerobic and Settlement Ponds.

3.8.7. Settled Sludge Management

The sludge removal pipe work in the base of the Settlement Pond will permit connection to a sludge pump

or truck for removal of settled sludge as required. Due to the long HRT in the aerated pond, and the fact

that the sludge remains in the base of the Settlement Pond for an extended period, it is probable that the

volume needing to be removed will be considerably less than the 620m3 indicated in Table 7. The sludge

will be suitable for land spreading or further digestion in a sludge drying pit.

3.8.8. Commissioning

The aerated pond will be commissioned with the addition of approx. 10m3 of sludge from the Currie STP.

The pond should approach design performance rapidly (within 1-2 weeks) since the growth rates of

aerobic bacterial populations is high.

Monitoring during commissioning will include measurements of temperature, dissolved oxygen, and pH

on a daily basis for the first 2 weeks, and weekly monitoring of BOD5 or COD and TSS concentrations

until the system settles down.

If the aerated pond struggles to accumulate sufficient bacterial concentrations, it is possible to return

sludge from the Settlement Pond back to the Aerated Pond to assist.

Page 37: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 37

3.9. Process Design – Polishing Ponds

This section describes the design and operation of the final two ponds in the proposed system.

3.9.1. Reason for Selection

The main roles of the polishing ponds are;

• Reduce pathogenic bacterial numbers through natural attrition due to sunlight, high pH and

dissolved oxygen levels;

• Reduce biodegradable BOD5 levels;

• Allow for ammonia volatilisation during summer periods when the combination of high pH and

warm water temperatures combine to shift the equilibrium towards volatile ammonia in the water

column. Wind assists the mass transfer processes associated with ammonia loss.

• Ensure good oxygenation of the effluent prior to release.

The polishing ponds provide robust and cost effective treatment and allow reuse of the water for

appropriate non-potable uses within the facility. Unfortunately the high nutrient levels remaining in the

effluent make it inadvisable for use in applications where bacterial or algae growth can cause difficulties.

3.9.2. Design Parameters

Table 8 outlines the main design features of the two polishing ponds. The design flows has been adjusted

to the 7-day average on the assumption that the hydraulic variation due to the 5-day processing cycle of

the abattoir has been damped out by the proceeding pond volumes of the CAL and aerated and settling

ponds. The polishing ponds have the following features:

• A series configuration has been adopted to maximise bacterial die off, which is enhanced by plug

flow design (e.g. a number of ponds in series).

• A final 5 kW low speed surface aerator is provided near the exit of Polishing Pond 2 to ensure the

final discharge to the 4 km pipeline conveying treated effluent to the ocean outfall is well

oxygenated. The action of this aerator should also break up any stratification in Pond 2 that can

be deleterious to disinfection performance.

• The long axis of Pond 2 is arranged to allow good longitudinal wind run along its length from the

direction of the prevailing breezes.

• Polishing Pond 1 is a small pond at the western end of the aerated and settlement ponds. It

primarily transfers effluent from the settlement pond to polishing pond 2.

Page 38: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 38

Table 8: Design parameters for polishing ponds

Parameter Units Polish Pond 1 Polish Pond 2

Design Flow kL/day 190 190

Design hydraulic retention days 2.2 19

Volume @ TWL kL 400 3,500

Pond depth @ TWL m 2.0 2.0

Design organic loading (OLR) kgBOD/ha.d 475 80

BOD loading kg BOD5/day 19 19

Design installed aeration kW 5

Supply as surface aerators - 1 x 5 kW

Freeboard (above TWL) m 0.5 0.5

The organic BOD5 loadings displayed in Table 8 assume an entry BOD5 concentration of 100 mg/l from

the discharge of the Settlement Pond. Although the “design organic loading” for Polishing Pond 1 is very

high at 475 kg/ha.d, in reality, the concentration is sufficiently low that odour is very unlikely. The BOD

load is only of the order of 20 kg/day. For Polishing Pond 2, the loading will typical be 80 kg/ha.day.

3.10. Overall Pollutant Removal

Table 9 outlines the design percentage removals of important pollutants across the total pond system.

Table 9: Design pollutant removals across the pond system

Parameter % removal

Summer Winter

BOD5 99.3 98.7

TSS 95 95

Oil & Grease 96 96

Total Nitrogen 38 10

Total Phosphorus 10 10

Thermotolerant coliforms 99.9 99.9

Page 39: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 39

3.11. Solid Waste Management

The management of the discharge of pollutants from point sources, such as wastewater treatment plants,

will be managed in accordance with the following hierarchy of waste management:

1. Waste avoidance;

2. Reclamation and recycling;

3. Waste reuse;

4. Waste treatment to reduce potentially degrading impacts; and

5. Waste disposal.

Swift have implemented waste avoidance practices within production areas, to ensure that all reasonable

actions have been taken to reduce the volume of wastewater and pollution loads being discharged from

the abattoir and rendering activities, and that trade waste controls are in place to ensure that the effluent

does not contain contaminants that cause environmental harm.

Solid Waste Management will remain consistent with current practices and the site will continue to

manage its waste generation in accordance with the EMPCA (Controlled Waste Tracking) Regulation.

The Regulated Waste is generated on site is detailed in Table 10. These are removed by an EPA licence

operator located on King Island.

Table 10: Solid Waste Description

Solid Waste Description EPA Description EPA Class

• Paunch

material

• Animal Effluent and Residues (abattoir effluent,

poultry and fish processing waste)

K100

• DODA

Screenings

• Animal Effluent and Residues (abattoir effluent,

poultry and fish processing waste)

K100

• WWTP Sludge • Animal Effluent and Residues (abattoir effluent,

poultry and fish processing waste)

K100

Our expected de-sludging program is based on like experience with systems around Australia. For

example, the expected frequency for desludging anaerobic lagoons is 20 years, Aerobic (10 years) and

Setting ponds (every 1-3 years).

The WWTP polishing pond 1 is not expected to require desludging annually with the 2nd and final

polishing pond every 5 years. This program will be reviewed annually after commissioning.

Page 40: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 40

Swift has made positive steps in waste reduction by incorporating within the abattoir operations the

means to recover by-products for the rendering plant, recovering blood, separating paunch material to

return to the land, and removing screenings and biosolids matter from the wastewater for alternative use.

The recovery, reuse and recycling of effluent and biosolids is encouraged and supported to allow positive

and sustainable environmental outcomes. The DTAE Guidelines state that “The discharge of effluent to

surface waters should not be permitted unless it is demonstrated to the satisfaction of the regulatory

authority that effluent application to land is not feasible or would result in a higher net environmental risk”.

Improved effluent quality and careful consideration of discharge arrangements from an environmental

perspective are key requirements of the State Policy.

3.12. Air Emissions (Odour Dispersion Assessment)

Swift commissioned EML (Air) Pty Ltd to complete an odour dispersion modelling and impact assessment

of the expected odour emissions from the proposed WWTP and existing equipment at the abattoir. This

dispersion modelling has been carried out in accordance with Environmental Protection Policy (Air

Quality) 2004 and the Atmospheric Dispersion Modelling Requirements Draft V0.91 October 2009. The

full details of this report can be seen on Appendix L – Odour Dispersion Assessment, Report No 86330.

The model predicted dispersed odour ground level concentrations for the existing biofilter and proposed

WWTP to extend beyond the boundary of the premises. However, the predicted 2 OU contour 99.5th

percentile 1-hour average complies with the odour criteria specified by the Environment Protection Policy

(Air Quality) – Schedule 3.

EML (Air) Pty Ltd has determined that based on their Odour Dispersion Assessment, the predictions of

adverse impacts attributed to odour from the existing biofilter or the proposed WWTP on the beneficial

uses of air environment beyond the boundary are unlikely to occur.

It is important to note, that the Abattoir plant has recently undergone a full upgrade that has resulted in

improvement operating efficiencies and delivered significant environmental improvement to odour

reductions. These inclued improved Steam recovery, enclosing wastewater transfer stations and paunch

storage and refurbished biofilter.

Page 41: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 41

3.13. Energy Management

The proposed WWTP will require the following estimated energy sources to facilitate the effective and

sustainable operation of the facility. The following Table 11; shows the energy using apparatus required.

All equipment will be managed through an online monitoring system (SCADA) that will enable variable

speed (on / off) setting to be managed automatically. The aerator will be controlled by this method via

Dissolved Oxygen (DO) level monitoring, saving energy through decrease aerator operation.

Table 11: Energy Using Apparatus

Apparatus kW (existing) kW (new)

Primary Pit 1 Effluent transfer pump no 1 - Duty 11

Primary Pit 1 Effluent transfer pump no 2 -

Standby 11

DODA Effluent solids screen 1.8

Setting Pond Surface Aerator No 1 7.5

Setting Pond Surface Aerator No 2 7.5

Polishing Pond Final Surface Aerator No 1 5

Effluent Transfer Pump No 1 – Duty 11

Effluent Transfer Pump No 2 – Standby 11

Biogas Flare Blower 3

Air Compressor 3

General Light and Power (accessories) 0.5

Total 22 50.3

The switchboard will be designed so if biogas is determined sufficient to run a small 50kW generator,

automatic swing over to generator power from mains can be initiated from the biogas pressure and flow

meters.

3.14. Noise Management

The proposed WWTP will produce ambient background noise less than 35dBA that would impact any

residential development in the area. Noise sources are limited to the aerators, flare, pump operations and

general operational works (DODA screen / solids collection). A predictive Noise Impact Assessment has

been completed by Acoustics RB Pty Ltd (Appendix N).

3.15. Traffic

There is expected to be little requirement for vehicle movement in to the plant. The majority of traffic

movement will be isolated to the WWTP construction zone with excavator, dozer and tip trucks.

Page 42: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 42

After commissioning, the only traffic requirements will be by tractor and trailer to remove the solids

generate via the DODA screen (1 load per day, 5 days per week) between the hours of 7am to 3 pm as

per current practices.

3.16. Construction and Commissioning

3.16.1. Construction Phase

The targeted construction plan (as shown in Appendix C1-4) is a guide only and subject to change

pending date of EPA approval of this DPEMP, King Island council approval, community review feedback,

contractor availability / timelines and unseasonal weather conditions. The construction works will consist

of the follow;

• Plant stormwater segregation (currently underway with plan upgrade improvements)

o Stormwater will be redirected away from the effluent system where identified –namely

redirecting entrance roadway stormwater, redirecting roof stormwater from existing areas.

o Improved stormwater collection from the factory roof including the new blast freezers will

be redirected into the on site stormwater tank for reuse as cattle yard wash down water

• Site excavation (Clay harvesting)

o Clay harvesting will be done during the construction of all the ponds and placed to one

side. This will be used as a base prior to the installation of the synthetic HDPE liners to

obtain a solid, smooth surface free of abrasive materials.

• Anaerobic and Facultative Pond construction

o Construction will include compaction testing, and preparation of each pond surface to

accommodate synthetic HDPE liners to achieve requirements as specified and requested

by EPA Tasmania

• Anaerobic Cover Installation

o The CAL cover will be designed and installed for capture of methane gas emissions and

vented to a flare or potential future energy recovery. It is hoped the energy recovery will

be sufficient in time to self power the effluent treatment system if this option is viable.

• Bird Netting Installation

o The uncovered ponds will have a bird netting structure erected over the ponds to prevent

birds utilising the waters and thus creating bird strike issues for the incoming air traffic at

the airport (roof height to 4mt above TOW, 4mt posts on the central wall for internal

support with 2 access points either end of central dam wall – refer diagram Appendix B1)

• Flare Installation

o The flare installation by Gasco as per section 3.6.5.

• Pump station pit and pipelines

o A pump station pit with automatic level control will control the final polishing pond levels.

At the end of the stage 1 works this will transfer back to the current Porky creek

discharge point, albeit at significantly improved quality – once stage 2 works are

approved then it will pump to the ocean outfall

Page 43: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 43

• Hard stand for DODA screen and solids removal

o This is to provide good access to turn the solids removal tractor and trailer

o The DODA screen is proposed to be erected on a frame sufficiently high such that gravity

discharge of solids can be achieved to a tractor and trailer setup – these solids will be

added to the paunch grass collected elsewhere on site

• Roadway construction

• Installation of temporary outfall line to Porky creek.

3.16.2. Project Timetable

The expected construction period, subject to the approval of the DPEMP and construction phase being

completed within the proposed timelines, is shown in Appendix C1-4.

Page 44: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 44

4. The Existing Environment

4.1. Planning Aspects

4.1.1. Location Selected

As shown in Section 3.1.1, the proposed WWTP location has been subject to previous like proposal

presented to the EPA by previous proprietors whom operated the site abattoir. The proposed site is

owned and operated by Swift Australia Pty Limited and formally contained in the existing site Certificate of

Title, Volume 47288, Folio 1, show in Appendix E.

The site is subject to the provisions of the King Island council planning scheme, which requires Swift to

file the required Development Application and supporting information (Statement of Environmental

Effects). The specific landholding has been part of the King Island Abattoir since the early 1950’s. The

land surrounding the site to the south and west is used for primary production, predominately grazing on

land classified as being within the Rural Agriculture zone. The land to the North and East is occupied by

King Island Airport.

4.2. Environment Aspects

The proposed WWTP site located on Morrison Avenue, 7km north of the Currie Township, will provide the

following environmental, public health, social and economic benefits:

• Protects public health;

• Protects Porky Creek / coastal ecosystem;

• Protects surface waters and groundwater;

• Improves local amenity

4.2.1. Topography

The area is characterised a flat. The site slopes slightly from the north east corner (elevation 45 m) about

2 m to the western and southern boundaries.

4.2.2. Geology (Soils)

ADG Laboratories have been commissioned to analyse the soil sample collected from 3 test points

located on the proposed site for the WWTP as shown in Appendix A2. Test pit, located in the anaerobic

pond was dug to a depth of 7 metres, with test pits 2& 3 located in the aerated and settling pond area

terminated a 3.1 metres. The soil profile reports are shown in Appendix M and the typically characteristics

can be summarised as being an initial layer of silty / sand, followed by a layer of sandy silty clay, then

clayed sand and finally sandy gravel.

Page 45: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 45

4.2.3. Ground Water

No ground water monitoring bores are being proposed for the new WWTP site. The WWTP is expected to

have no adverse impacted groundwater geology due to the installation of 1.5 & 2mm synthetic HDPE

liners in all ponds as detailed in section 3.6.3 & 3.8.5.

Test Pits were constructed on the 17th July 2010, with test pit 1 allowing observations to a depth of 7.0m.

The results of the soil structure and condition seen on the day are detailed in Appendix M. This

determined that there was no groundwater leaching into any of the test pits.

The pond will utilised the recovered soil (including clay) in the preparation of a smooth compacted pond

surface prior to the installation of the fully sealed synthetic HDPE liners protecting the area from any lose

of wastewater to groundwater.

4.2.4. Flora and Fauna

The proposed location for the WWTP will not disturb any established plantations. The area is currently a

mix of pasture grasses that is consistently grazed by cattle. A survey of the area was completed using

Natural Values Atlas report number 40096 completed 02:29:46 PM Thursday, 9th August 2010 which

reviewed the following parameters.

• Threatened Flora: buffers 500m and 5000m

• Threatened Fauna: buffers 500m and 5000m

• Conservation Significance Flora: buffers 500m and 5000m

• Conservation Significance Fauna: buffers 500m and 5000m

• Weeds: buffers 500m and 5000m

• Tasmania Vegetation: buffer 1000m

• Threatened N on-Forest : buffer 1000m

• Geo-conservation: buffer 1000m

• Tasmanian Reserve Estate: buffer 1000m

The report determined that there are no threatened plant species found in the surveyed areas. The final

report is combined wit the Dam Assessment Report – Application sent to the Assessment Committee for

Dam Construction, Water Licence and Dam Administration of the Water Management Branch, Water

Resources Division, Department of Primary Industries, Parks, Water and Environment Ground in Hobart.

A 30 m border of medium height native vegetation is located along the southern boundary of the site.

Page 46: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 46

4.2.5. Climate

Climatic information needed to estimate treatment process operating temperatures, rainfall and other

relevant data was sourced from Bureau of Meteorology for the King Island Airport Station 098017. The

data covers 36 years of data for rainfall (1974 – 2010) and 14 years for temperatures (1995 – 2009). It is

summarised in Appendix 2.

The climate is temperate with half the mean rainfall falling in the 4 months June – September, typically as

light rain (< 10 mm/day). Some rain occurs during other months, but summer is typically dry. Annual

mean rainfall is 854.8 mm.

Evaporation data are not measured on King Island, but the Bureau of Meteorology calculates daily

evapotranspiration rates. During 2009, which was a 90 percentile wet year, evapotranspiration amounted

to 1,023 mm. There is relatively little difference between annual evaporation and rainfall.

Mean maximum air temperatures are 21oC and 13oC in mid-summer and mid-winter, respectively.

King Island is exposed to Bass Strait winds and wind roses show a frequently strong wind pattern even in

the mornings. This is optimal for polishing pond aeration. In the afternoon, the prevailing winds are

predominantly from the western quadrant, but with easterly contributions during spring and summer. The

westerly winds blow across the proposed pond site towards the facility and the adjacent airport. In the

mornings, prevailing wind patterns are more confused with contributions from all directions, depending on

season.

The following climate data has been sourced from the Bureau of Meteorology King Island Airport weather

station.

Climate Data - King Island 1995 to 2010

0

5

10

15

20

25

January February March April May June July August September October November December

Month

Temperature (oC)

0

20

40

60

80

100

120

140

Rainfall (mm)

Mean rainfall (mm) for years 1974 to 2010 Mean maximum temperature (Degrees C) for years 1995 to 2010 Mean minimum temperature (Degrees C) for years 1995 to 2010

Page 47: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 47

4.2.6. Natural Events

Fire - The area surrounding the site is predominately grazing land, typically lined at the boundaries by tea

trees. This does not eliminate the risk of fire, however reduces the possibility of severe bushfire affecting

the site and immediate surrounds.

Flooding - The site is located on an elevated nature rise which will significantly reduce the risk of any

natural flood event to impact the proposed site of the Wastewater Treatment Plant.

4.2.7. Heritage - Areas of Special Conservation

The area identified has been heavily disturbed over many years of clearing, farming and grazing

activities. An archaeological survey for Aboriginal Heritage was conducted on the 4th Augusts 2010 (refer

Appendix H) by Mr Vernon Graham (Senior Aboriginal Heritage Officer & Principal of Palawa Heritage

Services Pty Ltd).

At the time, no Aboriginal artefacts were located during the survey. In relation to European Heritage, the

archaeological report noted there were three areas in the local area that were referred to in early historic

accounts of King Island:

• The campsite at the mouth of the Fraser River where a group of naturalists from the French

scientific expedition led by Baudin stayed for 13 days in 1802;

• An early sealers’ campsite near Cower Point which is referred to by the French naturalists in

1802; and

• A nineteenth century snarer’s camp in the Eldorado Creek vicinity where the Field Naturalist’s

Club of Victoria camped during their 1887 trip to King Island

Swift will also ensure that, if at any time during works, workers suspect Aboriginal or European heritage,

works will cease immediately and AHT or Heritage Tasmania will be contacted, as appropriate, for advice.

4.3. Socio-Economic Aspects

The Swift plant is the largest employer on the island outside the Council, employing approximately 85

people directly and indirectly supports around 90 farming families.

The major industries on King Island include the Cray Fishing industry, where there are about 15 local

fishermen who run boats around both Tasmania and King Island. The majority of their catch goes direct to

China and Japan. National Foods operates the King Island Dairy and produces world famous cheese,

cream and yoghurt. They employ approx 80 people and are along with the Abattoir the biggest employer’s

on the island. There is also a Kelp factory processes bull kelp and they ship their product to a Sister

company in Scotland. The factory employs approx 20 people.

Page 48: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 48

4.4. Alternative sites

No other alternative site has been seriously considered by Swift. The current location selected has been

subject to previous proprietor, EPA and Council encouragement and recommendations for the past 5

years.

Page 49: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 49

5. Potential Effects and Their Management

5.1. Air Emissions (Odour Dispersion)

As previously outlined throughout sections 3.6.1, 3.8.4 and 3.12 the new WWTP will result in an overall

improvement to the impact of the site operations that contribute to odour by decommissioning the DAF

and covering the Paunch tanks. The potential effects of odour from the proposed WWTP and the

mitigation measure that will be employed to eliminate or reduce these are detailed in Section 5.1.1, table

12.

5.1.1. Potential Effects - WWTP Emissions

The provision of a synthetic cover across the top water surface of the CAL will ensure that the majority of

odorous emissions associated with WWTP are captured and combusted via a biogas flare. Odour

emissions from the aerated and settling ponds can be expected to be negligible as detailed in Section

3.12. The follow table 12 addresses all potential air emission points;

Table 12 New Wastewater Treatment Plant Potential Odour Sources

Potential odour Source Assessment Mitigation

Paunch Tank Medium source of odour emission

during hours of operation

• Building secondary containment bund

• Installation of cover

Fan Press Low source of odour emission during

hours of operation

• Maintenance of Fan press in good

working order

Abattoir Wastewater

transfer pit

Closed system – sealed lid / removal

for servicing only

• N/A

DODA Screen Low source of odour emission during

hours of operation (2 hrs / day)

• Maintenance of DODA screen in good

working order

Solids Collection Very low source of odour emission • Waste to be collected within 24 hour for

land application

Covered Anaerobic Lagoon

(CAL)

Fully seal cover • Biogas to be burnt via Flare

Biogas Flare Potential source of odour emission in

event of flame failure

• continuous direct sparking at 1.5 second

interval, powered by solar panel and a

12-volt rechargeable gel cell pack which

has capacity for continuous operation of

2 weeks in darkness

1st Aerated Pond Low source of odour emission • Anaerobic waste reduction analysis

monitoring

• aerator will operate only as required

(DO level controller)

Settling Pond No odour emissions expected • DO level monitoring

Sludge Removal Low odour emission expected • Very low frequency of activity (1 – 3

Page 50: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 50

years)

1st Polishing Pond No odour emissions expected • DO level monitoring

2nd Polishing Pond No odour emissions expected • DO level monitoring

Final Aerator No odour emissions expected • aerator will operate only as required

(DO level controller)

Porky Creek Outfall No odour emissions expected • DO level monitoring

5.2. Wastewater

The final effluent quality is presented in Table 4. The pond system design seeks to provide a final effluent

pollutant removal as detailed in section 3.10; that is expected to be Odour-free after treatment and during

storage in the final polishing dam; and permits discharge to Porky’s Creek with no visible scums, slicks or

colour.

5.2.1. Mitigation Measures

The WWTP will have the facility to return wastewater to the initial anaerobic section via the DODA screen

in the event that outfall parameters are not achieved. Further operation mitigation measures are detailed

in Section 3.7.

5.3. Ground Water

The site sources 100% of its water requirements from ground water bored located approximately 4 km

directly north of the site. There is no ground water extraction bores located on the abattoir title.

5.3.1. Mitigation Measures

The groundwater system is not expected to be impacted as a result of the construction, commissioning

and ongoing operation of the proposed WWTP. There has been no evidence of shallow groundwater

being detected in test pits 1 – 3 (Appendix M) on the proposed site. Wastewater will be metered exiting

the proposed WWTP.

5.4. Noise Emissions

The ambient background noise is not expected to be noticeable off site. The aerators are the only

equipment that has the potential to generate low level noise. No further sound proofing is deemed

necessary due to the location and distance from local residence.

5.4.1. Mitigation Measures

Noise impacts have been considered and Swift has selected very efficient, stable (dynamically and

statically) aerators that will result in low surface noise. The specification for the 2 x 7.5 kWh and 1 x 5.5

kWh aerators are shown in Appendix G & H respectively.

Page 51: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 51

5.5. Solid and Controlled Waste Management

During construction the project, is not expected to produce Solid or Controlled waste with all material

being used on site for the pond construction. In the event of waste being generated during construction,

commissioning this material will be managed in accordance with existing site management procedures

and disposed of using approved waste transporters. The waste management hierarchy will be adopted

where ever practicable to minimise waste generation and recycle if appropriate.

The new WWTP will generate Solid waste from the DODA screen and future Sludge from pond cleaning

that will be managed in accordance with EPA guidelines as detailed in section 3.11.

5.6. Dangerous Goods

The construction of the proposed facility will involve the use of some combustible materials, such as fuels

for construction equipment. These materials will be used, stored and transported in accordance with the

Dangerous Substances (Safe Handling) Act 2005. After commissioning, there will be no dangerous goods

required to be stored or handle in and around the proposed WWTP other than that required for the

maintenance of pumps and aerators.

Any dangerous goods (consumables) used on site will be stored in accordance with Australian Standards

and legislative requirements.

5.7. Greenhouse Gases and Ozone Depleting Substances

Greenhouse Gas (GHG) emissions from the proposed WWTP construction will be isolated to the

construction machinery and any associated transport to and from the site. Swift will ensure that all

contracted equipment used on site shall be maintained in good working order.

During the operation of the proposed WWTP facility, biogas flow generation is estimated to have a

potential peak biogas flow is 50m3/hour. The Biogas composition is also estimated to contain

approximately 70 - 75% methane, with the remainder mainly being CO2. A methane analyser, biogas

mass flow meter (as shown in Appendix J) and PLC are proposed to be installed to monitor this system.

CO2-e emissions from the proposed new CAL are with 80% COD removal and no capture 1,767 tonne

CO2-e / year or as intended in this project, all biogas captured and flared 23 tonne CO2

-e / year. This is a

98.7% reduction in emissions which potential further savings if the biogas is used to displace fuel for

electricity generation.

Page 52: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 52

5.8. Visual Effects

The overall visual effects will not be visible from the public road servicing the Airport due to the lining of

tree surround this area. However, the size and shape of the proposed WWTP can be seen on the site

plans shown in Appendix A1. The final ponds will also be covered by bird netting as shown in Appendix

B1.

The maximum height of any structure is expected to be 4m. The site is part of the Abattoir operations and

is expected to complement the recent upgrade to this site.

5.9. Hazard Analysis and Risk Assessment

A preliminary risk assessment has been undertaken for this project in the form of the Dam Assessment

Report (see Section 4.2.4). There has been no significant risks identified with serious consequence,

however the application of mitigation measures using the hierarchy of control (eliminate, substitute,

engineering, administration and protection) has served to minimise the risk of each. This will be reviewed

and reflected in the site Environmental Management Plan.

5.10. Fire Risk

A fire management plan will be developed prior to the operation of the WWTP. The plan will outline any

fuel reduction measures needed to be undertaken of the surrounding area and ongoing maintenance.

The construction of the proposed facility will involve the use of some combustible materials, such as fuels

for construction equipment. These materials will be used, stored and transported in accordance with the

Dangerous Substances (Safe Handling) Act 2005.

All management measures relating to prevention and response to fire at the proposed facility will be

incorporated into an Emergency Response Plan, which will be developed prior to commissioning. All

electrical infrastructures will be constructed in compliance with the Tasmanian Electricity Code to

minimise risk of electrical faults that may act as ignition sources.

5.11. Infrastructure and Off-site Ancillary Facility

The construction phase will require the initial delivery of materials and construction equipment, however

minimal. The ongoing management of the proposed WWTP will have no additional impact on local

infrastructure.

5.12. Environmental Management System

Swift will ensure that ensure that the site management team will induct all contractors, ensuring all

appropriate environmental management expectations are communicated prior to commencing work.

Page 53: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 53

6. Monitoring and Review Swift will initiate an intensive monitoring program that will be subject to future Environment Protection Notice issued by EPA. Monitoring of the wastewater discharge will be undertaken to:

• Validate improved wastewater discharge characteristic; • Optimise WWTP performance; and • Assess compliance with targeted emission limited outlined with this DPEMP.

It is anticipated that after the initial commission period (the above measures achieved) and prior to the establishment of the Ocean Outfall, it is the intention that the monitoring frequency will be reduced to bi-monthly or quarterly.

6.1. Wastewater Discharge Monitoring

Monitoring points will be established to validate the performance of the WWTP. These points will include

the following:

• Wastewater supply inlet to CAL (after DODA screen);

• Inlet to Facultative Lagoon; and

• Facultative Lagoon Outlet.

All samples will the collected by Swift and sent via airmail to EML (Chem) Pty Ltd. Samples shall be

collected and analysed in accordance with the relevant Australian Standards at NATA certified laboratory.

EML (Chem) Pty Ltd, located in Melbourne, Victoria will provide this service and sampling jars, labels and

sample holding times, storage and transportation will be consistent with establish procedures and

practices on site.

Additional observations will be recorded at the time of sampling to assist with the review of any unusual

results. These observations shall include the following areas:

• Date and time of sample

• Name of sampler

• Sample location

• Ambient weather conditions (unusual events, cloud cover, wind, odour, visible variations)

• General comments

The wastewater parameters included in the monitoring program will include the following table 13.

Page 54: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 54

Table 13 - Wastewater Monitoring

Parameter Unit Sample frequency

Sample type CAL Inlet Inlet Facultative Outlet

pH - Monthly Monthly Monthly Grab

Conductivity Monthly Monthly Monthly Grab

BOD mg/l Monthly Monthly Monthly Grab

COD mg/l Monthly Monthly Monthly Grab

Faecal coliforms Monthly Monthly Monthly Grab

Non filterable residue mg/l Monthly Monthly Monthly Grab

Suspended Solids mg/l Monthly Monthly Monthly Grab

Total Dissolved Solids mg/l Monthly Monthly Monthly Grab

Total phosphorous mg/l Monthly Monthly Monthly Grab

Orthophosphate mg/l Monthly Monthly Monthly Grab

Total kjedahl nitrogen mg/l Monthly Monthly Monthly Grab

Ammonia – nitrogen mg/l Monthly Monthly Monthly Grab

Nitrate – nitrogen mg/l Monthly Monthly Monthly Grab

Nitrite – nitrogen mg/l Monthly Monthly Monthly Grab

Calcium mg/l Monthly Monthly Monthly Grab

Magnesium mg/l Monthly Monthly Monthly Grab

Sodium mg/l Monthly Monthly Monthly Grab

Potassium mg/l Monthly Monthly Monthly Grab

Chloride mg/l Monthly Monthly Monthly Grab

Sulphate mg/l Monthly Monthly Monthly Grab

Oil and Grease mg/l Monthly Monthly Monthly Grab

6.2. Odour Monitoring

Odour dispersion will be monitored and recorded daily during the commissioning program. Predictive

modelling has been completed in preparation of this DPEMP as shown in attached appendices; this will

be repeated within 12 month of commissioning the WWTP and every 3 years thereafter.

6.3. Reporting Requirements

Swift currently maintains a complaints register and incident reporting system to record any event and

corrective actions taken to assess and rectify all issues as appropriate. Any incidents that have the

potential to create environmental harm or nuisance will be reported as required by the current site EPN.

Page 55: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 55

7. Commitments

Swift is committed to undertaking the construction and operation of the proposed WWTP as described in

the DPEMP. These are shown in the following table.

Table 14 Commitments

Number Details DPEMP

Reference Responsibility

1 Swift commit to the development of an Environmental

Management Plan (EMP) prior to commissioning 5.9 Swift

2 Swift commit to the development of an Emergency Response

Plan prior to commissioning 5.10 Swift

3

Swift commit to undertake a review of odour 12 months after

commissioning of the Wastewater Treatment Plant (and at

three-yearly intervals thereafter)

6.2 Swift

4 CAL emissions will be captured and flared continuous Swift

5 A CAL monitoring program will be established to monitoring and

control unwanted crust formation Swift

6 A program will be established to manage the Aerator operation

to provide adequate control in the ponds Swift

7 A monitoring program will be established for the inspection and

maintenance of the bird netting Swift

8 Swift commit to maintenance of complaints and incidents

register 6.3 Swift

Page 56: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 56

8. Conclusion

The proposed WWTP presented by Swift Australia, will ensure that significant improvement will be

achieved to the wastewater discharge loading and has been designed to treat an average flow of

260KL/day, 5 days / week.

The proposed treatment system consists of:

• Retaining the existing DODA rotary screen and fan screw press (treating the paunch stream);

• Retiring the existing DAF;

• Constructing a new 2.3 ML nominal covered anaerobic lagoon (CAL) with associated biogas

handling;

• Constructing a new 2 ML aerated pond equipped with low speed surface aeration to further

destroy organic material and an associated 0.7 ML settling zone to actively manage carryover

suspended sludge from the aerated pond;

• Constructing two new polishing ponds – the first of 0.4 ML volume, the second of 3.5 ML volume

to polish the effluent. The last pond will include a small surface aerator near the discharge to

maximise dissolved oxygen levels prior to discharge to the outfall transfer pipe.

The proposed WWTP will:

• Improve wastewater quality;

• Reduce nutrient load to Porky creek;

• Reduce solid waste generation;

• Reduce Greenhouse Gas emissions;

• Reduce and Control odour;

• Improve wastewater impact on groundwater ;

• Produce effluent which has high potential for future reuse;

• Have no impact on Aboriginal cultural heritage;

• Little to no impact on flora and fauna on the site identified.

This document addresses various design and operational issues with a focus on ensuring that the system

is robust and reliable. The project will have a net positive environmental impact, ranging from

improvements to local odour conditions; reduce GHG emissions and the minimisation of traditional waste.

The project represents the long term viability solution for the King Island Abattoir site, positioning it as a

leading edge WWTP with future possibility of renewable energy production.

Page 57: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 57

9. Abbreviations

ADWF = average dry weather flow

AHDF = average high day flow (tannery only)

AOTR = actual oxygen transfer rate.

Bio-P = Biological Phosphorus removal

BNR = Biological Nutrient Removal

BOD5 = Biochemical Oxygen Demand (measured in 5 days at 20°C) (mg/l).

CAPEX = Capital Cost

COD = Chemical Oxygen Demand (mg/l)

DAF = Dissolved Air Flotation

DPEMP = Development Proposal and Environmental Management Plan

DO = dissolved oxygen concentration (mg/l)

EP = Equivalent Person (used as basis for sizing sewage plants)

E.coli = Escherichia coli (cfu/100ml)

F/M = Food/Micro ratio – a measure of organic loading to activated sludge plants

HRT = hydraulic retention time (days)

LTR = Low Temperature Rendering Plant

NFR = Non-Filterable Residue, similar to SS.concentration (mg/l)

MLSS = Mixed Liquor Suspended Solids (mg/l)

MLVSS = Mixed Liquor Volatile Suspended Solids (mg/l)

ND = Not Determined

NH3-N = ammonia-nitrogen concentration (mg/l)

NO2-N = nitrite-nitrogen concentration (mg/l)

NO3-N = nitrate-nitrogen concentration (mg/l)

O&G = Oil and Grease

PF = Peaking factor

SBR = Sequencing Batch Reactor

SCOD = Soluble Chemical Oxygen Demand (mg/l)

Sol BOD5 = soluble Biochemical Oxygen Demand (mg/l)

SRT = solids retention time (sludge age) (days)

SS = suspended solids concentration (mg/l)

STP = Standard Temperature and Pressure

SVI = Sludge Volume Index (ml/g)

TCOD = Total Chemical Oxygen Demand (mg/l)

TDS = Total Dissolved Solids (mg/l)

TKN = Total Kjeldahl nitrogen (mg/l)

TN = Total Nitrogen concentration (mg/l)

Page 58: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 58

TP = Total Phosphorus concentration (mg/l)

TSS = Total Suspended Solids (mg/l)

TWL = top water level

UV = UltraViolet

VFA = Volatile Fatty Acids

VOC = Volatile Organic Compound

VS = Volatile Solids

VSS = Volatile Suspended Solids

WADF = Week-averaged daily flow (tannery only)

WAS = Waste Activated Sludge

LIST of UNITS

kg/ha.d = loading rate in kilograms per hectare per day

kg/m2.d = loading rate in kilograms per square metre per day

kL/d = kilolitres (cubic metres) per day

mg/L = milligrams per litre = ppm.

m/h = metres per hour

m3/m2.d = surface loading rate in cubic metres per square metre per day

ML = Megalitres (1,000 kL)

Page 59: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 59

10. References

1 1DPIWE (2001). Emission limit guidelines for sewage treatment plants that discharge pollutants into fresh and marine waters. Hobart. June 2001. x

2 2 AQIS (2008) Efficient use of water in export meat establishments. Meat Notice 2008/06. Issued 13 October 2008, Canberra.

X 3

3 MLA (2007). Environmental best practice guidelines for the red meat processing industry. Eds. M Johns, S McGlashan, & A Rowlands. Published Apr 2007, MLA, North Sydney, NSW.

x 4

4 MLA (2009). Anaerobic pond cover vulnerability – assessment of available cover materials. Project A.ENV.0072 Report prepared by Golder Assoc., Perth. Published Aug 2009, MLA, North Sydney, NSW.

5 Johns Environmental Pty Ltd, “Process Design for Wastewater Treatment Upgrade at King Island

Meat Processing Plant” (September 2010) 6 EML Air Pty Ltd, Odour Dispersion Assessment – Report No 86330 (September 2010)

Page 60: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 60

Appendix A1 - Design Drawing

Page 61: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 61

Appendix A2 - Design Drawing

Page 62: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 62

Appendix A3 - Design Drawing

Page 63: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift

1 Lock W

ay, Riverview, QLD 4303

T +61 3 93164732

[email protected]

www.jbsswift.com.au

Appendix B1 - Design Drawing

Page 64: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

64

Appendix B2 - Design Drawing

Page 65: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

65

Appendix C1 – Project Plan

Page 66: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

66

Appendix C2 – Project Plan

Page 67: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

67

Appendix C3 – Project Plan

Page 68: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

68

Appendix C4 – Project Plan

Page 69: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift 1 Lock Way, Riverview, QLD 4303 T +61 3 93164732 [email protected] www.jbsswift.com.au

Appendix D – DPEMP project specific guidelines

Page 70: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 70

Page 71: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 71

Page 72: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 72

Page 73: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 73

Page 74: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 74

Appendix E – Certificate of Title

Page 75: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 75

Page 76: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 76

Page 77: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 77

Appendix F - RENOIR Settling Data

The Settlement pond design is based on the successful settling zone in the Johns Environmental RENOIR

technology. In the settle zone, the effluent enters in a hydraulically controlled manner to minimise fluid

disturbance. The sludge settles and can be withdrawn in a similar manner to the system proposed for

the CAL – namely a sludge piping system attached to a sludge pump. The treated, clarified effluent

overflows the settle zone with much reduced TSS levels.

Since the settling zone is less rigorously constructed compared to the very expensive purpose-built

secondary clarifiers servicing modern activated sludge plants, a very conservative overflow rate is used.

The success of this strategy in the RENOIR is seen in the figure below. Whereas mixed liquor TSS

concentrations in the RENOIR aerated basin were as high as 2,500 mg/l or more, TSS in the pond

effluent remained below 100 mg/l. Only at extreme TSS levels in the aerated basin (> 2,500 mg/l) were

higher effluent TSS observed.

The facility where the RENOIR was installed processed on average 1.5 ML/day effluent.

Effectiveness of RENOIR settle zone – 9 months data.

Page 78: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 78

Appendix G - 7.5 kWh Aerator Specifications

Page 79: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 79

Page 80: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 80

Page 81: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 81

Appendix H – 5.5kWh Aerator Specifications

Page 82: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 82

Page 83: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 83

Page 84: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 84

Appendix I – Heritage Report

Palawa Heritage Services Pty Ltd- Aboriginal Archaeology ACN 112 128 015 - ABN 97 112 128 015

Aboriginal Heritage Consultant Aboriginal Cultural Heritage Survey

Cross Cultural Awareness Training, Arts Traditional Crafts & Photography

Vernon Graham

Aboriginal Heritage Consultancy & Photographer

61 Galvin Street

South Launceston

Tasmania 7249

Phone 03 63 431 036

Mobile 0417 378031or 0408 035884

22nd August, 2010

Troy White

Group Environment Manager

Swift Australia Pty Limited

30 Industry Park Drive, Brooklyn VIC 3012

PO Box 36, Altona North VIC 3025

E: [email protected]

Re: King Island Abattoir

Brief regarding 2 phase proposal, the first phase being two dams (9ML Anaerobic dam and 20ML Aerobic dam) and the second

phase is construction of a 4 kilometres Ocean Outfall Pipeline from the two dams near the Abattoir. The survey was conducted

on the 4th August 2010 by Vernon Graham a Senior Aboriginal Heritage Officer; in relation to the area proposed for the two

dams and also the proposed easement for the pipeline. Regarding the two proposals these will be in two stages, just dealing with

the first phase of the project proposal.

However in reference to the second phase of the proposal there needs to be discussions with Tasmanian Aboriginal Land & Sea

Council and possibly the Tasmanian Aboriginal Centre, prior to the assessment there was discussions with the Senior Aboriginal

Heritage Officer of the Tasmanian Aboriginal Land & Sea Council and they indicated that there was a known Aboriginal site

within the region of the proposal and there would be a need to conduct a TASI (Tasmanian Aboriginal Site Index) search.

The methodology in dealing with the area being surveyed to identify incidences of Aboriginal Archaeological (Heritage) values, the topographical layout of the land and the variation of ground visibility;

• Walking the proposed areas of the dams and the easement concerning the pipeline to identify incidences of Aboriginal

Heritage/Relics.

• Potential areas / pads of Aboriginal Archaeological sensitivity if needed.

• If any site is located it‘s recorded and GPS datum used is GDA 94.

Findings regarding the first phase being the 9ML Anaerobic dam and 20ML Aerobic dam located south of the Abattoir, this area has been highly disturbed there had been test pits dug in reference to layout of the soil profiles, this made visibility quite good

and there was no evidence of any heritage values in the areas of the two proposed dam sites, (see attached print).

This is a brief on the survey findings and there will be a need for a full report to be done in regards to the consultation process

with the Aboriginal community to review the survey outcomes for comment. However in regards to the first phase retaining to earth works if they proceed and there is quarries concerning Aboriginal heritage

the following applies;

Page 85: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 85

• That works cease if any there is any quarries regarding Aboriginal heritage.

• Contact either TALSC and or the AHT Aboriginal Heritage Tasmania.

All Aboriginal sites, along with other important landscape values and cultural resources, are an integral part of Aboriginal

Cultural/Heritage values and should be managed. Any Aboriginal site/s is to be afforded legal protection from the following

legislation.

Legal requirements

In compliance with the Aboriginal Relics Act 1975, as contained under Section 2 (3 a, b, c ) and (4) of the act, interpretation of

the term relic is as follows:

(3) For the purposes of this Act, but subject to the following provisions of this section, a relic is—

( a) any artefact, painting, carving, engraving, arrangement of stones, midden, or other object made or created by any of the

original inhabitants of Australia or the descendants of any such inhabitants;

( b) any object, site, or place that bears signs of activities of any such original inhabitants or their descendants; or

( c) the remains of the body of such an original inhabitant or of the descendant of such an inhabitant who died before the year 1876 that are not interred in—

( i) any land that is or has been held, set aside, reserved, or used for the purposes of a burial-ground or cemetery

pursuant to any Act, deed, or other instrument; or]

( ii) a marked grave in any other land.

As part of the client / proponent has an obligation to the Tasmanian Aboriginal community in accordance with the Aboriginal

Relics Act 1975, as contained under Section 14 (1).

Except as otherwise provided in the Act, no person shall otherwise than in accordance with the terms of a permit granted

by the Minister on the recommendation of the director— (a) destroy, damage, deface, conceal, or otherwise interfere with a relic.

If there’s any concerns please do not hesitate to call.

Thank You

Sign

Vernon Graham Senior Aboriginal Heritage Consultant

& being the Principal of Palawa Heritage Services Pty Ltd

Cc: Colin Hughes the SAHO of TALSC, and

Forward Email to Aboriginal Heritage Tasmania

Page 86: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 86

Appendix J – Biogas Monitoring

Page 87: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 87

Page 88: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift

1 Lock W

ay, Riverview, QLD 4303

T +61 3 93164732

[email protected]

www.jbsswift.com.au

Appendix K – Climate Data

Page 89: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift 1 Lock Way, Riverview, QLD 4303 T +61 3 93164732 [email protected] www.jbsswift.com.au

Appendix L – Odour Dispersion Assessment

Page 90: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 90

Page 91: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 91

Page 92: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 92

Page 93: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 93

Page 94: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 94

Page 95: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 95

Page 96: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 96

Page 97: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 97

Page 98: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 98

Page 99: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 99

Page 100: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 100

Page 101: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 101

Page 102: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 102

Page 103: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 103

Page 104: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 104

Page 105: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 105

Page 106: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift

1 Lock W

ay, Riverview, QLD 4303

T +61 3 93164732

[email protected]

www.jbsswift.com.au

Page 107: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

107

Page 108: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP

108

Page 109: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Swift 1 Lock Way, Riverview, QLD 4303 T +61 3 93164732 [email protected] www.jbsswift.com.au

Page 110: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 110

Page 111: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 111

Page 112: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 112

Page 113: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 113

Page 114: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 114

Page 115: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 115

Page 116: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 116

Page 117: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 117

Page 118: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 118

Page 119: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 119

Appendix M – Soil Test Pits (1-3) results

Page 120: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 120

Page 121: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 121

Page 122: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 122

Appendix N – Expected Acoustical Impact of New Aerator and Flare

Page 123: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Development Proposal and Environmental Management Plan

Swift Australia – DPEMP 123

Page 124: Development Proposal and Environmental …...purpose of constructing and commissioning a Covered Anaerobic Lagoon (CAL) followed by Aerated / Facultative Lagoons to treat wastewater

Filename: KI - WWTP Phase 1 DPEMP 6Nov2010.doc

Directory: C:\Documents and Settings\mmuliett\My Documents

Template: C:\Documents and Settings\mmuliett\Application

Data\Microsoft\Templates\Normal.dotm

Title:

Subject:

Author: twhite

Keywords:

Comments:

Creation Date: 11/9/2010 11:39:00 AM

Change Number: 2

Last Saved On: 11/9/2010 11:39:00 AM

Last Saved By: twhite

Total Editing Time: 1 Minute

Last Printed On: 11/9/2010 12:16:00 PM

As of Last Complete Printing

Number of Pages: 123

Number of Words: 15,900 (approx.)

Number of Characters: 90,631 (approx.)