FACILITY CONDITION ASSESSMENT © 2016 4tell™ Solutions, LP. All Rights Reserved. 4tell, iPlan (patent pending) Building Blocks, and Innovation for the Built Environment are trademarks of 4tell™ Solutions, LP. Capital City PCS (Lower, Middle, and High Schools) 100 Peabody St NW Washington, DC March 13, 2018 Submitted by: 3715 Martin Luther King Jr. Avenue, SE Washington, DC 20032 Submitted to: Mr. Stephen A. Campbell Senior Planner, Planning Office Department of General Services – Construction Division 2000 14th Street NW, 5th Floor Washington, DC 20009

Upload: trinhxuyen

Post on 13-Jul-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

FACILITY CONDITION

ASSESSMENT

© 2016 4tell™ Solutions, LP. All Rights Reserved. 4tell, iPlan (patent pending) Building Blocks, and Innovation for the Built Environment are trademarks of 4tell™ Solutions, LP.

Capital City PCS (Lower, Middle, and High Schools)

100 Peabody St NW

Washington, DC

March 13, 2018

Submitted by:

3715 Martin Luther King Jr. Avenue, SE

Washington, DC 20032

Submitted to:

Mr. Stephen A. Campbell

Senior Planner, Planning Office

Department of General Services – Construction Division

2000 14th Street NW, 5th Floor

Washington, DC 20009

Hayat Brown LLC Page 2 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

T A B L E O F C O N T E N T S

Table of Contents ................................................................................................................... 2

Executive Summary................................................................................................................ 3

1.1 General Description ..................................................................................................................... 3 1.2 Scope of Work ............................................................................................................................... 3 1.3 Definitions ....................................................................................................................................... 5 1.4 Limiting Conditions ..................................................................................................................... 7 1.5 Building Summary ........................................................................................................................ 8 1.6 Summary of Findings .................................................................................................................. 8 1.7 Facility Condition Index.............................................................................................................. 9 1.8 Expenditure Forecast .................................................................................................................11 1.9 Assets Observed .........................................................................................................................13 1.10 Planning Horizon Category Needs: Current Year to Year 10 ....................................14 1.11 Building System Needs: Immediate ....................................................................................16 1.12 Building System Needs: Year 2 - Year 10 ..........................................................................17 1.13 Building System Needs: 10 Year Forecast.........................................................................18

A SubStructure Systems .................................................................................................. 19

A10 FOUNDATIONS .......................................................................................................................19

B Shell Systems ................................................................................................................. 22

B10 SUPERSTRUCTURE ..............................................................................................................22 B20 EXTERIOR ENCLOSURE .....................................................................................................23 B30 ROOFING ...................................................................................................................................40

C Interiors Systems .......................................................................................................... 44

C10 INTERIOR CONSTRUCTION ..............................................................................................44 C20 STAIRS ........................................................................................................................................53 C30 INTERIOR F INISHES .............................................................................................................61

D Services Systems........................................................................................................... 75

D10 CONVEYING SYSTEMS ......................................................................................................75 D20 PLUMBING ................................................................................................................................78 D30 HVAC .........................................................................................................................................91 D40 F IRE PROTECTION SYSTEMS ..................................................................................... 138 D50 ELECTRICAL SYSTEMS ................................................................................................... 140

E Equipment & Furnishing Systems ............................................................................ 170

E10 EQUIPMENT ........................................................................................................................... 170

G Building Sitework Systems ....................................................................................... 173

G20 S ITE IMPROVEMENTS ..................................................................................................... 173

Appendices

Appendix A: Photographic Record

Appendix B: Survey Information Resulting In Plant Adaptation Recommendations

C21

Hayat Brown LLC Page 3 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

E X E C U T I V E S U M M A R Y

1.1 GENERAL DESCRIPTION

Hayat Brown LLC was retained by the District of Columbia Department of General Services (DGS) to undertake Facility Condition Assessments (FCAs) for District of Columbia Public Schools (DCPS) facilities. The purpose of the FCAs are to inventory the elemental components in the buildings, identify key attributes of those components, determine estimated remaining useful lives (RULs) and replacement costs of those components for inclusion in DCPS’ 6-year capital plan. The FCA will also identify physical deficiencies needing immediate attention. The FCA data was collected by Hayat Brown LLC’s assessment teams into the iPlan™ Sustainable Facility Governance Solution (iPlan) platform and will function as the source for DGS’ development of a comprehensive repair, alteration, and improvement program for DCPS facilities. The FCA and analytical data will enable the District to plan, manage and analyze data utilizing a single platform. This will enhance the District's ability to develop short-, intermediate-, and long-term capital improvement strategies based on stakeholder needs and will provide for a cost-effective operation of the facility based upon the prioritization code for each identified element or component in the FCA. The iPlan platform calculated the RULs and estimated replacement costs, and generated this draft Facility Condition Assessment Report (FCA Report) for DGS review. The iPlan platform also allows the FCA data and the FCA Report to be accessible via a web-based dashboard.

1.2 SCOPE OF WORK

The FCAs were carried out by Hayat Brown LLC (Contractor) and included a complete and thorough visual, non-destructive assessment of each facility. The Contractor followed ASTM standards ("ASTM E2018-08") for conducting property condition assessments, as well as guidance from DGS regarding additional survey information and cost estimates for possible plant adaptations. The FCA Report summarizes the FCA process, which included the following:

• Review of existing documentation provided by the District and interviews with DCPS personnel regarding

aspects of each facility.

• Physical assessment to include a limited non-intrusive visual assessment of the buildings and their

components.

• Identify and categorize each major component for predictive maintenance, testing and/or inspection,

preventative maintenance, emergency maintenance and/or routine maintenance needs.

• Based on provided templates surveyed elements included:

o Core and shell: These elements include superstructure, floors, bearing walls, columns, beams, and

exterior envelope components.

o Interiors: These elements include interior finishes of floors, walls, ceilings, stairways, etc.

o Building equipment and systems: These elements include HVAC systems, and electrical systems, fire

protection systems, and conveyor systems.

o Fixed equipment and non-movable furnishings: These elements include fixed equipment such as

kitchen equipment’s, audio equipment, public address systems, etc.

C21

Hayat Brown LLC Page 4 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

o Building site Improvements: These elements include paved surfaces, playground equipment, fencing,

recreational elements, site lighting, general site drainage and landscaping.

• Evaluated additional elements based on questionnaires provided by DGS. These questionnaires were

answered based on interviewing the facility staff and visual surveys:

o ADA accessibility: included questions relating to accessibility barriers of interior and exterior elements

o Safety and security: included questions relating to safety and security of the facility such as fire

protection systems

o Access control: included questions relating to controlled access to the facility such intrusion detection

systems and component hardware

o Hazardous materials: included questions relating to the existence hazardous materials at each facility

o LEED opportunities: included questions relating to existing components and improving LEED

certification points

o Additional space considerations: included additional questions relating to space allocation and the

existence of special features

C21

Hayat Brown LLC Page 5 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.3 DEFINITIONS

Facility Condition Assessment Report (FCA Report) - The work product resulting from completing a FCA is a FCA Report. The FCA Report incorporates the information obtained during the Walk-Through Site Assessment Survey, the Document Review, and Interviews to support the iPlan cost estimates for components at their RUL.

Document Reviews and Interviews - Includes document reviews, research, and interviews to augment the walk-through survey so as to assist the consultant's understanding of the subject property and identification of physical deficiencies. Walk Through Site Assessment Survey - The walk-through survey identifies the subject property's elemental components, conditions, RULs, and replacement costs at RUL. Costing - Costing is reported following the ASTM 2018-08 Guidelines Section 9, “Opinions of Costs to Remedy Physical Deficiencies. As such, they include general-scope opinions of costs to assist the user in developing a general understanding of the physical condition of the subject property. As outlined in ASTM 2018-08, the opinion of probable costs should only be construed as preliminary, order of magnitude budgets. Actual costs will vary based on design, quality of materials, field conditions and several other factors as outlined in ASTM 2018-08. Generally, costing does not include project management, contingency, permits, hazardous material remediation (unless specifically stated on a case by case basis) and other overhead costs such as Architect and Engineering fees, profit, or other markups.

Replacement and repair costs herein are based on the two major North American Standards for facility cost estimating: Whitestone Facility Maintenance and Repair Cost Library (Costlabs); and RSMeans. Whitestone visualizes costing from a Facility Maintenance viewpoint while RSMeans approaches costing from a construction viewpoint. Using industry best practices, the relative strengths of each costing approach has been integrated into a unified costing guide for the condition assessment process. The quantities associated with each item have been estimated during a walk-through during the site assessment and do not represent exact measurements or quantities. Costs have been adjusted to the local Washington DC area and are stated in constant 2017 dollars. The cost guide has been utilized by the assessment team as a starting point for costing and supplemented by the assessors adjusting costs based upon experience and facility factors (such as installation design) to determine maintenance and replacement costs. Physical Deficiencies - In defining good commercial and customary practice for conducting a baseline FCAs, the goal is to identify and communicate physical deficiencies to a user. The term physical deficiencies mean the presence of conspicuous defects or material deferred maintenance of a subject property's material systems, components, or equipment as observed during the assessor’s walk-through survey. This definition specifically excludes deficiencies that may be remedied with routine maintenance, miscellaneous minor repairs, normal operating maintenance, etc., and excludes conditions that generally do not present material physical deficiencies of the subject property. Survey Information Resulting in Plant Adaptation Recommendations - These are methodical questions based

upon defined industry or Owner standards resulting in a general costing amount that gives an Owner a cash

expenditure to plan on within proformas.

C21

Hayat Brown LLC Page 6 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Life Cycle - There are various approaches for determining an elemental component’s service life such as a “modeling” approach where an industry standard expected useful life (EUL) is added to a component’s date of installation resulting in a modeled or calculated expectation of replacement for that item. The methodology used in Hayat Brown LLC’s reported value for the expected replacement of an elemental component is a field assessed opinion of remaining useful life (RUL). Observed RUL takes into account a field assessor’s observation of the elemental component along with other factors such as maintenance records or observed measurable parameters. Planning Horizon – Since the life cycles of many elemental components exceed industry standard cash flow proformas, Hayat Brown LLC’s FCA Report only includes a timeframe of importance to an Owner’s immediate cash flow planning. In the case of this report, DGS requested a planning horizon window of 10 years. The Planning Horizon years and remaining useful lives (RULs) as defined in this report’s approach are summarized in the table below:

Planning Horizon Remaining Useful Life

(RUL)

Year 1 - “Immediate” or “Current” 0

Year 2 1

Year 3 2

Year 4 3

Year 5 4

Year 6 5

Year 7 6

Year 8 7

Year 9 8

Year 10 9

C21

Hayat Brown LLC Page 7 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.4 L IMITING CONDITIONS

This report has been prepared for the exclusive and sole use of the Department of General Services. The report may not be relied upon by any other person or entity without the express written consent of Hayat Brown LLC. Any reliance on this report by a third party, any decisions that a third party makes based on this report, or any use at all of this report by a third party is the responsibility of such third parties. Hayat Brown LLC accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made, or actions taken, based on this report. The assessment of the building/site components was performed using methods and procedures that are consistent with standard commercial and customary practice as outlined in ASTM Standard E 2018-08 for PCA assessments. As per this ASTM Standard, the assessment of the building/site components was based on a visual walk-through site visit, which captured the overall condition of the site at that specific point in time only. No legal surveys, soil tests, environmental assessments, geotechnical assessments, detailed barrier-free compliance assessments, seismic assessments, detailed engineering calculations, or quantity surveying compilations have been made. No responsibility, therefore, is assumed concerning these matters. Hayat Brown LLC did not design nor construct the building(s) or related structures and therefore will not be held responsible for the impact of any design or construction defects, whether or not described in this report. No guarantee or warranty, expressed or implied, with respect to the property, building components, building systems, property systems, or any other physical aspect of the property is made. The recommendations and cost estimates associated with these recommendations, as presented in this report, are based on walk-through non-invasive observations of the parts of the building which were readily accessible during our visual review. Conditions may exist that are not as per the general condition of the system being observed and reported in this report. Cost estimates presented in this report are also based on information received during interviews with operations and maintenance staff. In certain instances, Hayat Brown LLC has been required to assume that the information provided is accurate and cannot be held responsible for incorrect information received during the interview process. Should additional information become available with respect to the condition of the building and/or site elements, Hayat Brown LLC requests that this information be brought to our attention so that we may reassess the conclusions presented herein. The cost estimates are intended for global budgeting purposes only. The scope of work and the actual costs of the work recommended can only be determined after a detailed examination of the site element in question, understanding of the site restrictions, understanding of the effects on the ongoing operations of the site/building, definition of the construction schedule, and preparation of tender documents. We expressly waive any responsibilities for the effects of any action taken as a result of these endeavors unless we are specifically advised of prior to, and participate in the action, at which time, our responsibility will be negotiated. Our opinions and recommendations presented in our reports will be rendered in accordance with generally accepted professional standards and are not to be construed as a warranty or guarantee regarding existing or future physical conditions at the Site or regarding compliance of Site systems/components and procedures/operations with the various regulating codes, standards, regulations, ordinances, etc.

C21

Hayat Brown LLC Page 8 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.5 BUILDING SUMMARY

Item Description

Project Name Capital City PCS (Lower, Middle, and High Schools)

DCAM-17-NC-0058

Full Address 100 Peabody St NW Washington, DC 20011

Year Built 1963

Gross Building Area (SF) 176,900

Current Replacement Value $ 42,684,201

CRV/GSF ($/Sq Ft) $241.29 / Sq Ft

1.6 SUMMARY OF F INDINGS

This report represents summary-level findings for the Facility Condition Assessment. The deficiencies identified in this assessment can be combined with potential new construction requirements to develop an overall Long-Term Capital Needs Plan that can be the basis for a facility wide capital improvement funding strategy. Key findings from the Assessment include:

Key Finding Metric

Current Year Facility Condition Index

0.24%

Property Replacement Value (in Current Dollars)

$42,684,201

Current Year Capital Needs (included in FCI)

$101,185

Year 1 to Year 5 Capital Needs $597,118

5 Year FCI (Year 1-5 Needs/CRV)

1.40%

Year 1 to Year 10 Capital Needs $2,532,493

10 Year FCI (Year 1-10 Needs/CRV)

5.93%

C21

Hayat Brown LLC Page 9 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.7 FACILITY CONDITION INDEX

The Facility Condition Index (FCI) gives an indication of a building’s or portfolio’s overall state of condition. It is a widely recognized metric for benchmarking in the real estate industry. By definition, THE FCI is defined as the ratio of Deferred Maintenance Cost to the Current Building Replacement Value (CRV) of the property.

This CRV is based on the building type from the online Whitestone Facility Maintenance and Repair Cost Library (Costlabs) as of 1 September 2017 (a national recognized publication used in thousands on condition assessments throughout the country). Typically, the FCI is calculated using only the current condition values, not taking into account the future needs identified in the life cycle evaluation or building enhancements or programmatic upgrades that may be identified in a scoping or design process. Accounting principles indicate that a value of 65%, or the “rule of two-thirds”, be utilized for the FCI threshold for identifying potential replacement candidates. Once the current repair costs reach 65%, or roughly two-thirds of the full replacement value of the estimated cost to replace a facility, it may not be prudent to continue to fund repairs. In cases where aggressive facilities planning is expected to be necessary, this threshold may be adjusted to address more pressing need.

C21

Hayat Brown LLC Page 10 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

The Chart below indicates the cumulative effects of the FCI ratio over the study period assuming the required

funds and expenditures are NOT provided to address the identified works and deferred maintenance each year.

Year Deferred Maint. (Carried Forward)

Current Year Cost (Anticipated)

Total Deferred Maint.

FCI

2018 $0 $101,185 $101,185 0.24%

2019 $ 101,185 $326,862 $428,048 1%

2020 $ 428,048 $55,120 $483,168 1.13%

2021 $ 483,168 $0 $483,168 1.13%

2022 $ 483,168 $112,372 $595,540 1.4%

2023 $ 595,540 $0 $595,540 1.4%

2024 $ 595,540 $13,204 $608,744 1.43%

2025 $ 608,744 $146,539 $755,283 1.77%

2026 $ 755,283 $16,099 $771,381 1.81%

2027 $ 771,381 $1,759,534 $2,530,916 5.93%

C21

Hayat Brown LLC Page 11 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.8 EXPENDITURE FORECAST

Expenditure Forecast – Included in FCI

ElementNo.

ActionsLast

AssignedCondition

EUL*or

ReplacementCycle (Yrs)

RUL**(Yrs)

Qty. Units Unit Cost Plan Type 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total***

$ 0 1 2 3 4 5 6 7 8 9

A10 FOUNDATIONSA1011 Repair Foundation Wall Good 0 0 50.00 SF $11.07 Deferred Maintenance $554 $554A1032 Repair Concrete Slab Good 0 0 700.00 SF $10.23 Deferred Maintenance $7,161 $7,161

$7,715 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,715

B20 EXTERIOR ENCLOSUREB20 Repair Soffit Ceiling Good 0 0 75.00 SF $7.32 Deferred Maintenance $549 $549

$549 $0 $0 $0 $0 $0 $0 $0 $0 $0 $549

C20 STAIRS

C2011Replace Exterior Concrete Stairs at Softball Field

Poor 50 0 1,269.00 SF $37.48 Deferred Maintenance $47,556 $47,556

C2011 Repair Concrete, Exterior Stairs and coping Fair - Good 0 0 1.00 LS $1,500.00 Deferred Maintenance $1,500 $1,500

C30 INTERIOR FINISHESC3025 Replace Carpet Flooring - Theater Wing Fair - Good 8 7 7,296.00 SF $5.98 Capital Replacement $43,615 $43,615C3025 Replace Carpet Flooring Fair - Good 8 7 17,217.00 SF $5.98 Capital Replacement $102,923 $102,923C3032 Replace Acoustical Tile Ceiling Good 0 0 1,500.00 SF $3.10 Deferred Maintenance $4,650 $4,650

$53,706 $0 $0 $0 $0 $0 $0 $146,539 $0 $0 $200,244

D20 PLUMBINGD2018 Replace Fountain, Wall Mount Fair - Good 15 9 176,900.00 SF $0.20 Capital Replacement $35,380 $35,380

D2021Replace backflow preventer RPZ in Janitorial Closet 333

Good 0 0 1.00 EA $2,000.00 Deferred Maintenance $2,000 $2,000

D2023Replace Water Heater, Gas, Non-condensing, 300 MBH input

Fair - Good 15 9 1.00 Each $13,211.47 Capital Replacement $13,211 $13,211

D30 HVAC

D3032Replace DX Split Outdoor Unit, ~1.5 Ton, Fitness Office 127 Service

Fair - Good 15 9 1.00 EA $8,354.05 Capital Replacement $8,354 $8,354

D3032Replace DX Outdoor Unit, Multi-Split, 3 Ton, High School Common Area Service

Fair - Good 15 9 1.00 EA $5,967.18 Capital Replacement $5,967 $5,967

D3032Replace DX Split Outdoor Unit, 1.5 Ton, Server Room 204-B Service

Fair - Good 15 9 1.00 EA $7,757.33 Capital Replacement $7,757 $7,757

D3041Replace DX Split Indoor Unit, ~1.5 Ton, Ductless

Fair - Good 15 9 1.00 EA $2,770.38 Capital Replacement $2,770 $2,770

D3041Replace DX Split Indoor Unit, ~1.5 Ton, Ductless

Fair 15 9 1.00 EA $2,770.38 Capital Replacement $2,770 $2,770

D3041Replace DX Split Indoor Unit, ~1.5 Ton, Ductless

Fair - Good 15 9 2.00 EA $2,770.38 Capital Replacement $5,541 $5,541

D3041Replace Variable Air Volume (VAV) Unit, 400 CFM Average

Fair - Good 15 9 98.00 EA $3,761.11 Capital Replacement $368,589 $368,589

D3068Replace Building Controls - Throughout except Gymnasium South Side Area and Theather adjacent rooms

Fair - Good 15 9 169,961.00 SF $3.81 Capital Replacement $647,551 $647,551

D50 ELECTRICAL SYSTEMSD5031 Replace Public Address System Fair - Good 15 9 176,900.00 SF $1.24 Capital Replacement $219,356 $219,356D5038 Replace Card Reader Fair - Good 10 8 14.00 Each $1,149.90 Capital Replacement $16,099 $16,099D5038 Replace Intrusion Detection Fair - Good 15 9 176,900.00 SF $1.15 Capital Replacement $203,435 $203,435

$2,000 $0 $0 $0 $0 $0 $0 $0 $16,099 $1,520,683 $1,538,781

E10 EQUIPMENT

D. SERVICES SUB-TOTALSE. EQUIPMENT & FURNISHING

C. INTERIORS SUB-TOTALSD. SERVICES

A. SUBSTRUCTURE SUB-TOTALSB. SHELL

B. SHELL SUB-TOTALSC. INTERIORS

10 YEAR CAPITAL EXPENDITURE FORECAST

Capital City PCS (Lower, Middle, and High Schools)100 Peabody St NW, Washington, DC, 4

A. SUBSTRUCTURE

Powered by iPlan © 2013 4tell™ Solutions, LP.All Rights Reserved. 4tell, iPlan (patent pending) Building Blocks, and Innovation for the Built Environment are trademarks of 4tell™ Solutions, LP Run Date: March 13, 2018

E1027 Replace Sink, Epoxy Resin, Laboratory Fair - Good 15 9 16.00 EA $528.23 Capital Replacement $8,452 $8,452

$0 $0 $0 $0 $0 $0 $0 $0 $0 $8,452 $8,452

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

G20 SITE IMPROVEMENTS

G2022Replace Parking Lot, Paving, Concrete, Driveways

Poor 40 2 6,500.00 SF $8.48 Capital Replacement $55,120 $55,120

G2031 Repair Concrete Sidewalk Fair - Good 0 0 780.00 SF $28.94 Deferred Maintenance $22,573 $22,573

G2031Repair Clay Brick/Masonry Paver Sidewalk, Exterior

Good 0 0 100.00 SF $12.26 Deferred Maintenance $1,226 $1,226

G2041 Replace Chain Link Fence 8’ Fair 20 6 265.00 LF $43.33 Capital Replacement $11,482 $11,482G2041 Repair Retaining Wall, Brick/Stone Fair - Good 0 0 200.00 SF $11.39 Deferred Maintenance $2,278 $2,278G2041 Replace Chain Link Fence 4’ Fair 20 6 96.00 LF $17.93 Capital Replacement $1,721 $1,721G2042 Repair expansion joints at retaining wall Fair - Good 0 0 1.00 LS $10,000.00 Deferred Maintenance $10,000 $10,000

G2042Repair Retaining Wall, Brick/Stone (per SF Face)

Fair - Good 0 0 100.00 SF $11.39 Deferred Maintenance $1,139 $1,139

G2042 Replace Retaining Wall, Wood Tie Poor 40 1 100.00 LF $184.57 Capital Replacement $18,457 $18,457

G2047Replace Playing Fields, Basketball Court, Complete

Poor - Fair 25 4 1.00 EA $28,000.00 Capital Replacement $28,000 $28,000

G2047 Replace Soccer Field Poor 25 1 1.00 EA ######### Capital Replacement $211,728 $211,728

G2047Replace Playing Fields, Tennis Courts, Asphaltic Concrete

Poor - Fair 20 4 1.00 EA $84,372.12 Capital Replacement $84,372 $84,372

G2047 Replace Playing Fields, Softball Field Poor 25 1 1.00 EA $96,677.58 Capital Replacement $96,678 $96,678G2054 Replace Landscaping Fair - Good 25 9 192,000.00 SF $1.20 Capital Replacement $230,400 $230,400

$37,216 $326,862 $55,120 $0 $112,372 $0 $13,204 $0 $0 $230,400 $775,175

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$101,185 $326,862 $55,120 $0 $112,372 $0 $13,204 $146,539 $16,099 $1,759,534 $2,530,9160.24% 0.77% 0.13% 0.00% 0.26% 0.00% 0.03% 0.34% 0.04% 4.12%

$42,684,201Notes

*

**

***

- EUL is the Estimated Useful Life of an Asset- RUL is the Remaining Useful Life of an Asset- Non-Escalated and Non-Inflated Adusted Dollars

† - FCI Formula (As Currently Programmed):

FCI† By Year

CRV***

(Deferred Maintenance + Plant Adaptation + Capital Replacement)/(Building Replacement Value)

G. BUILDING SITEWORK

G. BUILDING SITEWORK SUB-TOTALSZ. GENERALZ. GENERAL SUB-TOTALS

Expenditure Totals per Year

E. EQUIPMENT & FURNISHING SUB-TOTALSF. SPECIAL CONSTRUCTION AND DEMOLITIONF. SPECIAL CONSTRUCTION AND DEMOLITION SUB-TOTALS

Powered by iPlan © 2013 4tell™ Solutions, LP.All Rights Reserved. 4tell, iPlan (patent pending) Building Blocks, and Innovation for the Built Environment are trademarks of 4tell™ Solutions, LP Run Date: March 13, 2018

ElementNo.

ActionsLast

AssignedCondition

EUL*or

ReplacementCycle (Yrs)

RUL**(Yrs)

Qty. Units Unit Cost Priority Plan Type 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total***

$ 0 1 2 3 4 5 6 7 8 9

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

C20 STAIRS

C2011 Repair Concrete, Exterior Stairs Good 0 0 20.00 SF $3.88 Priority 3Routine Maint Minor

Repairs$78 $78

$78 $0 $0 $0 $0 $0 $0 $0 $0 $0 $78

D20 PLUMBING

D2021Perform inspection and certification of backflow preventers

Good 0 0 1.00 LS $500.00 Priority 2Predictive Maint Test

Inspec$500 $500

D30 HVAC

D3021 Replace pressure relief valve Fair - Good 0 0 1.00 EA $1,000.00 Priority 2Routine Maint Minor

Repairs$1,000 $1,000

$1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

$1,578 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,578$42,684,201

Notes

*

**

***

- EUL is the Estimated Useful Life of an Asset- RUL is the Remaining Useful Life of an Asset- Non-Escalated and Non-Inflated Adusted Dollars

CRV***

F. SPECIAL CONSTRUCTION AND DEMOLITION SUB-TOTALSG. BUILDING SITEWORKG. BUILDING SITEWORK SUB-TOTALSZ. GENERALZ. GENERAL SUB-TOTALS

Expenditure Totals per Year

D. SERVICES SUB-TOTALSE. EQUIPMENT & FURNISHINGE. EQUIPMENT & FURNISHING SUB-TOTALSF. SPECIAL CONSTRUCTION AND DEMOLITION

B. SHELLB. SHELL SUB-TOTALSC. INTERIORS

C. INTERIORS SUB-TOTALSD. SERVICES

10 YEAR ROUTINE MAINTENANCE EXPENDITURE FORECAST

Capital City PCS (Lower, Middle, and High Schools)100 Peabody St NW, Washington, DC, 4

A. SUBSTRUCTUREA. SUBSTRUCTURE SUB-TOTALS

Powered by iPlan © 2013 4tell™ Solutions, LP.All Rights Reserved. 4tell, iPlan (patent pending) Building Blocks, and Innovation for the Built Environment are trademarks of 4tell™ Solutions, LP Run Date: March 13, 2018

C21

Hayat Brown LLC Page 13 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.9 ASSETS OBSERVED

Assets observed at the site are provided in this Section and sorted by the modified Uniformat II coding indexed as applicable. See the listing below for the sequence.

▪ A SUBSTRUCTURE A10 Foundations A20 Basement Construction

▪ B SHELL B10 SuperStructure B20 Exterior Enclosure B30 Roofing

▪ C INTERIORS C10 Interior Construction C20 Stairs C30 Interior Finishes

▪ D SERVICES D10 Conveying Systems D20 Plumbing D30 HVAC D40 Fire Protection Systems D50 Electrical Systems

▪ E EQUIPMENT & FURNISHING E10 Equipment E20 Furnishings

▪ F SPECIAL CONSTRUCTION AND DEMOLITION F10 Special Construction F20 Selective Demolition

▪ G BUILDING SITEWORK G10 Site Preparation G20 Site Improvements G30 Site Civil/Mechanical Utilities G40 Site Electrical Utilities G90 Other Site Construction

▪ Z GENERAL Z10 General Requirements Z20 Bidding Requirements, Contract Forms, Conditions Z90 Project Cost Estimate

C21

Hayat Brown LLC Page 14 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.10 PLANNING HORIZON CATEGORY NEEDS : CURRENT YEAR TO YEAR 10

The deficiencies are sorted by categories which define briefly the reason the need exists. A requirement may have more than one applicable category. The category is selected based on the need priority, the most heavily impacted building system and the category with the greatest life safety significance.

Plan Types Total Cost

Deferred Maintenance $101,185

Routine Maint Minor Repairs $1,078

Capital Replacement $2,429,730

Predictive Maint Test Inspec $500

Total $2,532,493

The following is a list of the Plan Types with a brief description: Capital Replacement Indicates the need for replacement or major refurbishment of an asset, typically based on age and use but required in the future within a reasonable planning horizon. Deferred Maintenance Indicates a deficiency or a conditional, performance, or failure related issue with an elemental component that has persisted past a reasonable time frame and should have been remedied prior to the time of assessment.

C21

Hayat Brown LLC Page 15 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Routine Maint. Minor Repairs Indicates the need for normal or ongoing minor component renewal or repair, generally required to sustain the anticipated life cycle of the asset. Plant Adaptation Indicates the need for alterations to the property for improvement in safety and security, ADA, hazardous materials abatement, green roof and LEED requirements. Note that the Category selected is the primary factor understood to be the cause for the recommendation. However, there may be more than one driver of the need for repair, replacement, or upgrade.

C21

Hayat Brown LLC Page 16 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.11 BUILDING SYSTEM NEEDS : IMMEDIATE

Building Systems Estimated Costs Percentage of Total Cost

A SubStructure $7,715 7.5%

B Shell $549 0.5%

C Interiors $53,783 52.3%

D Services $3,500 3.4%

G Building Sitework $37,216 36.2%

Total $102,763 100.0%

C21

Hayat Brown LLC Page 17 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.12 BUILDING SYSTEM NEEDS : YEAR 2 - YEAR 10

Building Systems Estimated Costs Percentage of Total Cost

C Interiors $146,539 6.0%

D Services $1,536,781 63.3%

E Equipment & Furnishing $8,452 0.4%

G Building Sitework $737,958 30.4%

Total $2,429,730 100.0%

C21

Hayat Brown LLC Page 18 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

1.13 BUILDING SYSTEM NEEDS : 10 YEAR FORECAST

Building Systems Estimated Costs Percentage of Total Cost

A SubStructure $7,715 0.3%

B Shell $549 0.0%

C Interiors $200,322 7.9%

D Services $1,540,281 60.8%

E Equipment & Furnishing $8,452 0.3%

G Building Sitework $775,175 30.6%

Total $2,532,493 100.0%

C21

Hayat Brown LLC Page 19 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

A S U B S T R U C T U R E S Y S T E M S

A10 FOUNDATIONS

Item Description

A1011 Wall Foundations Wall Foundations, Footings

Condition Good

RUL 40

Plan Type Capital Replacement

Quantity 10578

Unit of Measure SF

Unit Cost $10.60

Type Component Description Plan Type Year Expenditures

($)

A1011 Repair Foundation Wall Deferred

Maintenance 2018 $554

C21

Hayat Brown LLC Page 20 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

A1032 Structural Slab on Grade Slab on Grade

Condition Good

RUL 40

Plan Type Capital Replacement

Quantity 54040

Unit of Measure SF

Unit Cost $6.47

C21

Hayat Brown LLC Page 21 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

A1032 Repair Concrete Slab Deferred

Maintenance 2018 $7,161

C21

Hayat Brown LLC Page 22 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

B S H E L L S Y S T E M S

B10 SUPERSTRUCTURE

Item Description

B10 SuperStructure SuperStructure

Condition Good

RUL 40

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $13.40

C21

Hayat Brown LLC Page 23 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

B20 EXTERIOR ENCLOSURE

Item Description

B20 Exterior Enclosure Metal Soffits

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 2511

Unit of Measure SF

Unit Cost $14.63

C21

Hayat Brown LLC Page 24 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B20 Exterior Enclosure Cementitious Soffits

Condition Good

RUL 44

Plan Type Capital Replacement

Quantity 2511

Unit of Measure SF

Unit Cost $7.87

Comments

C21

Hayat Brown LLC Page 25 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

B20 Repair Soffit Ceiling Deferred

Maintenance 2018 $549

C21

Hayat Brown LLC Page 26 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2011 Exterior Wall Construction Concrete Exterior Walls

Condition Good

RUL 42

Plan Type Capital Replacement

Quantity 6300

Unit of Measure SF

Unit Cost $17.23

Comments

C21

Hayat Brown LLC Page 27 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2011 Exterior Wall Construction Exterior Brick Wall - Existing Building

Condition Good

RUL 17

Location Existing Building

Plan Type Capital Replacement

Quantity 34136

Unit of Measure SF

Unit Cost $34.40

C21

Hayat Brown LLC Page 28 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 29 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2013 Exterior Louvers, Screens, and Fencing Aluminum Louver - Small Units

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 33

Unit of Measure EA

Unit Cost $394.74

C21

Hayat Brown LLC Page 30 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2013 Exterior Louvers, Screens, and Fencing Aluminum Louvers - Mid-sized Units

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 76

Unit of Measure Each

Unit Cost $523.19

C21

Hayat Brown LLC Page 31 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2013 Exterior Louvers, Screens, and Fencing Aluminum Louvers - Large Units

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 48

Unit of Measure Each

Unit Cost $697.59

C21

Hayat Brown LLC Page 32 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2021 Windows Aluminum Fixed Window, Larger Units

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 13

Unit of Measure EA

Unit Cost $701.98

C21

Hayat Brown LLC Page 33 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2021 Windows Aluminum Operable Windows

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 406

Unit of Measure EA

Unit Cost $1,922.92

Comments

C21

Hayat Brown LLC Page 34 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2021 Windows Aluminum Fixed Window, Small

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 68

Unit of Measure EA

Unit Cost $436.39

C21

Hayat Brown LLC Page 35 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2021 Windows Aluminum Fixed Window, Mid-sized Window

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 59

Unit of Measure EA

Unit Cost $581.85

C21

Hayat Brown LLC Page 36 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2022 Curtain Walls Curtain Wall

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 1320

Unit of Measure SF

Unit Cost $110

C21

Hayat Brown LLC Page 37 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2023 Storefronts Storefronts - Glazed Metal Framed

Condition Good

RUL 29

Plan Type Capital Replacement

Quantity 249

Unit of Measure SF

Unit Cost $27.43

C21

Hayat Brown LLC Page 38 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2031 Glazed Doors & Entrances Exterior Aluminum Frame Fully Glazed Doors

Condition Good

RUL 44

Plan Type Capital Replacement

Quantity 28

Unit of Measure EA

Unit Cost $1,273.14

C21

Hayat Brown LLC Page 39 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B2032 Solid Exterior Doors Exterior Steel Doors

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 40

Unit of Measure Each

Unit Cost $887.04

C21

Hayat Brown LLC Page 40 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

B30 ROOFING

Item Description

B3011 Roof Finishes Roof Coverings, Built-up Roof

Condition Good

RUL 29

Plan Type Capital Replacement

Quantity 10500

Unit of Measure SF

Unit Cost $10.46

C21

Hayat Brown LLC Page 41 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B3011 Roof Finishes Roof Coverings, Inverted Membrane System

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 53200

Unit of Measure SF

Unit Cost $11.21

C21

Hayat Brown LLC Page 42 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B3011 Roof Finishes Roof Coverings, Adhered Membrane, EPDM - New Addition

Condition Good

RUL 21

Plan Type Capital Replacement

Quantity 9500

Unit of Measure SF

Unit Cost $14.84

C21

Hayat Brown LLC Page 43 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

B3021 Glazed Roof Openings Roof Skylight

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $819.89

Comments

C21

Hayat Brown LLC Page 44 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C I N T E R I O R S S Y S T E M S

C10 INTERIOR CONSTRUCTION

Item Description

C1011 Fixed Partitions Interior Partitions Concrete Block

Condition Good

RUL 20

Plan Type Capital Replacement

Quantity 48181

Unit of Measure SF

Unit Cost $9.23

C21

Hayat Brown LLC Page 45 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1017 Interior Windows & Storefronts Interior Windows & Storefronts

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 545

Unit of Measure SF

Unit Cost $82.29

C21

Hayat Brown LLC Page 46 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 47 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Wood, Solid Interior Doors

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 162

Unit of Measure EA

Unit Cost $1,343.55

C21

Hayat Brown LLC Page 48 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Steel, Painted, w/ Safety Glass, Interior Door

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 9

Unit of Measure EA

Unit Cost $1,195.66

Comments

C21

Hayat Brown LLC Page 49 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Fully Glazed Interior Door

Condition Good

RUL 39

Plan Type Capital Replacement

Quantity 2

Unit of Measure Each

Unit Cost $2,004.26

C21

Hayat Brown LLC Page 50 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Wood/Glass Doors

Condition Good

RUL 37

Plan Type Capital Replacement

Quantity 123

Unit of Measure EA

Unit Cost $1,876.30

C21

Hayat Brown LLC Page 51 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Steel, Interior Door

Condition Good

RUL 37

Plan Type Capital Replacement

Quantity 2

Unit of Measure Each

Unit Cost $857.53

C21

Hayat Brown LLC Page 52 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C1021 Interior Doors Fire Doors

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 8

Unit of Measure EA

Unit Cost $1,382.34

C21

Hayat Brown LLC Page 53 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C20 STAIRS

Item Description

C2011 Regular Stairs Interior Utility Metal Stairs

Condition Good

RUL 32

Plan Type Capital Replacement

Quantity 24

Unit of Measure Riser

Unit Cost $703.60

C21

Hayat Brown LLC Page 54 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C2011 Regular Stairs Exterior Concrete Stairs

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 1269

Unit of Measure SF

Unit Cost $37.48

C21

Hayat Brown LLC Page 55 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

C2011 Repair Concrete, Exterior Stairs and coping Deferred

Maintenance 2018 $1,500

C21

Hayat Brown LLC Page 56 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C2011 Regular Stairs Exterior Concrete Stairs, New

Condition Good

RUL 44

Plan Type Capital Replacement

Quantity 210

Unit of Measure SF

Unit Cost $37.48

Type Component Description Plan Type Year Expenditures

($)

C2011 Repair Concrete, Exterior Stairs Routine

Maint Minor Repairs

2018 $78

C21

Hayat Brown LLC Page 57 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 58 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C2011 Regular Stairs Exterior Concrete Stairs at Softball Field

Condition Poor

RUL 0

Plan Type Deferred Maintenance

Quantity 1269

Unit of Measure SF

Unit Cost $37.48

Type Component Description Plan Type Year Expenditures

($)

C2011 Replace Exterior Concrete Stairs at Softball Field Deferred

Maintenance 2018 $47,556

C21

Hayat Brown LLC Page 59 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C2011 Regular Stairs Interior Stairs, Metal, Painted

Condition Good

RUL 44

Plan Type Capital Replacement

Quantity 7936

Unit of Measure SF

Unit Cost $35.88

C21

Hayat Brown LLC Page 60 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C2014 Stair Handrails and Balustrades Exterior Railing

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 292

Unit of Measure LF

Unit Cost $46.40

C21

Hayat Brown LLC Page 61 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C30 INTERIOR F INISHES

Item Description

C3012 Wall Finishes to Interior Walls Ceramic Interior Wall - Theater Wing

Condition Good

RUL 39

Location New Addition

Plan Type Capital Replacement

Quantity 685

Unit of Measure SF

Unit Cost $12.70

C21

Hayat Brown LLC Page 62 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3012 Wall Finishes to Interior Walls Ceramic Tile, Interior Wall Finish

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 7152

Unit of Measure SF

Unit Cost $12.70

C21

Hayat Brown LLC Page 63 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Ceramic Tile Flooring - Theater Wing

Condition Good

RUL 39

Plan Type Capital Replacement

Quantity 529

Unit of Measure SF

Unit Cost $13.49

C21

Hayat Brown LLC Page 64 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Ceramic Tile Flooring

Condition Good

RUL 34

Plan Type Capital Replacement

Quantity 4041

Unit of Measure SF

Unit Cost $13.49

C21

Hayat Brown LLC Page 65 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Athletic Wood Flooring

Condition Good

RUL 37

Plan Type Capital Replacement

Quantity 7776

Unit of Measure SF

Unit Cost $14.84

C21

Hayat Brown LLC Page 66 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Floor Finish, Vinyl Sheet

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 1406

Unit of Measure SF

Unit Cost $9.77

C21

Hayat Brown LLC Page 67 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Vinyl Tile Flooring

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 121902

Unit of Measure SF

Unit Cost $3.04

C21

Hayat Brown LLC Page 68 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3024 Flooring Floor Finish, Tile, Rubber

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 1178

Unit of Measure SF

Unit Cost $7.40

C21

Hayat Brown LLC Page 69 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3025 Carpeting Carpet Flooring - Theater Wing

Condition Fair - Good

RUL 7

Plan Type Capital Replacement

Quantity 7296

Unit of Measure SF

Unit Cost $5.98

Comments

Type Component Description Plan Type Year Expenditures

($)

C3025 Replace Carpet Flooring - Theater Wing Capital

Replacement 2025 $43,615

C21

Hayat Brown LLC Page 70 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3025 Carpeting Carpet Flooring

Condition Fair - Good

RUL 7

Plan Type Capital Replacement

Quantity 17217

Unit of Measure SF

Unit Cost $5.98

Type Component Description Plan Type Year Expenditures

($)

C3025 Replace Carpet Flooring Capital

Replacement 2025 $102,923

C21

Hayat Brown LLC Page 71 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3031 Ceiling Finishes Gypsum Board, Finished Ceiling - Existing Bldg.

Condition Good

RUL 34

Location Existing Building

Plan Type Capital Replacement

Quantity 16726

Unit of Measure SF

Unit Cost $5.27

C21

Hayat Brown LLC Page 72 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3032 Suspended Ceilings Acoustical Tile Ceiling

Condition Good

RUL 19

Plan Type Capital Replacement

Quantity 120039

Unit of Measure SF

Unit Cost $2.83

Type Component Description Plan Type Year Expenditures

($)

C3032 Replace Acoustical Tile Ceiling Deferred

Maintenance 2018 $4,650

C21

Hayat Brown LLC Page 73 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 74 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

C3032 Suspended Ceilings Acoustical Tile Ceiling - Theater Wing

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 13530

Unit of Measure SF

Unit Cost $2.83

C21

Hayat Brown LLC Page 75 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

D S E R V I C E S S Y S T E M S

D10 CONVEYING SYSTEMS

Item Description

D1011 Passenger Elevators Elevator, Traction, 3,500 Lbs

Condition Good

RUL 24

Location Building

Plan Type Capital Replacement

Quantity 1

Unit of Measure Each

Unit Cost $135,408.41

Elevator Elevator

C21

Hayat Brown LLC Page 76 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Elevator Elevator Controls in Elevator Control Room

C21

Hayat Brown LLC Page 77 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D1091 Dumbwaiters Dumbwaiter, 2~5 Storeys

Condition Good

RUL 19

Location Library

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $15,129

Dumbwaiter Dumbwaiter

C21

Hayat Brown LLC Page 78 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

D20 PLUMBING

Item Description

D2010.0 Water_Fixtures Typical Plumbing Fixtures

Condition Good

RUL 24

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $7.33

Urinal Toilet

Lavatory/Sinks

C21

Hayat Brown LLC Page 79 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Toilet Lavatory/Sinks

Bathroom Fixtures

C21

Hayat Brown LLC Page 80 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2014 Sinks Commercial Grade Kitchen Sinks, multiple compartments

Condition Good

RUL 34

Location Warming Kitchen

Plan Type Capital Replacement

Quantity 3

Unit of Measure Each

Unit Cost $1,007.80

Kitchen Sink

C21

Hayat Brown LLC Page 81 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2016 Wash Fountains Emergency Eye wash and Shower - Plumbed

Condition Good

RUL 19

Location Science Lab 309

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $3,438.05

Eye wash

C21

Hayat Brown LLC Page 82 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2018 Drinking Fountains and Coolers Fountain, Wall Mount

Condition Fair - Good

RUL 9

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $0.20

Drinking Fountain Drinking Fountain

Type Component Description Plan Type Year Expenditures

($)

D2018 Replace Fountain, Wall Mount Capital

Replacement 2027 $35,380

C21

Hayat Brown LLC Page 83 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2021 Cold Water Service Domestic Water Distribution Piping

Condition Good

RUL 39

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $4.52

Leaky RPZ in Janitorial Closet 333 RPZ at Boilers Make-up Water Piping

Water Main in Boiler Room Domestic Water Piping, Circulating Pumps & Mixing Valve in Boiler Room

C21

Hayat Brown LLC Page 84 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Piping Expired RPZ inspection tag in

Boiler Room

Type Component Description Plan Type Year Expenditures

($)

D2021 Perform inspection and certification of backflow

preventers

Predictive Maint Test

Inspec 2018 $500

D2021 Replace backflow preventer RPZ in Janitorial Closet

333 Deferred

Maintenance 2018 $2,000

C21

Hayat Brown LLC Page 85 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2022 Hot Water Service Insta-hot Under Counter Water Heater (no storage tank)

Condition Good

RUL 34

Location Warming Kitchen

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $1,280.13

Water Heater

C21

Hayat Brown LLC Page 86 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2023 Domestic Water Supply Equipment Water Flow Meter, 4.00 In

Condition Good

RUL 19

Location Boiler Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $5,025.85

Water Meter

C21

Hayat Brown LLC Page 87 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2023 Domestic Water Supply Equipment Water Heater (Boiler), Gas, 801~1,400 MBH

Condition Good

RUL 19

Location Boiler Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $42,853.38

Boiler Boiler

C21

Hayat Brown LLC Page 88 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2023 Domestic Water Supply Equipment Water Heater, Gas, Non-condensing, 300 MBH input

Condition Fair - Good

RUL 9

Location Boiler Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure Each

Unit Cost $13,211.47

Water Heater Water Heater

Type Component Description Plan Type Year Expenditures

($)

D2023 Replace Water Heater, Gas, Non-condensing, 300

MBH input Capital

Replacement 2027 $13,211

C21

Hayat Brown LLC Page 89 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2031 Waste Piping Waste Piping

Condition Good

RUL 19

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $6.51

C21

Hayat Brown LLC Page 90 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D2041 Pipe & Fittings Rainwater Drainage Piping

Condition Good

RUL 19

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $2.68

C21

Hayat Brown LLC Page 91 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

D30 HVAC

Item Description

D3012 Gas Supply System Gas Supply and Distribution, Laboratory

Condition Good

RUL 37

Location Science Lab 309

Plan Type Capital Replacement

Quantity 1

Unit of Measure LS

Unit Cost $25,000

Science Lab Gas Science Lab Gas

C21

Hayat Brown LLC Page 92 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3012 Gas Supply System Gas Distribution Piping, Gas Packaged / Rooftop Units service

Condition Good

RUL 47

Location From Basement to Gymnasium Roof, Lower Roof North Side adjacent to Gymnasium and Lower Roof adjacent to Theater

Plan Type Capital Replacement

Quantity 26300

Unit of Measure SF

Unit Cost $1.18

Gas piping at RTU-2 Gas piping at RTU-1

Gas piping at Theater RTU

C21

Hayat Brown LLC Page 93 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3012 Gas Supply System Gas Distribution Piping, Boilers and Domestic Water Heaters Service

Condition Good

RUL 37

Location Boiler Room

Plan Type Capital Replacement

Quantity 107621

Unit of Measure SF

Unit Cost $1.18

Gas piping Gas train at boiler

C21

Hayat Brown LLC Page 94 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3016 Solar Energy System Solar Panels

Condition Fair - Good

RUL 14

Location Roof

Plan Type Capital Replacement

Quantity 1143

Unit of Measure EA

Unit Cost $1,325.73

Solar System Solar System

Solar System Solar System

C21

Hayat Brown LLC Page 95 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3021 Boilers Boiler, Gas, Hot Water, 2843 MBH Net

Condition Fair - Good

RUL 12

Location Boiler Room

Plan Type Capital Replacement

Quantity 3

Unit of Measure EA

Unit Cost $72,680

Comments Boiler system installed prior major building renovation, according to building drawing provided. Installation year of Boilers and auxiliaries is estimated.

Boilers Boiler Label

Boilers Breeching Gas burners at Boilers

C21

Hayat Brown LLC Page 96 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Combustion Air Louvers Leaky relief valve by

Boiler 2

Type Component Description Plan Type Year Expenditures

($)

D3021 Replace pressure relief valve Routine

Maint Minor Repairs

2018 $1,000

C21

Hayat Brown LLC Page 97 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3022 Boiler Room Piping & Specialties Heating Hot Water/Steam Piping Syst Medium Density

Condition Fair - Good

RUL 12

Location Boiler Room

Plan Type Capital Replacement

Quantity 3000

Unit of Measure SF

Unit Cost $16.38

Hydronic Heating Expansion Tanks Hydronic Heating Pumps

Hydronic Heating - Boilers Piping

C21

Hayat Brown LLC Page 98 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3023 Auxiliary Equipment Heat Exch, Water > Water, Plate/Frame, 381~620 GPM

Condition Good

RUL 29

Location Boiler Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $35,329.84

Comments Plate & Frame Heat Exchanger exchanges heat between boiler system loop and condenser water loop.

Heat Exchanger

C21

Hayat Brown LLC Page 99 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3031 Chilled Water Systems Cooling Tower, Closed Circuit, 301 Ton

Condition Fair - Good

RUL 14

Location Main Roof

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $167,585.33

Cooling Tower Cooling Tower

Cooling Tower Chemical Treatment, Stair 5 Roof Level

C21

Hayat Brown LLC Page 100 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3032 Direct Expansion Systems DX Split Outdoor Unit, ~1.5 Ton, Fitness Office 127 Service

Condition Fair - Good

RUL 9

Location Building Exterior

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $8,354.05

Split Unit

Type Component Description Plan Type Year Expenditures

($)

D3032 Replace DX Split Outdoor Unit, ~1.5 Ton, Fitness

Office 127 Service Capital

Replacement 2027 $8,354

C21

Hayat Brown LLC Page 101 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3032 Direct Expansion Systems DX Split Outdoor Unit, 1.5 Ton, Server Room 204-B Service

Condition Fair - Good

RUL 9

Location Main Roof

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $7,757.33

Split Unit Split Unit

Type Component Description Plan Type Year Expenditures

($)

D3032 Replace DX Split Outdoor Unit, 1.5 Ton, Server Room

204-B Service Capital

Replacement 2027 $7,757

C21

Hayat Brown LLC Page 102 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3032 Direct Expansion Systems DX Outdoor Unit, Multi-Split, 3 Ton, High School Common Area Service

Condition Fair - Good

RUL 9

Location Lower Roof adjacent to Theather

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $5,967.18

Comments

Split Unit Split Unit

Type Component Description Plan Type Year Expenditures

($)

D3032 Replace DX Outdoor Unit, Multi-Split, 3 Ton, High

School Common Area Service Capital

Replacement 2027 $5,967

C21

Hayat Brown LLC Page 103 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3032 Direct Expansion Systems DX Outdoor Unit, Ave. 1.43 Ton, Theater Rooms Service

Condition Fair - Good

RUL 13

Location Lower Roof adjacent to Theather

Plan Type Capital Replacement

Quantity 4

Unit of Measure EA

Unit Cost $8,354.05

HVAC Unit HVAC Unit

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 104 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

HVAC Unit

C21

Hayat Brown LLC Page 105 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Variable Air Volume (VAV) Unit, 400 CFM Average

Condition Fair - Good

RUL 9

Location Areas served by DOAS RTUs (Main Building)

Plan Type Capital Replacement

Quantity 98

Unit of Measure EA

Unit Cost $3,761.11

Variable Air Volume (VAV) Unit Variable Air Volume (VAV) Unit

Type Component Description Plan Type Year Expenditures

($)

D3041 Replace Variable Air Volume (VAV) Unit, 400 CFM

Average Capital

Replacement 2027 $368,589

C21

Hayat Brown LLC Page 106 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems DX Split Indoor Unit, ~1.5 Ton, Ductless

Condition Fair - Good

RUL 9

Location High School Common Area

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $2,770.38

Fan Coil Unit

Type Component Description Plan Type Year Expenditures

($)

D3041 Replace DX Split Indoor Unit, ~1.5 Ton, Ductless Capital

Replacement 2027 $5,541

C21

Hayat Brown LLC Page 107 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems DX Split Indoor Unit, ~1.5 Ton, Ductless

Condition Fair - Good

RUL 9

Location Server Room 204-B

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $2,770.38

Fan Coil Unit

Type Component Description Plan Type Year Expenditures

($)

D3041 Replace DX Split Indoor Unit, ~1.5 Ton, Ductless Capital

Replacement 2027 $2,770

C21

Hayat Brown LLC Page 108 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems DX Split Indoor Unit, ~1.5 Ton, Ductless

Condition Fair

RUL 9

Location Fitness Office 127

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $2,770.38

Fan Coil Unit

Type Component Description Plan Type Year Expenditures

($)

D3041 Replace DX Split Indoor Unit, ~1.5 Ton, Ductless Capital

Replacement 2027 $2,770

C21

Hayat Brown LLC Page 109 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems DX Split Indoor Unit, ~1.43 Ton Average

Condition Fair - Good

RUL 13

Location Theater adjacent rooms

Plan Type Capital Replacement

Quantity 4

Unit of Measure EA

Unit Cost $2,572.49

Ceiling concealed ductless unit in corridor Ceiling concealed ducted unit

Ceiling concealed ducted unit

C21

Hayat Brown LLC Page 110 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Duct Heater, Electric Reheat, VAV, 3~5 kW

Condition Fair - Good

RUL 13

Location Adjacent Area South Side to Gymnasium - Locker Rooms and others

Plan Type Capital Replacement

Quantity 6

Unit of Measure EA

Unit Cost $1,574.27

Duct Heater

C21

Hayat Brown LLC Page 111 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Air Distribution Ductwork - Main Building

Condition Good

RUL 29

Location Main Building

Plan Type Capital Replacement

Quantity 75679

Unit of Measure SF

Unit Cost $7.34

Typical exhaust ductwork in IT Closet Typical air distribution in classrooms

Ductwork at RTU

C21

Hayat Brown LLC Page 112 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Variable Air Volume (VAV) Unit, ~2,100 CFM Average

Condition Fair - Good

RUL 13

Location Theater Building

Plan Type Capital Replacement

Quantity 6

Unit of Measure EA

Unit Cost $7,982.24

Variable Air Volume (VAV) Unit

C21

Hayat Brown LLC Page 113 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Air Distribution Ductwork - Gymnasium and adjacent areas

Condition Good

RUL 33

Location Gymnasium and adjacent areas

Plan Type Capital Replacement

Quantity 18913

Unit of Measure SF

Unit Cost $4.54

Registers Ductwork

Ductwork

C21

Hayat Brown LLC Page 114 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Air Distribution Ductwork - Theatre Building

Condition Good

RUL 33

Location Theater Building

Plan Type Capital Replacement

Quantity 10000

Unit of Measure SF

Unit Cost $4.54

Ductwork in back stage rooms

C21

Hayat Brown LLC Page 115 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Energy Recovery Ventilator Unit (ERV), ~1,500 CFM

Condition Fair - Good

RUL 13

Location Mechanical Room by Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $9,086.40

Energy Recovery Unit

C21

Hayat Brown LLC Page 116 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3041 Air Distribution Systems Energy Recovery Ventilator Unit (ERV), 1250 CFM

Condition Fair - Good

RUL 14

Location Lower Roof South Side adjacent to Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $9,086.40

Energy Recovery Unit Energy Recovery

Unit

C21

Hayat Brown LLC Page 117 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3042 Exhaust Ventilation Systems Exhaust System, Fume Hood (EA), Ductwork/Fan

Condition Good

RUL 19

Location Science Lab 309

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $22,446.76

Exhaust Hood

C21

Hayat Brown LLC Page 118 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3042 Exhaust Ventilation Systems Exhaust / Ventilation, General (SF) Mid-Sized Building / Avg Density

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $1.46

Comments Majority of exhaust ventilation was renovated in 2012.

Ceiling fan in corridor Roof Exhaust Fans

C21

Hayat Brown LLC Page 119 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3045 Chilled Water Distribution Piping, Condenser Water Supply and Return

Condition Good

RUL 29

Location Throuhgout except areas served by gas RTUs

Plan Type Capital Replacement

Quantity 107621

Unit of Measure SF

Unit Cost $8.21

Comments Piping service distributes condenser water to water source heat pumps throughout, from plate & frame heat exchanger in Boiler Room and closed-circuit cooling tower on main roof. Cost includes piping, pumps and expansion tank.

Condenser water piping at Cooling Tower Condenser water

piping at Heat Pump in Gymnasium MER

Condenser water pumps in Boiler Room Condenser water pumps in Room 328

C21

Hayat Brown LLC Page 120 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Condenser Water Expansion Tank in Boiler Room

C21

Hayat Brown LLC Page 121 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3051 Terminal Self-Contained Units Unit Heater, Hydronic, 26 to 55 MBH

Condition Fair - Good

RUL 14

Location Boiler Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $1,611.62

Unit Heater

C21

Hayat Brown LLC Page 122 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3051 Terminal Self-Contained Units Unit Heater, Electric, 1~2 kW

Condition Fair - Good

RUL 14

Location Stairs, Exits and other locations

Plan Type Capital Replacement

Quantity 5

Unit of Measure EA

Unit Cost $1,095.84

Unit Heater Unit Heater

C21

Hayat Brown LLC Page 123 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3051 Terminal Self-Contained Units Unit Heater, Electric, 3~6 kW

Condition Fair - Good

RUL 14

Location Boiler Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $1,535.11

Unit Heater

C21

Hayat Brown LLC Page 124 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Heat Pump, Water Source, 30 Ton, RTU-4

Condition Fair - Good

RUL 14

Location Lower Roof East Side adjacent to Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $31,925

Comments Unit is currently out of service, however defective part has already been delivered on site and it is waiting for installation.

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 125 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Heat Pump, Water Source, 30 Ton, DOAS, RTU-1, 2, 3

Condition Fair - Good

RUL 14

Location Main Roof

Plan Type Capital Replacement

Quantity 3

Unit of Measure EA

Unit Cost $31,925

DAOS, RTU-3 DAOS, RTU-3

DAOS, RTU-1 DAOS, RTU-1

C21

Hayat Brown LLC Page 126 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

DAOS, RTU-2 DAOS, RTU-2

C21

Hayat Brown LLC Page 127 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Roof, 6.0~10.0 Ton DX Cooling, No Heat

Condition Good

RUL 19

Location Lower Roof South Side adjacent to Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $8,975

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 128 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Roof, Single Zone, 3.0~5.0 Ton DX Cooling, 60~112 MBH Gas Heat

Condition Good

RUL 17

Location Lower Roof North Side adjacent to Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $6,262.50

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 129 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Roof, Single Zone, 40.0~65.0 Ton DX Cooling, 670~900 MBH Gas Heat

Condition Good

RUL 18

Location Lower Roof adjacent to Theather

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $72,115

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 130 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Roof, Single Zone, 40.0~65.0 Ton DX Cooling, 670~900 MBH Gas Heat

Condition Good

RUL 17

Location Gymnasium Roof

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $72,115

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 131 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Heat Pump, Water Source, 2.0~4.0 Ton Cooling, 25~31 MBH Heat

Condition Fair - Good

RUL 14

Location Throuhgout except areas served by gas RTUs

Plan Type Capital Replacement

Quantity 113

Unit of Measure EA

Unit Cost $3,706.25

HVAC Unit HVAC Unit

C21

Hayat Brown LLC Page 132 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3052 Package Units A/C Package, Heat Pump, Water Source, 10.0~18.0 Ton Cooling, 50~64 MBH Heat

Condition Good

RUL 18

Location Mechanical Room by Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $14,587.50

HVAC Unit HVAC Unit

Condenser Water Piping at Heat Pump

C21

Hayat Brown LLC Page 133 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3067 Energy Monitoring & Control Meter, Natural Gas

Condition Good

RUL 24

Location Building Exterior

Plan Type Capital Replacement

Quantity 1

Unit of Measure Each

Unit Cost $3,011.14

Gas Meter Gas Meter

C21

Hayat Brown LLC Page 134 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3068 Building Automation Systems Building Controls - Throughout except Gymnasium South Side Area and Theather adjacent rooms

Condition Fair - Good

RUL 9

Location Throughout except Gymnasium South Side Area and Theather adjacent rooms

Plan Type Capital Replacement

Quantity 169961

Unit of Measure SF

Unit Cost $3.81

BMS computer screen in Boiler Room - Condenser Water Loop

BMS computer screen in Boiler Room - Hot Water System

BMS computer screen in Boiler Room - Third Floor Typical Thermostat and and CO2 sensor

C21

Hayat Brown LLC Page 135 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

D3068 Replace Building Controls - Throughout except

Gymnasium South Side Area and Theather adjacent rooms

Capital Replacement

2027 $647,551

C21

Hayat Brown LLC Page 136 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3068 Building Automation Systems Building Controls - Adjacent Area South Side to Gymnasium - Locker Rooms and others

Condition Fair - Good

RUL 13

Location Adjacent Area South Side to Gymnasium - Locker Rooms and others

Plan Type Capital Replacement

Quantity 3060

Unit of Measure SF

Unit Cost $2.70

Comments Stand-alone DDC controls for RTU, ERV and reheat VAV duct heaters, controlling space temperature and ventilation with space temperature sensors in 6 locations and CO2 sensor.

Room thermostat controlling Reheat VAV

C21

Hayat Brown LLC Page 137 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D3068 Building Automation Systems Building Controls - Theatre adjacent rooms

Condition Fair - Good

RUL 14

Location Theater adjacent rooms

Plan Type Capital Replacement

Quantity 1600

Unit of Measure SF

Unit Cost $2.70

DDC Panel above ceiling in Control Room Typical thermostat

C21

Hayat Brown LLC Page 138 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

D40 F IRE PROTECTION SYSTEMS

Item Description

D4012 Sprinkler Pumping Equipment Sprinkler System

Condition Good

RUL 29

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $5.47

C21

Hayat Brown LLC Page 139 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D4031 Fire Extinguishers Fire Extinguishers

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $0.37

Fire Extinguishers

C21

Hayat Brown LLC Page 140 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

D50 ELECTRICAL SYSTEMS

Item Description

D5012 Low Tension Service & Dist. Primary Transformer, Dry, 300kVA

Condition Good

RUL 24

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $43,352.89

Transformer Transformer

C21

Hayat Brown LLC Page 141 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Secondary Transformer, Dry, 75 kVA

Condition Good

RUL 24

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $7,032.12

Transformer Transformer

C21

Hayat Brown LLC Page 142 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Panel Board - Newer

Condition Good

RUL 29

Location 2nd Floor Offices Above Theater

Plan Type Capital Replacement

Quantity 4

Unit of Measure Each

Unit Cost $10,664.25

Newer Panelboards

C21

Hayat Brown LLC Page 143 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Panel Board

Condition Good

RUL 24

Location Throughout

Plan Type Capital Replacement

Quantity 42

Unit of Measure Each

Unit Cost $10,664.25

Panelboards Panelboards

C21

Hayat Brown LLC Page 144 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Motor Starter, 2.000 HP, 208 V

Condition Fair - Good

RUL 12

Location Above Ceiling in Science Prep Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $1,128.90

Motor Starters

C21

Hayat Brown LLC Page 145 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Main Service Switch

Condition Fair - Good

RUL 14

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $456,364

Main Service Switch Main Service Switch

C21

Hayat Brown LLC Page 146 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Transfer Switch, Auto, 600 V, 100 Amps

Condition Fair - Good

RUL 12

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $6,449.31

Automatic Transfer Switches

C21

Hayat Brown LLC Page 147 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Secondary Transformer, Dry, 45 kVA

Condition Good

RUL 24

Location 2nd Floor Laundry Room behind Gymnasium

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $5,600.77

Transformer

C21

Hayat Brown LLC Page 148 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Switchboard, 4000 Amps, 2 sections

Condition Good

RUL 24

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 1

Unit of Measure Each

Unit Cost $543,459.76

Switchboard

C21

Hayat Brown LLC Page 149 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Switchboard, 1000 Amps, 1 section

Condition Good

RUL 24

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure Each

Unit Cost $427,004.09

Switchboard Switchboard

C21

Hayat Brown LLC Page 150 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Variable Frequency Drive (VFD), 100.0~150.0 HP Motor, P-3, P-4

Condition Fair - Good

RUL 14

Location Boiler Room

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $33,303.78

VFD for P-4

C21

Hayat Brown LLC Page 151 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5012 Low Tension Service & Dist. Variable Frequency Drive (VFD), 10.0~15.0 HP Motor, P-1, P,2, P-5, P-6

Condition Fair - Good

RUL 14

Location Boiler Room

Plan Type Capital Replacement

Quantity 4

Unit of Measure EA

Unit Cost $7,174.37

VFDs P-1, P-2

C21

Hayat Brown LLC Page 152 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5021 Branch Wiring Devices Branch Wiring Peripheral Devices

Condition Good

RUL 24

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $3.75

C21

Hayat Brown LLC Page 153 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5021 Branch Wiring Devices Occupancy Sensors, Indoor Lighting

Condition Good

RUL 24

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $2.41

Occupancy Sensors Occupancy Sensors

C21

Hayat Brown LLC Page 154 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment HID Lighting

Condition Fair - Good

RUL 14

Location Boiler Room

Plan Type Capital Replacement

Quantity 15

Unit of Measure EA

Unit Cost $1,007.30

HID Lighting HID Lighting

C21

Hayat Brown LLC Page 155 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Exterior Lighting

Condition Fair - Good

RUL 14

Location Building Perimeter

Plan Type Capital Replacement

Quantity 32

Unit of Measure EA

Unit Cost $527.93

Exterior Lighting Exterior Lighting

C21

Hayat Brown LLC Page 156 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Flood Light, Exterior Newer

Condition Good

RUL 19

Location Building Perimeter

Plan Type Capital Replacement

Quantity 12

Unit of Measure Each

Unit Cost $844.04

Newer Exterior Lighting Newer Exterior

Lighting

C21

Hayat Brown LLC Page 157 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Flood Light, Exterior

Condition Fair - Good

RUL 14

Location Building Perimeter

Plan Type Capital Replacement

Quantity 52

Unit of Measure Each

Unit Cost $844.04

Comments

Exterior Lighting

C21

Hayat Brown LLC Page 158 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Lighting Equipment - LED

Condition Good

RUL 19

Location Theater

Plan Type Capital Replacement

Quantity 98

Unit of Measure EA

Unit Cost $178.94

LED Lighting LED Lighting

LED Lighting

C21

Hayat Brown LLC Page 159 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Lighting Equipment - Fluorescent

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 158342

Unit of Measure SF

Unit Cost $4.54

Fluorescent Lighting Fluorescent Lighting

Fluorescent Lighting

C21

Hayat Brown LLC Page 160 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5022 Lighting Equipment Stage Lighting

Condition Good

RUL 19

Location Theater

Plan Type Capital Replacement

Quantity 75

Unit of Measure EA

Unit Cost $969.86

Theater Lighting System Theater Lighting

System

C21

Hayat Brown LLC Page 161 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5031 Public Address & Music Systems Public Address System

Condition Fair - Good

RUL 9

Location Room 102 IT Closet

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $1.24

Public Address System

Type Component Description Plan Type Year Expenditures

($)

D5031 Replace Public Address System Capital

Replacement 2027 $219,356

C21

Hayat Brown LLC Page 162 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5031 Public Address & Music Systems Sound System

Condition Fair - Good

RUL 14

Location Theater

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $2,067.61

Theater Local Sound System

Theater Local Sound System

C21

Hayat Brown LLC Page 163 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5037 Fire Alarm Systems Fire Alarm Systems

Condition Fair - Good

RUL 14

Location Main Electrical Room

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $4.02

Fire Alarm System

C21

Hayat Brown LLC Page 164 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5038 Security and Detection Systems Card Reader

Condition Fair - Good

RUL 8

Location Entrances

Plan Type Capital Replacement

Quantity 14

Unit of Measure Each

Unit Cost $1,149.90

Card Reader Card Reader

Type Component Description Plan Type Year Expenditures

($)

D5038 Replace Card Reader Capital

Replacement 2026 $16,099

C21

Hayat Brown LLC Page 165 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5038 Security and Detection Systems Security and Detection Systems - CCTV

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $3.64

CCTV System CCTV System

C21

Hayat Brown LLC Page 166 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5038 Security and Detection Systems Intrusion Detection

Condition Fair - Good

RUL 9

Location Room 102 IT Closet

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $1.15

Intrusion Detection Intrusion Detection

Type Component Description Plan Type Year Expenditures

($)

D5038 Replace Intrusion Detection Capital

Replacement 2027 $203,435

C21

Hayat Brown LLC Page 167 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5092 Emergency Light & Power Systems Emergency Lights

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $1.06

Emergency Lighting Emergency Lighting

C21

Hayat Brown LLC Page 168 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5092 Emergency Light & Power Systems Exit Lighting Fixture

Condition Fair - Good

RUL 14

Location Throughout

Plan Type Capital Replacement

Quantity 176900

Unit of Measure SF

Unit Cost $0.66

Exit Lighting Exit Lighting

C21

Hayat Brown LLC Page 169 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

D5092 Emergency Light & Power Systems Generator, Natural Gas, 128 kW

Condition Good

RUL 19

Location Outdoor Enclosure

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $130,323.04

Emergency Generator

Emergency Generator

C21

Hayat Brown LLC Page 170 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

E E Q U I P M E N T & F U R N I S H I N G S Y S T E M S

E10 EQUIPMENT

Item Description

E1027 Laboratory Equipment Sink, Epoxy Resin, Laboratory

Condition Fair - Good

RUL 9

Location Science Labs

Plan Type Capital Replacement

Quantity 16

Unit of Measure EA

Unit Cost $528.23

Laboratory Sink in Chemistry Lab 309

Type Component Description Plan Type Year Expenditures

($)

E1027 Replace Sink, Epoxy Resin, Laboratory Capital

Replacement 2027 $8,452

C21

Hayat Brown LLC Page 171 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

E1093 Food Service Equipment Kitchen Food Service Equipment, various types

Condition Fair - Good

RUL 14

Location Warming Kitchen

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $33,765.83

C21

Hayat Brown LLC Page 172 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 173 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

G B U I L D I N G S I T E W O R K S Y S T E M S

G20 S ITE IMPROVEMENTS

Item Description

G2012 Paving & Surfacing Roadway, Asphalt Paved

Condition Good

RUL 21

Location Exterior

Plan Type Capital Replacement

Quantity 324

Unit of Measure LF

Unit Cost $85.40

C21

Hayat Brown LLC Page 174 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2022 Paving & Surfacing Parking Lot, Asphalt Paved

Condition Good

RUL 16

Location Exterior

Plan Type Capital Replacement

Quantity 22800

Unit of Measure SF

Unit Cost $4.50

C21

Hayat Brown LLC Page 175 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2022 Paving & Surfacing Parking Lot, Paving, Concrete, Driveways

Condition Poor

RUL 2

Plan Type Capital Replacement

Quantity 6500

Unit of Measure SF

Unit Cost $8.48

Type Component Description Plan Type Year Expenditures

($)

G2022 Replace Parking Lot, Paving, Concrete, Driveways Capital

Replacement 2020 $55,120

C21

Hayat Brown LLC Page 176 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2031 Paving & Surfacing Pedestrian Paving, Asphalt

Condition Fair - Good

RUL 11

Plan Type Capital Replacement

Quantity 8795

Unit of Measure SF

Unit Cost $4.65

C21

Hayat Brown LLC Page 177 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2031 Paving & Surfacing Pedestrian Paving, Concrete

Condition Fair - Good

RUL 11

Plan Type Capital Replacement

Quantity 11902

Unit of Measure SF

Unit Cost $12.37

Type Component Description Plan Type Year Expenditures

($)

G2031 Repair Concrete Sidewalk Deferred

Maintenance 2018 $22,573

C21

Hayat Brown LLC Page 178 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

C21

Hayat Brown LLC Page 179 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2031 Paving & Surfacing Pedestrian Paving, Concrete, New Paving

Condition Good

RUL 19

Plan Type Capital Replacement

Quantity 1440

Unit of Measure SF

Unit Cost $12.37

C21

Hayat Brown LLC Page 180 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2031 Paving & Surfacing Pedestrian Paving, Stone Paving

Condition Good

RUL 19

Plan Type Capital Replacement

Quantity 1912

Unit of Measure SF

Unit Cost $43.79

Type Component Description Plan Type Year Expenditures

($)

G2031 Repair Clay Brick/Masonry Paver Sidewalk, Exterior Deferred

Maintenance 2018 $1,226

C21

Hayat Brown LLC Page 181 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2033 Exterior Steps Exterior Concrete Ramp

Condition Good

RUL 34

Location Existing Building

Plan Type Capital Replacement

Quantity 12

Unit of Measure LF

Unit Cost $804

C21

Hayat Brown LLC Page 182 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2041 Fences & Gates Fence, Masonry

Condition Fair - Good

RUL 11

Plan Type Capital Replacement

Quantity 145

Unit of Measure LF

Unit Cost $103.10

Type Component Description Plan Type Year Expenditures

($)

G2041 Repair Retaining Wall, Brick/Stone Deferred

Maintenance 2018 $2,278

C21

Hayat Brown LLC Page 183 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2041 Fences & Gates Sliding Gate, Motor Operated

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 2

Unit of Measure EA

Unit Cost $5,041.36

C21

Hayat Brown LLC Page 184 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2041 Fences & Gates Metal Ornamental Fence

Condition Good

RUL 24

Plan Type Capital Replacement

Quantity 1054

Unit of Measure LF

Unit Cost $78.14

C21

Hayat Brown LLC Page 185 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2041 Fences & Gates Chain Link Fence 8’

Condition Fair

RUL 6

Plan Type Capital Replacement

Quantity 265

Unit of Measure LF

Unit Cost $43.33

Comments

Type Component Description Plan Type Year Expenditures

($)

G2041 Replace Chain Link Fence 8’ Capital

Replacement 2024 $11,482

C21

Hayat Brown LLC Page 186 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2041 Fences & Gates Chain Link Fence 4’

Condition Fair

RUL 6

Plan Type Capital Replacement

Quantity 96

Unit of Measure LF

Unit Cost $17.93

Comments

Type Component Description Plan Type Year Expenditures

($)

G2041 Replace Chain Link Fence 4’ Capital

Replacement 2024 $1,721

C21

Hayat Brown LLC Page 187 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2042 Retaining Walls Retaining Wall, Wood Tie

Condition Poor

RUL 1

Plan Type Capital Replacement

Quantity 100

Unit of Measure LF

Unit Cost $184.57

Comments

Type Component Description Plan Type Year Expenditures

($)

G2042 Replace Retaining Wall, Wood Tie Capital

Replacement 2019 $18,457

C21

Hayat Brown LLC Page 188 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2042 Retaining Walls Retaining Wall, Masonry

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 20

Unit of Measure LF

Unit Cost $154.72

Comments

C21

Hayat Brown LLC Page 189 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

G2042 Repair Retaining Wall, Brick/Stone (per SF Face) Deferred

Maintenance 2018 $1,139

C21

Hayat Brown LLC Page 190 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2042 Retaining Walls Retaining Wall, Cast in Place Concrete

Condition Fair - Good

RUL 12

Plan Type Capital Replacement

Quantity 1610

Unit of Measure LF

Unit Cost $142.34

Comments

C21

Hayat Brown LLC Page 191 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

G2042 Repair expansion joints at retaining wall Deferred

Maintenance 2018 $10,000

C21

Hayat Brown LLC Page 192 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Soccer Field

Condition Poor

RUL 1

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $211,727.69

Type Component Description Plan Type Year Expenditures

($)

G2047 Replace Soccer Field Capital

Replacement 2019 $211,728

C21

Hayat Brown LLC Page 193 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Play Equipment

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $42,840

C21

Hayat Brown LLC Page 194 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Playing Fields, Softball Field

Condition Poor

RUL 1

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $96,677.58

Type Component Description Plan Type Year Expenditures

($)

G2047 Replace Playing Fields, Softball Field Capital

Replacement 2019 $96,678

C21

Hayat Brown LLC Page 195 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Mulch

Condition Fair - Good

RUL 11

Location Exterior

Plan Type Capital Replacement

Quantity 6500

Unit of Measure SF

Unit Cost $2.85

C21

Hayat Brown LLC Page 196 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Playing Fields, Basketball Court, Complete

Condition Poor - Fair

RUL 4

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $28,000

Type Component Description Plan Type Year Expenditures

($)

G2047 Replace Playing Fields, Basketball Court, Complete Capital

Replacement 2022 $28,000

C21

Hayat Brown LLC Page 197 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Play Equipment- Courtyard

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $28,050

C21

Hayat Brown LLC Page 198 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Playing Fields, Soccer Field, Asphaltic Concrete

Condition Fair - Good

RUL 14

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $84,372.12

C21

Hayat Brown LLC Page 199 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2047 Playing Fields Playing Fields, Tennis Courts, Asphaltic Concrete

Condition Poor - Fair

RUL 4

Plan Type Capital Replacement

Quantity 1

Unit of Measure EA

Unit Cost $84,372.12

Type Component Description Plan Type Year Expenditures

($)

G2047 Replace Playing Fields, Tennis Courts, Asphaltic

Concrete Capital

Replacement 2022 $84,372

C21

Hayat Brown LLC Page 200 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Item Description

G2054 Seeding and Sodding Landscaping

Condition Fair - Good

RUL 9

Location Exterior

Plan Type Capital Replacement

Quantity 192000

Unit of Measure SF

Unit Cost $1.20

C21

Hayat Brown LLC Page 201 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

Type Component Description Plan Type Year Expenditures

($)

G2054 Replace Landscaping Capital

Replacement 2027 $230,400

C21

Hayat Brown LLC Page 202 of 299 Powered by iPlan™ © 4tell™ Solutions, LP

THIS PAGE INTENTIONALLY LEFT BLANK