don wareham – field application engineer · don wareham – field application engineer ... design...

60
© 2013 Eaton. All rights reserved. Step Voltage Regulators Don Wareham – Field Application Engineer

Upload: dinhhanh

Post on 17-Apr-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

© 2013 Eaton. All rights reserved.

Step Voltage Regulators

Don Wareham – Field Application Engineer

Page 2: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

2 © 2013 Eaton. All rights reserved.

Today’s Agenda

• Introduction • Voltage Regulator theory • Voltage Regulator application considerations • Installation and proper bypassing • Wrap-up/questions

Page 3: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

3 © 2013 Eaton. All rights reserved.

TRANS- FORMER

End of line

Volta

ge

Distance

VLD = Voltage drop due to line losses

VLD

Page 4: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

4 © 2013 Eaton. All rights reserved.

Regulator Theory – Purpose • Why is voltage regulation needed?

• Power quality criteria requires a constant voltage despite variations in load current

• Load current variations are due to: • New loads • Load profiles – Daily and Seasonal

CURRENT

TIME OF DAY 12am 6am 12pm 6pm

LOAD CURRENT VS TIME OF DAY

Page 5: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

5 © 2013 Eaton. All rights reserved.

• A 10% voltage reduction reduces heat output by 9.75%

• Overvoltage may cause burnouts.

• A 10% voltage reduction reduces light output by 30%

• A 10% overvoltage reduces lamp life 70%.

• Incandescent light bulbs wear out much faster at higher voltages

• Low voltage causes overheating, reduced starting and running torques and overload capacity

• Operating at 90% nominal, the full load current is 10 to 50% higher; temperature rises by 10 to 15%

• At a reduced voltage, the motor has reduced starting torque

• Low voltage on computers and televisions can cause them to become inoperative

Heating Element Lighting Motors Electronics

Why is Voltage Regulation Needed? The inability to supply proper voltage effects the following:

Page 6: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

6 © 2013 Eaton. All rights reserved.

Regulator Theory – Purpose Voltage Regulators: Solve voltage drop problem

+5%

--5%

Nominal

Voltage

OLTC R1

L1 L4 L2 L5 L3 L6 L7

Applied at Substation and midpoint of Feeder.

Page 7: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

7 © 2013 Eaton. All rights reserved.

Theory and Application

Medium Voltage Substations

(A) Regulation with OLTC Transformers

N.C.

N.C.

N.O. OLTC #1

OLTC #2

(B) Bus Regulation

Non-OLTC

(C) Feeder Regulation

Non-OLTC

SVR = Step-Voltage Regulator

3 - 1 SVRs f

3 - 1 SVRs f

Methods of Regulation

3 - 1 SVRs f

3 - 1 SVRs f

Page 8: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

8 © 2013 Eaton. All rights reserved.

• Regulate individual phases • Separate regulation from voltage transformation • Fast change out • Maintenance will not disrupt service • Standardized product • Readily Available vs sub transformer LTs

Why Voltage Regulators vs. LTC?

Page 9: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

9 © 2013 Eaton. All rights reserved.

• LTC ratings go beyond VR ratings

• Some prefer 3Ph Ganged Operation for dedicated 3Ph Loads

• Footprint

Why LTC vs. Voltage Regulators?

Page 10: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

10 © 2013 Eaton. All rights reserved.

What is a Voltage Regulator?

• Voltage Regulator - A device which will provide a constant voltage output under varying input voltages and load currents

• By standards, regulates +10% voltage and –10% voltage. • Total of 33 steps; = 5/8% voltage per tap. • 16 steps in the Raise direction, 16 steps in

the Lower direction, and one Neutral position.

Page 11: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

11 © 2013 Eaton. All rights reserved.

Three Basic Parts of a Voltage Regulator

• Autotransformer - A transformer in which part of one winding is common to both the primary and secondary windings

• Load Tap Changer - A switch designed to work under load to change the configuration of a transformer coil

• Voltage Regulator Control - A control which senses the system and automatically commands the tap changer.

Page 12: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

12 © 2013 Eaton. All rights reserved.

Page 13: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

13 © 2013 Eaton. All rights reserved.

N 1 2 3 4 5 6 7 8

1.25%

L

SL

S

SHUNT WINDING

CONTROL

SERIES WINDING

TYPE A REGULATOR

POTENTIAL TRANSFORMER

REVERSING SWITCH

CURRENT X-FORMER

Page 14: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

14 © 2013 Eaton. All rights reserved.

Type A Design – “Straight”

Page 15: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

15 © 2013 Eaton. All rights reserved.

N 1 2 3 4 5 6 7 8

1.25%

SL

S

SHUNT WINDING CONTROL

SERIES WINDING

CONTROL WINDING

TYPE B REGULATOR

REVERSING SWITCH

CURRENT X-FORMER

L

Page 16: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

16 © 2013 Eaton. All rights reserved.

Type B Design – “Inverted”

Page 17: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

17 © 2013 Eaton. All rights reserved.

Differences from Customer’s Point of View

Type A verses Type B Differences

1. No difference in external connections or operation

2. Type B Regulation Range is +10% and -8.3%. Type A Regulation Range is +10% and -10%

3. It is okay to 3 phase bank a mix of Type A & Type B units

4. If paralleling, place the affected units in the Neutral position during the switching operation. Having them on the same step other than Neutral can generate circulating current between the banks due to voltage differences caused by differences in regulation between a Type A and Type B.

Page 18: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

18 © 2013 Eaton. All rights reserved.

• Pressure Relief Device Rating and Location Defined • Venting pressure = 34.5 kPa (5 psig) and flow of 50 Standard Cubic Feet per Minute SCFM • Located on the tank above the 110 °C top fluid level, as determined by the manufacturer's calculation.

It shall not be located in the quadrant of the tank that contains the control device. • Short Circuit Requirement Revised

• First Cycle Asymmetrical Peak increased to 2.60 from 2.26 for ratings greater than 165 kVA. • Maximum short circuit current changed from 20,000 amps to 16,000 amps. Design must meet 25 times

the rating or 16,000 maximum, whichever is less. • Nameplate Info Additions

• Symmetrical short circuit withstand ampere rating with time duration • Tap changer model • Ratio of load current to switched current (if series transformer is present)

• Support Lugs (Hanger Bracket) Requirements • Support lugs for pole mounting shall be provided for ratings 288 kVA and less, with rated line current of

328 amps or less. • Substation voltage regulators shall be arranged for rolling in two directions: parallel to and right angles

to one side of the voltage regulator. Bases for substation mounting shall be provided for 165 kVA and higher.

• Bushing Terminals Requirements Added • 4-hole spade terminals to be provided on current ratings above 668 amps

IEEE C57.15-2009 (IEC 60076-21)

Page 19: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

19 © 2013 Eaton. All rights reserved.

Given: 10 MVA, 3f transformer, 13.2 kV system voltage, grounded wye

Find: The proper regulator rating to use…...

Regulator Sizing

• Watch the units! 10 MVA = 10,000 KVA • For the regulator current rating:

Line current = Transformer size

VL−L× 3=

10,000kVA

13.2kV×1.732= 438 A

• For Regulator kVA Rating:

kVA rating = 𝑉𝐿−𝐺 × 𝐼 × % 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 = 7.62 𝑘𝑉 × 438 × 0.10 = 333 𝑘𝑉𝐴

• Choose standard rating from tables

Page 20: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

20 © 2013 Eaton. All rights reserved.

Page 21: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

21 © 2013 Eaton. All rights reserved.

Single Phase Voltage Regulators

• Self contained • +/- 10% regulation in 32- 5/8%

steps • 55/65 °C average winding rise

(12% more capacity) • 25 to 2000 kVA (pad 875 A) • 2400 V to 34500 V (60-200 BIL) • Mineral oil or FR3 • Fan cooling option (33% more

capacity) • Substation, pole and pad mounted

designs

Page 22: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

22 © 2013 Eaton. All rights reserved.

Padmount Voltage Regulator

Page 23: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

23 © 2013 Eaton. All rights reserved.

Page 24: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

24 © 2013 Eaton. All rights reserved.

Basic Control Settings Function Codes

• FC 1 - Set Voltage • FC 2 - Bandwidth • FC 3 - Time Delay • FC 4 – LDC Resistance • FC 5 – LDC Reactance • FC 39 - Source Side Calculation

• FC 140 Regulator Type • FC 41- Regulation Configuration • FC 42 - Control Operating Mode • FC 43 - Systems Voltage

(Nominal) • FC 44 - PT Ratio • FC 45 - CT Ratio • FC 49 - Tap Changer Type

• FC 50 - Clock • FC 143- Time Format • FC 142- Date Format

• FC 56 - Reverse Sensing Mode • FC 69 - Auto Blocking Status • FC 70 - Voltage Reduction • FC 80 - Voltage Limiter Mode

Page 25: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

25 © 2013 Eaton. All rights reserved.

Set Voltage

• The voltage level (on 120V base) to which the control will regulate

• Settable for both forward & reverse power flow

Page 26: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

26 © 2013 Eaton. All rights reserved.

Bandwidth

• The total voltage range around the set voltage which the control will consider acceptable

• Acceptable voltage range defined as: Range = SV +/- 1/2 BW

Page 27: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

27 © 2013 Eaton. All rights reserved.

Time Delay

• The number of seconds the control waits, from the start of an out-of-band condition, before initiating a tap change

Page 28: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

28 © 2013 Eaton. All rights reserved.

Time Delay

30 SECONDS

120

122

124

126

128

118

116

114

112

BANDWIDTH

TIME

VO

LTA

GE

SE

T P

OIN

T

Given: TD = 30

Page 29: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

29 © 2013 Eaton. All rights reserved.

Cascading Regulators

3-phase LTC

transformer TD = 30 SEC

SVR TD = 45 SEC

SVR TD = 45 SEC SVR

TD = 45 SEC

SVR TD = 75 SEC

SVR TD = 60 SEC

SVR TD = 60 SEC

Rule 1: Each succeeding regulator in series down line from the source requires a longer time delay Rule 2: The minimum time delay from one regulator to the next in cascade is 15 seconds

Page 30: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

30 © 2013 Eaton. All rights reserved.

Voltage Profile Without LDC

120

124

128

116

112

VOLT

AG

E

Minimum

DISTANCE FEEDER

voltage

voltage Maximum

Max. load

Min. load

Page 31: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

31 © 2013 Eaton. All rights reserved.

Line Drop Compensation • Control compensates for line losses – load, resistance and

impedance are considered • Dialing in line drop compensation moves the set voltage point

from the load bushing to the ‘Load Center’. VR > 0, and VX > 0

Page 32: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

32 © 2013 Eaton. All rights reserved.

Regulator - Capacitor Comparison

120

124

128

116

112

VO

LTA

GE

O

n Li

ne

DISTANCE FEEDER

R C

Page 33: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

33 © 2013 Eaton. All rights reserved.

Coordination w/Capacitors

• Any capacitor on the source side of a regulator does not affect regulator settings, as current through the line drop compensator is proportional to load current

• Any capacitor at the load center of a regulator (or beyond) does not affect regulator settings as current through the line drop compensator is proportional to load current

Page 34: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

34 © 2013 Eaton. All rights reserved.

Coordination w/Capacitors

• A regulator with capacitors located between the regulator and the load center must have it’s set voltage adjusted to compensate for additional voltage drop due to capacitor current flowing back to the source

• Only applies if LDC setting are used

Page 35: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

35 © 2013 Eaton. All rights reserved.

Reverse Sensing Mode

• Reverse Sensing Mode defines power flow condition settings • Reverse Sensing Mode Options

• Locked Forward (default setting) • Locked Reverse • Reverse Idle • Bi-directional • Neutral Idle • Co-generation • React Bi-directional

Page 36: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

36 © 2013 Eaton. All rights reserved.

When DG generates power that does not meet the load demand, DG will offset current through the VR and may cause VR to tap down, considering this situation as light loading

Load Side

R X

DG

When DG generates power that exceeds the load demand, some power is exported back to the power system. In this case, DG may increase current through the VR and cause VR to tap up, considering this situation as heavy loading. This may occur when the VR source voltage is near ANSI upper limit. As a result, voltage at the load may be excessive

DG Interactions with Voltage Regulators

Page 37: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

37 © 2013 Eaton. All rights reserved.

• When DG generates real power that does not meet the local load demand, some real power is provided by the power system. The VR will regulate voltage at the DG location in Forward Mode

• When DG generates real power that exceeds the load demand, some real power is exported back to the power system. However, the VR will not reverse direction and will continue to regulate voltage on the DG side

Substation

DG

Regulated voltage during forward or reverse power flow

Customer Load

Co-Generation Mode

Page 38: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

38 © 2013 Eaton. All rights reserved.

Substation

Substation

P, Q

P, Q

Open

Closed

When one source is lost, power flow will change and some VRs should change direction of the voltage regulation

Substation

Circuit Breaker

Tie Recloser N.O.

Voltage Regulator

Substation

Circuit Breaker

P, Q

P, Q

Direction of Voltage Regulation

DG DG

Why Co-Generation Mode may not be suitable for Loop Scheme applications?

Co-Generation Mode

Page 39: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

39 © 2013 Eaton. All rights reserved.

• DG operates with constant power factor mode, consuming some reactive power from the system. The VR controls voltage on its load side (DG side)

• The VR controls voltage on its load side irrespective of the real power flow that can be in both directions depending on the DG operation

Direction of voltage regulation during normal operation (Tie Recloser Open)

Source 1

DG

CB1 Closed

CB2 Closed

Tie Recloser Open

Q P

Source 2

Q

P

Reactive Bi-Directional Mode

Page 40: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

40 © 2013 Eaton. All rights reserved.

• When the Tie Recloser is closed and CB1 open, the reactive power through the VR will

change. When the VR detects the reactive power change, it will change the direction of the voltage regulation and will regulate voltage on the CB1 side

Source 1

DG

CB1 Open

CB2 Closed

Tie Recloser Closed

Q P

Source 2

Q

P

Direction of voltage regulation during Loss of Source 1 (CB1 Open)

(Tie Recloser Closed)

Reactive Bi-Directional Mode

Page 41: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

41 © 2013 Eaton. All rights reserved.

Solar Field Application

• Application: Need to be able to react to a 12-20% drop in utility voltage and correct it to 12% in less than 5 seconds.

• Solution: Utilize voltage limiting threshold to establish limits to initiate quick response to bring voltage back within threshold with minimal time delay

90

95

100

105

110

115

120

125

130

Volta

ge

Time (s)

Response to Undervoltage

Voltage setting

Upper Band

lower band

Actual Voltage

Lower Voltage limit

Page 42: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

42 © 2013 Eaton. All rights reserved.

Voltage Limiting

• Places a high and/or low limit on the output at the load bushing

• Highest priority of all operating functions • Options

• Off • High limit only; then requires High Limit Value • High & Low limits; then requires High and Low

Limits Values. • Default value = Off

Page 43: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

43 © 2013 Eaton. All rights reserved.

Voltage Limiter Response

Time Delay = 30 Seconds

2s delay between tap changes High Limit + 3 volts

c=0 c=10 (CL-6)

c=30

Time Delay counter (C) activated

High Limit

Low Limit + 3 volts

Low Limit

Low Bandwidth Edge

Set Voltage

High Bandwidth Edge

C is adjustable on CL-7

Response delay between

tap changes adjustable on CL-7

Page 44: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

© 2013 Eaton. All rights reserved.

INSTALLATION & OPERATION

Page 45: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

45 © 2013 Eaton. All rights reserved.

Regulator Installation • Ground the regulator tank AND the control

cabinet.

Page 46: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

46 © 2013 Eaton. All rights reserved.

Connections

S

L

SL

A

B

CN

Source

Disconnect

SeriesLightningArrester

Bypass Switch

ShuntLightningArrester

L

S SL S

L

SL

Bypass Switch Phase A Phase B Phase C

S

L

SL S

L

SL

Disconnect Switches

S

L

SL

Disconnect Switch

Bypass Switch Phase A Phase B Phase C

S

L

SL S

L

SL

4 Wire grounded wye: • 3 regulators required • ± 10% regulation

3 Wire open delta: • 2 regulators required • ± 10% regulation

3 Wire closed delta: • 3 regulators required • ± 15% regulation

Page 47: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

47 © 2013 Eaton. All rights reserved.

Paralleling Regulators

2 situations to consider :

• Continuous Parallel operation (in substation)

• Tying Feeders through N.O. point (or with Bus Tie switch)

Page 48: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

48 © 2013 Eaton. All rights reserved.

Paralleling Regulators

V

Simplified Diagram – 2 Voltage sources, 2 Impedances

V

Must have: • Same %Z

• Same turns ratio

Reactive Circulating Current

Regulators must use a “Leader-Follower” control setup

Page 49: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

49 © 2013 Eaton. All rights reserved.

Paralleling Regulators

Tying Feeders through a N.O. switching operation

R R

How do you set the Regulators ? Block Regulators (at least one) -Match Tap position? What tap? -Match Voltage? Where? -Impedance is your friend

N.O.

Page 50: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

50 © 2013 Eaton. All rights reserved.

Bypassing a Regulator

Definition: Bypassing means installing a regulator or removing a regulator from service.

Installing or removing the regulator with the tap changer off neutral will short circuit part of the series winding! Before bypassing, the regulator must be in neutral.

Warning! !

Page 51: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

51 © 2013 Eaton. All rights reserved.

Prior to Bypassing Place the regulator in neutral position A minimum of four indications are recommended

for neutral determination.

– Neutral lamp is “on” continuously

– Verify the tap position of the control indicates Neutral

– Position indicator is in neutral position

– Verify that there is no voltage difference between the S and L bushings

Tap Position 0

At Limit

P.I. ADD-AMP -16, 16

Tap Position 0

At Limit

P.I. ADD-AMP -16, 16

Bypassing a Regulator

Page 52: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

52 © 2013 Eaton. All rights reserved.

Theory and Application

Page 53: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

53 © 2013 Eaton. All rights reserved.

BYPASSING 1 step = 5/8% = .00625

Base voltage

Voltage per step

120 2400 4800 7200 7620 12000 14400 19920

.75 15 30 45 48 75 90 125

Page 54: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

54 © 2013 Eaton. All rights reserved.

Take action to prevent the tap changer motor operation

• Power switch is OFF

• ‘Auto/Off/Manual’ switch is OFF

• Remove motor fuse

• V1 & V6 knife switches are OPEN

Prior to Bypassing Bypassing a Regulator

Page 55: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

55 © 2013 Eaton. All rights reserved.

Bypassing Regulator Connected Line-to-Ground (GY)

Source Load

Phase A

Neutral

Bypass

Disconnect Disconnect

SL

L S

Page 56: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

56 © 2013 Eaton. All rights reserved.

Bypassing - Remove Procedure Regulator Connected Line-to-Ground (GY)

Source Load

Phase A

Neutral

SL

L S

S-DIS L-DIS

B

Start 1 2 3 B O C C C

S-Dis C C C O L-Dis C C O O

Step 1 is Critical Operation.

Page 57: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

57 © 2013 Eaton. All rights reserved.

Bypassing Regulator Connected Line-to-Line (Delta)

Source Load

Phase A

Phase B

Bypass

Disconnect Disconnect

Disconnect

S L

SL

Page 58: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

58 © 2013 Eaton. All rights reserved.

Bypassing - Remove Procedure Regulator Connected Line-to-Line (Delta)

Source Load

Phase A

Phase B

B

S-DIS

S L

SL

L-DIS

SL-DIS

Start 1 2 3 4 B O C C C C

SL-Dis C C C C O S-Dis C C C O O L-Dis C C O O O

Step 1 is Critical Operation.

Page 59: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

59 © 2013 Eaton. All rights reserved.

Page 60: Don Wareham – Field Application Engineer · Don Wareham – Field Application Engineer ... Design must meet 25 times ... (Tie Recloser Open) Source 1 DG . CB1 Closed CB2

60 © 2013 Eaton. All rights reserved.

Regulators

• Questions??