© Institute for International Research, Inc. 2006. All rights reserved.
Module 6:Manufacturing Throughput
![Page 2: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/2.jpg)
2international
Module 6 Purpose and Objectives Module Purpose:
Process optimization requires understanding the process. The student will examine the variables involved with sublimation and then review “whole manufacturing cycles”.
Module Objectives:After this module, you will be able to
Look at a lyophilization cycle in the broader context of a manufacturing cycle.
![Page 3: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/3.jpg)
3international
Throughput
Vials per Year Manufacturing Cycle: (related to Lyo)
Sterilize Lyo and Cool the shelves.Perform the leak test.Fill vialsLoad Lyo (Close Door)Lyophilize vialsUnload LyoRun CIPVerify cleaning via swab testing
![Page 4: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/4.jpg)
4international
Step Timing
Sterilize Lyo – 3 hours, including cool down.Assumes the lyo is clean at startIncludes performing filter integrity.Assumes a 30 minute steam exposure at 121C.Allows some time for cool down.
[Do not start a lyo load with frozen shelves.]
Leak Test – automated cycle. If a leak is detected, there is time in the manufacturing schedule to find, fix and repeat sterilization.
![Page 5: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/5.jpg)
5international
Vial Filling
Lyo should be ready to use at the beginning of a fill shift. – When the product is “committed”.
Loading will likely occur throughout the filling period.
Filling period will be 4 to 12 hours.
![Page 6: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/6.jpg)
6international
Lyophilize Vials
Can there be “planned variable length cycles”? What about validation?Option 1: Stay in freeze mode (lowest shelf
temperature) without vacuum for a variable length of time?
Option 2: Hold vials (pre-stoppering) at some defined temperature (e.g. -5C) until it is “convenient” for manufacturing?
Option 3: Hold vials (post-stoppering) inside the lyophilizer and at their designated storage temperature?
![Page 7: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/7.jpg)
7international
Unload & CIP
Unloading may go slowly and include capping.
Some products require a post filter integrity test. If so, it can be done during the unloading.
CIP cycles are pre-built and validated, so the time is known.
Verify cleaning. Are test results required (due to product changeover) before proceeding?
![Page 8: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/8.jpg)
8international
Example Lyo Cycle
Segment Current NewTime to Transition
C °C MinutesEquilibrate 5 5 30Freeze Down 5 -45 90Hold -45 -45 60Anneal Up -45 -14 30Hold -14 -14 60Freeze Down -14 -45 30Hold -45 -45 180Apply VacuumCondensers OnPrimary Up -45 -20 60Hold -20 -20 900Secondary Up -20 50 240Hold 50 50 300Done Down 50 22 27Hold 22 22 30
Temperature
![Page 9: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/9.jpg)
9international
Lyo Cycle Segment Compare
Segment TargetRamp Time
Soak Time
C Minutes MinutesEquilibrate 5 0 30Freeze -45 90 60Anneal -14 30 60Freeze -45 30 180Primary -20 60 900Secondary 50 240 300Done 22 27 30
Segment TargetRamp Rate
Hold Time
C C/Min MinutesEquilibrate 5 AFAP 30Freeze -45 -0.56 60Anneal -14 1.03 60Freeze -45 -1.03 180Primary -20 0.42 900Secondary 50 0.29 300Done 22 -1.04 30
![Page 10: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/10.jpg)
10 international
Unload & Clean
Stoppering will take about 30 minutes. Unloading/Capping may take 4 or more
hours. CIP (if the water is ready) may take 1 to 2
hours. Swab sampling: 2 hours (includes
gowning) Swab testing: up to 8 hours if started
immediately.
![Page 11: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/11.jpg)
11 international
Scheduling
Constraints: Filling begins on the day shift.
Ergo: The complete lyo manufacturing cycle has to be an integral number of days.
Slack Time: Some built in slack time may be needed in order to keep to a schedule.
![Page 12: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/12.jpg)
12 international
Cycle Optimization – 3 day turn
Making the Lyo Cycle shorter can’t really help.
![Page 13: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/13.jpg)
13 international
PQ Validation Considerations
Freeze Holds.Perform one PQ cycle with an extended freeze hold.
Does vacuum or not matter to the validation?
Perform one media fill where vials see an extended time in the lyophilizer ? Might the media dry out? Media fills are not normally exposed for the time that a vial
is open in the lyophilizer.
In the cycle state a freezing time range from X to Y hours. Why? Vacuum and Condenser and Shelves have to reach
set points.
![Page 14: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/14.jpg)
14 international
PQ Validation Considerations
Perform all PQ cycles with a hold prior to stoppering. Why? Stoppering is manual and 3AM is inconvenient for the
Manufacturing personnel. Why? Stoppering is a critical activity and a lot of errors are
made at 3AM. Why? The actual cycle start time is variable due to lot size,
variable filling times, unknowns holds during the fill, etc. Consequently, the stoppering time isn’t known soon enough to permit scheduling personnel.
Rational: This is the same as defining a longer “secondary dry” with a new temperature.
![Page 15: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/15.jpg)
15 international
An “Optimized” Machine Cycle
A longer “secondary dry” with a new temperature permits the design of a “convenient” cycle.
![Page 16: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/16.jpg)
16 international
PQ Validation Considerations
Perform one (or all) PQ cycles with a hold post – stoppering. Why? Vial is closed and sterility is assured. Why? Storage condition can be the final storage temperature. Why? Cycle can be defined such that it begins and ends at
convenient work times. Why Not? Stoppering may require alert personnel during a
night shift.
![Page 17: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput](https://reader035.vdocument.in/reader035/viewer/2022071709/56649f445503460f94c64ce5/html5/thumbnails/17.jpg)
17 international
Exercise: 6.1
Recommend a manufacturing cycle for a vaccine filling operation that has an optimized drying cycle of 12 hours. Assume
The market cap is limited by manufacturing. There are currently two lyophilizers for one filling line. Filling for one dryer takes 6 hours. Fill room clearance and re-set takes 4 hours. Indicate the risks associated with your recommendation.