© institute for international research, inc. 2006. all rights reserved. module 6: manufacturing...

17
© Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

Upload: merryl-small

Post on 14-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

© Institute for International Research, Inc. 2006. All rights reserved.

Module 6:Manufacturing Throughput

Page 2: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

2international

Module 6 Purpose and Objectives Module Purpose:

Process optimization requires understanding the process. The student will examine the variables involved with sublimation and then review “whole manufacturing cycles”.

Module Objectives:After this module, you will be able to

Look at a lyophilization cycle in the broader context of a manufacturing cycle.

Page 3: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

3international

Throughput

Vials per Year Manufacturing Cycle: (related to Lyo)

Sterilize Lyo and Cool the shelves.Perform the leak test.Fill vialsLoad Lyo (Close Door)Lyophilize vialsUnload LyoRun CIPVerify cleaning via swab testing

Page 4: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

4international

Step Timing

Sterilize Lyo – 3 hours, including cool down.Assumes the lyo is clean at startIncludes performing filter integrity.Assumes a 30 minute steam exposure at 121C.Allows some time for cool down.

[Do not start a lyo load with frozen shelves.]

Leak Test – automated cycle. If a leak is detected, there is time in the manufacturing schedule to find, fix and repeat sterilization.

Page 5: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

5international

Vial Filling

Lyo should be ready to use at the beginning of a fill shift. – When the product is “committed”.

Loading will likely occur throughout the filling period.

Filling period will be 4 to 12 hours.

Page 6: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

6international

Lyophilize Vials

Can there be “planned variable length cycles”? What about validation?Option 1: Stay in freeze mode (lowest shelf

temperature) without vacuum for a variable length of time?

Option 2: Hold vials (pre-stoppering) at some defined temperature (e.g. -5C) until it is “convenient” for manufacturing?

Option 3: Hold vials (post-stoppering) inside the lyophilizer and at their designated storage temperature?

Page 7: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

7international

Unload & CIP

Unloading may go slowly and include capping.

Some products require a post filter integrity test. If so, it can be done during the unloading.

CIP cycles are pre-built and validated, so the time is known.

Verify cleaning. Are test results required (due to product changeover) before proceeding?

Page 8: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

8international

Example Lyo Cycle

Segment Current NewTime to Transition

C °C MinutesEquilibrate 5 5 30Freeze Down 5 -45 90Hold -45 -45 60Anneal Up -45 -14 30Hold -14 -14 60Freeze Down -14 -45 30Hold -45 -45 180Apply VacuumCondensers OnPrimary Up -45 -20 60Hold -20 -20 900Secondary Up -20 50 240Hold 50 50 300Done Down 50 22 27Hold 22 22 30

Temperature

Page 9: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

9international

Lyo Cycle Segment Compare

Segment TargetRamp Time

Soak Time

C Minutes MinutesEquilibrate 5 0 30Freeze -45 90 60Anneal -14 30 60Freeze -45 30 180Primary -20 60 900Secondary 50 240 300Done 22 27 30

Segment TargetRamp Rate

Hold Time

C C/Min MinutesEquilibrate 5 AFAP 30Freeze -45 -0.56 60Anneal -14 1.03 60Freeze -45 -1.03 180Primary -20 0.42 900Secondary 50 0.29 300Done 22 -1.04 30

Page 10: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

10 international

Unload & Clean

Stoppering will take about 30 minutes. Unloading/Capping may take 4 or more

hours. CIP (if the water is ready) may take 1 to 2

hours. Swab sampling: 2 hours (includes

gowning) Swab testing: up to 8 hours if started

immediately.

Page 11: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

11 international

Scheduling

Constraints: Filling begins on the day shift.

Ergo: The complete lyo manufacturing cycle has to be an integral number of days.

Slack Time: Some built in slack time may be needed in order to keep to a schedule.

Page 12: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

12 international

Cycle Optimization – 3 day turn

Making the Lyo Cycle shorter can’t really help.

Page 13: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

13 international

PQ Validation Considerations

Freeze Holds.Perform one PQ cycle with an extended freeze hold.

Does vacuum or not matter to the validation?

Perform one media fill where vials see an extended time in the lyophilizer ? Might the media dry out? Media fills are not normally exposed for the time that a vial

is open in the lyophilizer.

In the cycle state a freezing time range from X to Y hours. Why? Vacuum and Condenser and Shelves have to reach

set points.

Page 14: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

14 international

PQ Validation Considerations

Perform all PQ cycles with a hold prior to stoppering. Why? Stoppering is manual and 3AM is inconvenient for the

Manufacturing personnel. Why? Stoppering is a critical activity and a lot of errors are

made at 3AM. Why? The actual cycle start time is variable due to lot size,

variable filling times, unknowns holds during the fill, etc. Consequently, the stoppering time isn’t known soon enough to permit scheduling personnel.

Rational: This is the same as defining a longer “secondary dry” with a new temperature.

Page 15: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

15 international

An “Optimized” Machine Cycle

A longer “secondary dry” with a new temperature permits the design of a “convenient” cycle.

Page 16: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

16 international

PQ Validation Considerations

Perform one (or all) PQ cycles with a hold post – stoppering. Why? Vial is closed and sterility is assured. Why? Storage condition can be the final storage temperature. Why? Cycle can be defined such that it begins and ends at

convenient work times. Why Not? Stoppering may require alert personnel during a

night shift.

Page 17: © Institute for International Research, Inc. 2006. All rights reserved. Module 6: Manufacturing Throughput

17 international

Exercise: 6.1

Recommend a manufacturing cycle for a vaccine filling operation that has an optimized drying cycle of 12 hours. Assume

The market cap is limited by manufacturing. There are currently two lyophilizers for one filling line. Filling for one dryer takes 6 hours. Fill room clearance and re-set takes 4 hours. Indicate the risks associated with your recommendation.