![Page 1: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/1.jpg)
Capital Plan2018-19
![Page 2: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/2.jpg)
CapitalBudgetSummary
Total Capital Budget $8,428,425Funded By:Borrowing: $6,067,467(SW, Water and
Sewer)Operating Reserve: $282,000Gas Tax Reserve: $891,800Wind Revenue Reserve: $380,000Sewer Reserve: $105,500Grants: $432,927Operating Budget: $138,731Area Rate: $130,000
![Page 3: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/3.jpg)
Trails:BridgeEvaluations
$25,000
External Funding: $25,000 Gas TaxNet Costs: 0 Start : June 2018Multi-Year Project: YesProcurement Method: Engineering ServicesContract (RFP)
DescriptionBridge Evaluation for Little East River Bridge andGoat Lake Bridge.RationaleRequired by our Letter of Authority from DNR; Willensure safe trail infrastructure for trail users.
![Page 4: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/4.jpg)
Trails:East RiverTrail
$25,000
External Funding: Gas Tax $9K; TD Grant $16KNet Costs: 0 Start: May 2018Multi-Year Project: NoProcurement Method: Heavy Equipment Contract
DescriptionEnhance walking trail on Municipal Property inEast River; Signage, trail markers and bridgeconstruction to connect to Rum Runners Trail.RationaleImproved access to the Property
![Page 5: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/5.jpg)
Trails:Swing Gates
$7,800
External Funding: $7.8K Gas TaxNet Costs: 0 Start: May 2018Multi-Year Project: YesProcurement Method: Heavy Equipment Contract
DescriptionContinuation of the transition from trail bollards toswing gatesRationaleImprove access to trail for emergency andmaintenance purposes
![Page 6: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/6.jpg)
RuralBroadband/Internet
$50,000
External Funding: Start: May 2018Net Costs: $50,000 (from Reserve)Multi-Year Project: Yes ($6.75 M)Procurement Method: High Value Procurement(HVP) - RFP
DescriptionSpeed Study (existing upload/download); Detailedbusiness plan developmentRationaleInformation is necessary to qualify for funding
![Page 7: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/7.jpg)
Landfill(Valley)
Second TowerSite$170,000(pre-budget)
External Funding: no Start: Feb 2018Net Costs: $170,000Multi-Year Project: NoProcurement Method: High ValueProcurement(HVP)- Tender
DescriptionLocation of a second site for disbursement oftreated leachate; Completion of Project started in2017-18RationaleGuarantee regulatory compliance and mitigate riskof high nitrite levels
![Page 8: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/8.jpg)
LandfillChlorineContractChamber
$30,000
External Funding: No Start: May 2018Net Costs: $30,000 (Area Rate)Multi-Year Project: noProcurement Method: LVP- Quotes
DescriptionPurchase and installation of two well crocks fortreatment during emergency situations (ie. duringheavy rain events)RationaleTo control potential overflows from severeweather events
![Page 9: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/9.jpg)
Landfill:ElectronicGate (Valley)
$20,000
External Funding: $0 Start: May 2018Net Costs: $20,000Multi-Year Project: NoProcurement Method: Low Value Procurement(LVP) - Quotes
DescriptionInstallation of pass card controlled gate forafterhours use and security control
RationaleEnable afterhours use without requiring theuse of staff hours
![Page 10: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/10.jpg)
AnaerobicDigester
$5,000,000
External Funding: TBD Start: April 2018Net Costs: $5,000,000Multi-Year Project: Yes (to be finished in 2019)Procurement Method: HVP– Tender; RFP
DescriptionDesign, Purchase and implementation of WetAnaerobic Digestion Technology for organicsprocessing and energy generationRationaleGeneration of Non-Tax Revenue; OrganicsProcessing solution
![Page 11: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/11.jpg)
EconomicDevelopment
Business/Industrial ParkDevelopment$380,000
External Funding: $0 Start: May 2017Net Costs: $380,000 (Reserve Funding)Multi-Year Project: Yes ($1.25M)Procurement Method: Engineering ServicesContract; HVP- Tender
DescriptionLand Purchase, design and preliminaryconstruction (clearing, grubbing, access/some roadconstruction)RationaleBe investment ready with sites ready to bedeveloped.
![Page 12: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/12.jpg)
Flood PlainModelling
$100,000
External Funding: $100K Gas TaxNet Costs: 0 Start: May 2018Multi-Year Project: NoProcurement Method: HVP- Engineering ServicesContract
DescriptionUse of LiDAR data to generate flood plainmodellingRationaleUsed for Emergency Management Purposes,Informed decision making on Land Use Planningand increase public awareness
![Page 13: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/13.jpg)
SharedServices:Bldg./Fire/Dangerousand Unsightly
$115,000
External Funding: $ 115,000 Start: April 2018Net Costs: $40,606Multi-Year Project: Yes (2 Years; remainder TBD)Procurement Method: High Value - RFP
DescriptionPurchase of Scheduling, Permit Tracking Software,and Records Management SoftwareRationaleFacilitates regional delivery of service to mitigaterisks in service delivery that exists
![Page 14: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/14.jpg)
Highway 3 –StreetscapePlan
$650,000
External Funding: $650K Gas TaxNet Costs: 0 Start: May 2018Multi-Year Project: YesProcurement Method: Engineering ServicesContract; HVP – Tender ;NSDOTIR
DescriptionAlign with NSDOTIR Highway 3 improvements-Marriott's Cove to East Chester- Paved Shoulders;intersection improvements (TBD); Trail /pedestrianenhancements near Victoria Road and TrainStationRationaleFacilitate safe active transportation and vehicle
MD6
![Page 15: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/15.jpg)
Slide 14
MD6 Procurement method correct?Matthew Davidson, 2/8/2018
![Page 16: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/16.jpg)
Fire InspectorVehicle
$45,000
External Funding: 0 Start: June 2018Net Costs: $45,000 (Operating Reserve)Multi-Year Project: NoProcurement Method: HVP- Tender
DescriptionPurchase of vehicle; Not a replacement- formeremployee received mileageRationaleMore economical to provide truck than paymileage; Vehicle will be rotated amoungst fleet asit ages.
![Page 17: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/17.jpg)
OrthoPhotography
$100,000
External Funding: $100K Gas TaxNet Costs: 0 Start: May 2018Multi-Year Project: No (5 years)Procurement Method: RFP
DescriptionGeo-rectified Aerial image of the Municipality of
ChesterRationaleAsset Management, Landfill Cell Management,
Erosion Characteristics, Urban and MunicipalPlanning, Tax Base Correction, GovernmentMapping, Watershed Mapping.
![Page 18: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/18.jpg)
SewerCleaning &Videoing
$10,000
External Funding: $5K PCAP Start: May 2018Net Costs: $5,000 (Area Rate)Multi-Year Project: Yes (Yr. 5 of 5)Procurement Method: LVP– Tender/RFP
DescriptionContinuation of cleaning and videoing sewer linesmainly in Western Shore and Chester.RationaleReduces the potential of sewer blockages,improves service and provides information forasset management program; enables master planto be developed for repairs.
![Page 19: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/19.jpg)
Sewers-ManholeRepairs/Infiltration
$30,000
External Funding: $15K PCAP Start: May 2018Net Costs: $15,000 (Area Rate)Multi-Year Project: Yes (Yr. 5 or 5)Procurement Method: LVP– Tender/RFP
DescriptionLocate, inspect and repair manholes inOtter Point, Western Shore and ChesterRationaleAddresses inflow and infiltration; improves wastewater treatment efficiency; reduces overflows;improves access to sewer; best practice
![Page 20: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/20.jpg)
Sewers- LiftStation PanelUpgrades
$30,000
External Funding: No Start: May 2018Net Costs: $30,000 (Area Rate)Multi-Year Project: YesProcurement Method: LVP- Tender
DescriptionAssess/Prioritize and replace panels in lift stationsdeemed critical for replacement. Hope to includeSCADARationaleReplace outdated technology to improve reliabilityof station, response time to service interruptions,data collection and staff efficiency.
![Page 21: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/21.jpg)
Sewers-PumpReplacement
$20,000
External Funding: no Start: May 2018Net Costs: $20,000 (Area Rate)Multi-Year Project: Yes- Annual allowanceProcurement Method: Alternative Procurement
DescriptionAllowance to replace a limited amount of pumpsassociated with collection and treatment
Rationale Enables purchase of pumps in the eventof breakdown (where cost is too high for repairs)
![Page 22: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/22.jpg)
ChesterV. Sewer-WWTPImprovement
$50,000
External Funding: 0 Start: May 2018Net Costs: $50,000 (Sewer Reserve)Multi-Year Project: NoProcurement Method: Engineering ServicesContract (RFP)
DescriptionDesign Phase : Convert to UV, improve sludgehandling, aeration, flow equalization.RationaleImprove wastewater treatment and adherence toNSP Approval to Operate
![Page 23: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/23.jpg)
Mill Cove-WWTPUpgrades(Carry over tofinish project)
$115,000(Pre-Budget)
External Funding: $86 K Completed: June 2018Net Costs: $28KMulti-Year Project: NoProcurement Method: Existing contracts in place
DescriptionComplete Mill Cove WWTP upgrades started in2017-18RationaleAlready approved; Carrying over funds to completeproject
![Page 24: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/24.jpg)
WesternShore-WWTP
$530,000(Pre-Budget)
External Funding: $236K Completed : June 2018Net Costs: $293KMulti-Year Project: NoProcurement Method: Existing contracts in place
DescriptionComplete Western Shore WWTP Upgrades startedin 2017-18RationaleAlready approved; Carrying over funds to completeproject
![Page 25: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/25.jpg)
ChesterBasin- WWTPIncreaseCapacity
$30,000
External Funding: $0 Start: May 2018Net Costs: $30,000 (Area Rate)Multi-Year Project: yesProcurement Method: Engineering ServicesContract
DescriptionConcept and Design phase; Address permitrequirements – flow monitoring, reduce I&I anddisinfectionRationaleIncrease capacity to meet needs of the servicedcommunity and enable economic growth in thecentral area
![Page 26: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/26.jpg)
Otter Point-Sewer-Expansion
$42,500
External Funding: 0 Start: May 2018Net Costs: $42,500 (reserve)Multi-Year Project: NoProcurement Method: Engineering ServicesContract
DescriptionDesign the second leg (Plant expansion) based onthe original design, replace outfall, and incorporateUV disinfection.RationaleNeed to meet permit effluent requirements, whichare presently not being met.
![Page 27: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/27.jpg)
Chester V.Sewer-PropertyImprovements
$10,500
External Funding: 0 Start: May 2018Net Costs: $10,500 (Sewer Reserve)Multi-Year Project: NoProcurement Method: Low Value Procurement
DescriptionRoof replacement (metal); installation of feed linefrom permanently located generator to building(as opposed to using portable)RationaleMaintaining existing infrastructure, extending life,improving efficiency of staff during power outages
![Page 28: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/28.jpg)
Chester V. -CentralWater
$500,000
External Funding: 0 Start: May 2018Net Costs: $500,000Multi-Year Project: NoProcurement Method: Engineering ServicesContract
DescriptionDesign Phase- based on selected water sourcedesign transmission line, treatment, distributionand reservoirs.RationaleAddress need identified and socio-economicbenefit (subject to verification by study)
![Page 29: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/29.jpg)
MunicipalBuildingImprovements-
$125,000
External Funding: 0 Start: May 2018Net Costs: $125,000 (Reserve)Multi-Year Project: YesProcurement Method: Internal resources;Engineering Services Contract; LVP
DescriptionMain Bldg.- Water system upgrades, roof repairdue to leaks; side cedar shakes are rotten; Annex-Vestibule; Stairwell; Side Entrance; Overall FacilityAudit re: Accessibility RegulationsRationaleAddress deficiencies and OH&S issues
![Page 30: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/30.jpg)
VehicleReplacement
$45,000
External Funding: $0 Start: May 2018Net Costs: 45,000 (reserves)Multi-Year Project: NoProcurement Method: HVP - Tender
DescriptionReplacement of Building Inspection Truck ; Transferringexisting truck to Kaizer Meadows to replace Hybrid
RationaleContinuity in delivery of service; reduce maintenancecosts; Existing Truck is a 2011 with 100,400 kms
![Page 31: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/31.jpg)
Mobile RadarUnit
$10,000
External Funding: 0 Start: May 2018Net Costs: $10,000Multi-Year Project: NoProcurement Method: LVP
DescriptionPurchase of Mobile Radar Unit to aid in MotorVehicle Act enforcement (speeding).
RationaleReduce vehicle speeds, ensure safe roads.
![Page 32: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/32.jpg)
Mill Cove –FireProtectionSystem(Water)
$20,000
External Funding: 0 Start: May 2018Net Costs: $20,000Multi-Year Project: YesProcurement Method: Engineering Services Contract
DescriptionEither undertake the design of (1) of the three optionsfor the rehabilitation of the Fire Protection System or ifdetermined feasible, the design of systemdecommissioningRationaleRecommendation from the Mill Cove Fire SuppressionSystem Evaluation. Fire Protection is currentlycompromised
![Page 33: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/33.jpg)
Mill Cove-FireProtectionSystem –Repairs
$35,000
External Funding: $0 Start: May 2018Net Costs: $35,000Multi-Year Project: YProcurement Method: Low Value Procurement
DescriptionReplace portions of the distribution branches andassociated Fire HydrantsRationaleRecommendation from the Mill Cove FireSuppression System Evaluation. Fire Protection iscurrently compromised
![Page 34: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/34.jpg)
Duke Street-SidewalkDrainage
$40,000
External Funding: 0 Start: May 2018Net Costs: $40,000Multi-Year Project: NoProcurement Method: Sole Source
DescriptionPoor drainage of surface water, pooling before catchbasin impacting road shoulder and private property.Road to be resurfaced to better direct water to catchbasinRationaleEliminate property damage, traffic hazard and effecton pedestrians.Request NSDOTIR to do work; MODC to cover costs.
![Page 35: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/35.jpg)
ChesterBasin- WharfRepairs
$65,125(Pre-Budget)
External Funding: 0 Start: May 2018Net Costs: $65,125 + $17,000 (Reserve)Multi-Year Project: NoProcurement Method: LVP
DescriptionAs per Engineering assessment - Deckreplacement; repair two sides of wharf.RationaleExtend the life of an existing asset for recreationaluse.
![Page 36: 2018-19 8.2 b)...Gate (Valley) $20,000. External Funding:$0 Start: May 2018 Net Costs: $20,000 Multi-Year Project: No Procurement Method: Low Value Procurement (L VP) - Quotes Description](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebc068ff778c22df44859a0/html5/thumbnails/36.jpg)
10 YearCapitalPlan
MajorInvestments
2019- 2028
ITEM AMOUNTSewers $6,356,000Admin Bldg. $650,000Central Water (25%) $6,000,000*Broadband/Internet $6,750,000Highway 3 $900,000Industrial Park $1,250,000Fire Protection $1,205,000
* Needs to be adjusted once report finalized (approx. $14M)