Transcript

* Based on information from the Central Severn Vale Strategy - Corridor 3 note.

A40(T)

New Sheet Piled retaining wall to allowcarriageway to be widened intoverge/embankment. Profile of existingembankment below new wall to remainas existing

Carriageway widening(darker shaded area)

Approach lanes extended toincrease capacity at roundabout

Indicative route of underground ductingto be installed to allow for possiblefuture installation of traffic signals

All existing pedestrian and cycleroutes (Sustrans routes 42 & 45)to remain as existing

Carriageway widening(darker shaded area)

A417

N

A417 Southbound WideningThis section will consist of:

• New sheet piled wall to be constructed• Westbound approach to be improved by extending 3 lanes• Additional 60m of left turn queue length provided• Introduction of ‘Spiral’ road marking system• Refurbishment of Street Lighting and road markings• Trees and habitat on existing embankment to be substantially retained• Future proofed for installation of trafc signals

Working inpartnership with

Gloucestershire County Council

LA076627

Top Related