* Based on information from the Central Severn Vale Strategy - Corridor 3 note. A40(T) New Sheet Piled retaining wall to allow carriageway to be widened into verge/embankment. Profile of existing embankment below new wall to remain as existing Carriageway widening (darker shaded area) Approach lanes extended to increase capacity at roundabout Indicative route of underground ducting to be installed to allow for possible future installation of traffic signals All existing pedestrian and cycle routes (Sustrans routes 42 & 45) to remain as existing Carriageway widening (darker shaded area) A417 N A417 Southbound Widening This section will consist of: • New sheet piled wall to be constructed • Westbound approach to be improved by extending 3 lanes • Additional 60m of left turn queue length provided • Introduction of ‘Spiral’ road marking system • Refurbishment of Street Lighting and road markings • Trees and habitat on existing embankment to be substantially retained • Future proofed for installation of trafc signals Working in partnership with Gloucestershire County Council LA076627

Upload: dinhkhuong

Post on 13-Apr-2018

218 views

Category:

Documents


4 download

TRANSCRIPT

* Based on information from the Central Severn Vale Strategy - Corridor 3 note.

A40(T)

New Sheet Piled retaining wall to allowcarriageway to be widened intoverge/embankment. Profile of existingembankment below new wall to remainas existing

Carriageway widening(darker shaded area)

Approach lanes extended toincrease capacity at roundabout

Indicative route of underground ductingto be installed to allow for possiblefuture installation of traffic signals

All existing pedestrian and cycleroutes (Sustrans routes 42 & 45)to remain as existing

Carriageway widening(darker shaded area)

A417

N

A417 Southbound WideningThis section will consist of:

• New sheet piled wall to be constructed• Westbound approach to be improved by extending 3 lanes• Additional 60m of left turn queue length provided• Introduction of ‘Spiral’ road marking system• Refurbishment of Street Lighting and road markings• Trees and habitat on existing embankment to be substantially retained• Future proofed for installation of trafc signals

Working inpartnership with