Weltek Limited
ABOUT
…….advancing technology
ABOUT WELTEK
NIS ISO 9001:2008
C E R T I F I E D
ABOUT WELTEK
Introduction
Incorporated 1986
NIS ISO 9001:2008 Certified 2013
Specializes in turnkey project delivery – Detailed Engineering, Procurement, Fabrication, Construction, Installation and Commissioning
o Mechanical Modular Packages
o Power and Public Utilities
o Automation and Controls
o Electrical and Instrumentation
o Wellhead & Process Control Panels
o Project Management
ABOUT WELTEK
Facilities
Situated on a 20,000m² space with: Engineering &
Project Management Mechanical
Fabrication Workshop
Electrical & Instrumentation FAT/Staging Area
Systems Integration Finance and Admin Warehouse/Store QMS – QA/QC Document
Management System Health Safety
Security & Environment (HSSE)
Corporate Office
ABOUT WELTEK
Engineering and Project Management
Engineering Pool
Project Management offices
Design Unit Scheduling
Facilities
ABOUT WELTEK
Facilities
Mechanical Fabrication Workshop
Mech. Skids Fabrication Workshop Blasting and Painting Bay
Piping and Spools Workshop
ABOUT WELTEK
Welding Machines
Welding Gases 10 Ton Overhead Crane
Facilities
Fabrication Equipment
ABOUT WELTEK
Electrical & Instrumentation FAT/Staging Area
Facilities
Hydrotest Equipment
Electrical & Instrumentation Test Equipment
ABOUT WELTEK
Warehouse /Storage Facilities
Facilities
Weltek has a 324m2 Warehouse /Storage Facility with gigantic doors for heavy Storage purposes
ABOUT WELTEK
Document Management System & QMS
Facilities
Document Management System Server Room
Quality Management System
ABOUT WELTEK
Facilities
Health Safety, Security and Environment
Safety Statistics Safety Meeting
ABOUT WELTEK
Switchgear & Subsea Control Building (SSCB)
Design, Fabrication and Systems Integration: Electrical Switchgear and Control Panels
Distributed Control Systems (DCS) with Remote Input/output and Processor/Gateway Panels
Heating Ventilation and Air-conditioning systems with Control Panel
Local Area Network (LAN) Distribution Cabin
Subsea Power Communication Unit (SPCU)
Master Control Station
Marshaling Cabinets
Products and Services
ABOUT WELTEK
Products and Services
Injection Skids
Methanol – High Rate Hydrate Inhibitor Injection Skid Flowline Corrosion Inhibition Injection Skid
Design and Fabrication of Injection Skids: For off-shore Deep Water Oil & Gas Hydrate and Corrosion control
ABOUT WELTEK
Products and Services
Hydraulic Power Unit & Hydraulic Control Unit Structure for FPSO
HPU & HCU Structure HPU & HCU Pedestal Stairs
Design and Fabrication: Of Support Structure for HPU & HCU
ABOUT WELTEK
Products and Services
Structural Members
Piping Spools and Structures for Oil and Gas Production facility
Piping spools
ABOUT WELTEK
Products and Services
Switchgears and Control Panels
ABOUT WELTEK
Products and Services
Cabling
ABOUT WELTEK
Products and Services
Transformers and Generator
ABOUT WELTEK
Control Panels
Products and Services
Control Panels
Process and Automation System Control Panel
Design and Integration • Wellhead Control Panels for Surface
and Subsurface control of wells • Process and Automation Systems
Control Panels
ABOUT WELTEK
Products and Services
Flowstation Surge Vessel Pedestal
Surge Vessel on Pedestal
Designed and Fabricated Pedestal: Surge Vessel mounted and Installed on the Pedestal
Pedestal
ABOUT WELTEK
Products and Services
Pump Skid
Designed and Fabricated Crude Oil Pump Skids with Export Pumps mounted and installed on the Oil & Gas Platform
ABOUT WELTEK
Flowline Crude Oil Metering
Products and Services
Coriolis Meter Installation
Design and Installation: Crude Oil Flowline and Separator/Export metering
Metering Skids
ABOUT WELTEK
Experience
PROJECT: BONGA NORTH WEST TOPSIDES FACILITIES CLIENT: SHELL NIGERIA EXPLORATION COMPANY
PROJECT OVERVIEW:
Engineering, Procurement, Installation and Commissioning(EPIC) Topsides Facilities on the Bonga FPSO:
1. Four Methanol Injection Pumps and Four Corrosion Inhibition Pumps including skids and accessories.
2. Electrical Switch gears and control buildings
STATUS: Ongoing
ABOUT WELTEK
CLIENT: SHELL PETROLEUM DEVELOPMENT COMPANY
PROJECT OVERVIEW: SPDC as the operator of the Cawthorne Channel, Awoba and Krakama fields intends to carry out further oil development on the facilities. The project work scope includes but is not limited to the following: Expansion of flow station production capacity from a single train (30Mbd) to double train
flow station (2 x 30Mbd); piling & extension of the existing flow station platform and installation of various production skid-mounted vessels and equipments.
Upgrade of Flow station instrumentation and control from pneumatic to electronic using foundation field bus technology for five (5) Flow stations. (CawCh1, 2, 3, Awoba & Krakama Flow stations).
Change out of existing gas engine driven reciprocating crude oil pumps, to electric motor driven centrifugal pumps in CawCh1, 2, 3, Awoba stations with associated electrical upgrade works.
Installation of Gaslift manifolds and tie-in to the gas sales manifold. Flow station Information technology (IT) upgrade. HIMA Safe Guarding System (SGS) Installation and Commissioning.
STATUS: Ongoing
PROJECT: CAWTHORNE CHANNEL FURTHER OIL DEVELOPMENT PROJECT
Experience
ABOUT WELTEK
CLIENT: SHELL NIGERIA GAS LIMITED
PROJECT OVERVIEW: This intent of this project is to Install and Commission Senior Daniel Orifice (SDOF) and Upgrade the chart recorders to Flow Computers for process metering.
The project work scope includes but is not limited to the following:
Sizing, procurement and replacement of Pietro Fiorentini orifice fittings with SDOF and orifice plates for the required flow regimes.
Replacement of chart recorders with Floboss 407 Flow computers powered by solar panels.
Training of SNG operators on the functions and operations of the installations.
STATUS: Completed 2009.
PROJECT: INSTALLATION OF SENIOR DANIEL ORIFICE UNITS AND FLOW COMPUTERS (ITOKI CTS).
Experience
ABOUT WELTEK
CLIENT: SHELL PETROLEUM DEVELOPMENT COMPANY
PROJECT OVERVIEW: SPDC carried out an accelerated electronic Instrumentation system for CAO/SCADA project at the flow stations, compressor and gas plant facilities for Sapele and Olomoro Fields. Weltek provided the Electronic Instrumentation and Control Systems in the flow stations, compressor stations and gas plants to address Gaslift Optimization, well testing, production accounting and essential facility monitoring.
The project work scope includes but was not limited to the following:
• Installation of Field instrumentation for detection, measurement and control of relevant process parameters/conditions.
• Installation of Remote Terminal Unit (RTU) in the facilities for receiving and processing measurement and control signals and for interfacing with local operator and remote CAO system.
• Provision of routine and non-routine maintenance services for a period of nine (9) months. • Installation of Instrument air system for Gaslift manifold. • Procurement of all materials and equipment. • Operator staff training on the instrumentation System.
STATUS: Completed 2008
PROJECT: ELECTRONIC INSTRUMENTATION SYSTEM FOR CAO SCADA SAPELE AND OLOMORO FIELDS.
Experience
ABOUT WELTEK
Experience
CLIENT: SHELL PETROLEUM DEVELOPMENT COMPANY
PROJECT OVERVIEW: Installation and Commissioning of Gaslift, Electronic Field Instrumentation upgrade for Real-time System (RTS) and Gaslift Optimization in accordance with approved specifications.
The project work scope included but was not limited to the following:
Procurement of installation materials. Installation and Commissioning of Field Instrumentation and Gaslift Skids. Installation and Commissioning of new Instrument Air Package. Upgrade of PAS Host. CAO upgrade of the flow station for Gaslift Optimization using Yokogawa Stardom Foundation
Fieldbus Distributed Control System (DCS). Control Panel assembly and HMI graphics development. Handover to the Districts and asset team of SPDC.
STATUS: Completed 2008.
PROJECT: AGBADA 2 GASLIFT OPTIMIZATION AND ELECTRONIC FIELD UPGRADE.
ABOUT WELTEK
Experience
PROJECT: OBAGI FLOWSTATION FIRE FIGHTING NETWORK UPGRADE.
CLIENT: ELF PETROLEUM NIGERIA LIMITED PROJECT OVERVIEW: The intent of this project is to upgrade the fire fighting network at Obagi Flow station, OML 58 to meet new Total specifications. The project work scope includes but is not limited to the following:
Revision and update of detailed engineering for the Electrical and Instrumentation works on the project. (Pump house, deluge system and Cathodic protection of main fire ring).
Procurement of all required Electrical & Instrumentation materials. Workshop Fabrication. Site Mobilization. Site works/Installation. DCS tie-in. Pre-commissioning and Commissioning. Demobilization/Rehabilitation. As-built Documentation.
STATUS: Ongoing
ABOUT WELTEK
Experience
CLIENT: CHEVRON NIGERIA LIMITED PROJECT OVERVIEW: This project seeks to upgrade the Power generation capability and controls to accommodate anticipated electrical load increases due to the expansion of the Lekki Estate. The upgrade was in fact to dismantle the existing generators and add 3 x 2.25 kVA, 11KV generators working as standby units to the public utility power generation while maintaining the existing estate ring main system. The work scope includes but is not limited to the following: Detailed engineering design for the construction (Civil & Electrical). Procurement and/or fabricate all materials and equipment to complete the work scope: o 3# 1.8 MW diesel engine generators, o 1# 11 kV switchgear o UPS o Generator / switchgear building o PLC based control system o Day tank o Cables, and other electrical, instrument and structural materials
Construction and Installation of all materials and equipment to enable system work to intent. Testing, Pre-commissioning and Commissioning. As-built documentation.
STATUS: Completed 2008.
PROJECT: LEKKI ELECTRICAL POWER SYSTEMS UPGRADE
ABOUT WELTEK
CLIENT: NATIONAL PETROLEUM DEVELOPMENT COMPANY (OZIENGBE) PROJECT OVERVIEW:
Weltek Limited designed and built the 10,000 Barrels per day Flow Station from the Inlet Manifold to the Export lines.
The work scope included but was not limited to the following:
Detailed engineering design for the construction (Mechanical, Civil & Electrical). Construction of 10,000bbl Storage Fire water package for the Flowstation Fire Protection System. Metering facility installation. Testing, Pre-commissioning and Commissioning. As-built documentation.
STATUS: Completed 2002.
PROJECT: OZIENGBE SOUTH EPF FLOWSTATION INSTALLTIAON
Experience
ABOUT WELTEK
PROJECT: OZIENGBE SOUTH EPF FLOWSTATION INSTALLATION
CLIENT: NIGERIAN PETROLEUM DEVELOPMENT COMPANY (NPDC)
PROJECT OVERVIEW:
Weltek Limited designed and built the 10,000 Barrels per day Flow Station from the Inlet Manifold to the Export lines.
The work scope included but was not limited to the following:
Detailed engineering design for the construction (Mechanical, Civil & Electrical). Procurement and Installation of all materials and equipment to complete the work scope:
o Generator Packages
o Switchgear System
o Process Control System
o Fire and Gas System. o Export Pumps/Control Units. o Facility Lighting.
Testing, Pre-commissioning and Commissioning. As-built documentation.
STATUS: Completed 2002
Experience
ABOUT WELTEK
PROJECT: BONNY TOWNSHIP ELECTRIFICATION CLIENT: NIGERIA LIQUEFIED NATURAL GAS (NLNG)
PROJECT OVERVIEW:
With the Partnership of Weltek Limited and Imtech Vonk, B.V the intent of this project was implemented to Supply Power to the Bonny Island and environs .The project work scope included but was not limited to the following: Detailed engineering design (Electrical). Procurement of materials and equipment for 11KV Injection Sub-Station which includes:
o High Voltage Container. o High Voltage Switchgear System. o 110VDC Rectifier. o Power Transformers.
Installation of all materials and equipment to enable system work to intent. Testing, Pre-commissioning and Commissioning. As-built documentation.
STATUS: Completed 2000
Experience
ABOUT WELTEK
Weltek Growth
• Repair and Calibration of instruments • Production operation and maintenance
2000s • Systems Integration: ESD, DCS, PLCS, SCADA, SGS, HMI, IT (Allen Bradley,
Emerson, Yokogawa, HIMA).
1990s • Design and build Wellhead & Process Control
Panels
2010s • Marginal field: Deliver production facilities and operate flowstations. • Power Projects
• EPC Projects: Production facility skids: Vessels, Pumps, Generators, Motors, Metering, Manifolds and Storage Tanks
• Offshore Deep-water: Topside Skid Fabrication, Modification & Installation
1980s Founded 1986 in by two Engineers with backgrounds from NNPC and Schlumberger.
Growth Plan
Weltek Limited Plot 307 Danjuma Drive, Trans Amadi Industrial Layout, Port Harcourt, Rivers State Email: [email protected] Website: www.weltekng.com
…….advancing technology