8/10/2019 Attachment 5.5.17 - Checklist for Inclination Test Rev 2
1/2
Descriptions Date Planned Date Actual In-charge Remarks
1 Preparation
1 Overall in charge of operation Tuan/Tan AH
2 Inclination test date to be confirmed 25-Feb3 Engineering to provide approved test procedure for Inclination test by LTI Engineering Done
4 Location of inclination test Engineering Wharf side
5 Survey inclination test location Engineering
6 Hire tug boats and work boats for the operation 23-Feb Cng LV
7 Spud can/ Leg position for each leg during the inclination test to be determined Engineering 8.5 feet
8 Schedule for events for the entire inclination test including sequence of works to be carried out Chnh
9 To obtain forecast of weather condition for operation day Ready Cng LV
2 Production Preparation/ Operation Readiness Check
1 Cantilever weighing operation to be completed done Production Certified by ABS
2 Preliminary audit of lightship weight to be carried out 1 week before inclination test 22-Feb Engineering/Production
Final Carried out with ABLTI
3 Secure all movable items onboard e.g. crane, derrick travelling block, 22-Feb Tao/Bang
4 Cantilever to be in stowage position Bang
5 Mark cantilever travel position for inclination test (8 position) 22-Feb Tao/Bang/Viet 46 ft travel finalised
6 All tanks to be cleaned and dry unless specified in the test procedure 23-Feb Bang/Tao
7 Preparation of central control station onboard Engineering refer to organ chart
8 Means to measure water depth at operation location e.g. echo sounder on rig done Engineering
9 Install pendulum at 3 locations as per test procedure 21-Feb Huy/QC Viet
10 Ensure skidding system for cantilever and drillfloor are operational and done as per TP Commissioning Done
11 Check and ensure no obstruction or restriction in the skidding path of cantilever prior to the test Bang12 To check and ensure Jacking motors has sufficient gear oil level 20-Feb Bang
13 Ensure Jacking system is functional including inclination monitor Bang ready
14To arrange for essential vendors/ personnel to be onboard during the test e.g. VSP barge captain, LTI
for inclination test and jacking systemProduction/PMT
refer to organ chart
15 All necessary operational and commissioning tools to be onboard Commissioning refer to equipment chec
16 Punch mark for freeboard measurement to be marked as per TP 21-Feb Huy/QC Viet
17 Prepare tools and equipment to clean up spud can 24-Feb Production
18 Pull and free spud can prior to inclining test 23-Feb Production
19 Nylon ropes for rig handling 22-Feb Trung
3 Logistics Preparation
1 To disconnect shore power, gases, air supply to rig 23-Feb Tuan/Bang
2 To remove gangways before Jacking up 23-Feb Linh NN
3 To provide portable toilet facilities 21-Feb Huy Re-location to Maindeck
4 To prepare food and drinks during the inclination test Chnh
4 Safety
1 Emergency procedure/ plan for fire fighting and other emergencies 23-Feb morning Safety Hai
A bl f ll l d i i S f H i
Attachment 5.5.17 - Production Checklist for Inclining Test
-
8/10/2019 Attachment 5.5.17 - Checklist for Inclination Test Rev 2
2/2
9-Feb-12
Next week Remark
Cum. Planned
Activity
Completion
Cum. Actual
Activity
Completion
Cum. Planned
Activity
Completion
Cum. Actual
Activity
Completion
Incremental Balance
Cum. Planned
Activity
Completion
Preparation 9
Production Preparation/ Operation
Readiness Check19
Logistics Preparation 4
Safety 7
Inclination Test 7
Total 46
Attachment 5.5.17 - Production Checklist for Inclining Test - SUMMARY OF REMAINING ACTIVITIES
Updated as at:
Items TotalTotal
Outstanding
Last week This week