Projeto Demonstrativo para o GerenciamentoIntegrado no Setor de Chillers
Commissioning Chilled Water SystemsFrom Design to Occupancy
Execução Implementação Realização
Anthony Avendano – Horizon Engineering Associates LLP
31/03/2016 – Fortaleza, CE
1
![Page 2: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/2.jpg)
90% of business is commissioning
10 offices; 75+ employees
Established in 199520 years of building commissioning
Expert Knowledge of LEED450+ LEED projects
OUR COMPANY
Who We Are
Professional certifications andregistrations
Strong Operational Background
![Page 3: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/3.jpg)
Objective• What types of Equipment is part of the
Chilled Water System• What are the advantages of
commissioning a chilled water system• What is the commissioning process of
chilled water systems• What is required to effectively commission
a chilled water system
![Page 4: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/4.jpg)
Chilled Water Systems
• Central Plant CHW– CHW distributed to constituents
• Equipment Served– AHUs– FCUs– Secondary Loops– Tertiary loop
![Page 5: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/5.jpg)
CHW Generation
![Page 6: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/6.jpg)
CHW System Overview
![Page 7: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/7.jpg)
Types of CHW SystemFlow• There are two basic types of CHW flow
systems1. Constant flow CHW2. Variable Flow CHW
• Constant flow for smaller systems, notused much today due to energy
• Variable flow for larger systems– Can be primary secondary loop– Good for green design
![Page 8: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/8.jpg)
Primary Secondary Loop
![Page 9: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/9.jpg)
Connected Loads - Dual Temperature
• Different types of systems when theheating and cooling distribution systemsare combined
1. Two pipe system2. Four pipe systems
![Page 10: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/10.jpg)
Two Pipe System
![Page 11: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/11.jpg)
Four Pipe System
![Page 12: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/12.jpg)
Chiller Types
• Reciprocating Liquid Chillers
• Centrifugal Chillers
• Modular Chillers (scroll, screw, magneticbearing)
![Page 13: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/13.jpg)
Reciprocating Chiller
![Page 14: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/14.jpg)
Centrifugal Liquid Chillers
![Page 15: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/15.jpg)
Modular ChillersBank of Chillers Compressor Types
![Page 16: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/16.jpg)
Condenser Water• Used to remove heat from chiller and reject to
another location• Examples:o Air Cooledo Cooling Towero Natural Water Source
![Page 17: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/17.jpg)
Cooling Tower - Installed
![Page 18: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/18.jpg)
Heat Exchangers
![Page 19: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/19.jpg)
Free Cooling
![Page 20: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/20.jpg)
• The United Nations (UN) complex spansover 17 acres and includes 6 buildingstotaling 2.7 million sf, originally built in 1950
• UN’s problems were associated with agingbuilding system and not the basicconstruction, a renovation of the complexwas the most cost-effective way of replacinginefficient equipment.
• UN’s chiller plant utilizes condenser waterby two methods: a river water system and acooling tower condenser water system.
• Under normal operation, river water is useddirectly as condenser water utilizing a waterside economizer mode.
Project Profiles
![Page 21: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/21.jpg)
Why Commission yourChilled Water System?• System Integration
– Individual pieces of equipment are not the wholesystem, e.g., chillers, cooling towers, pumps, heat
exchangers, thermal storage tanks, etc.
• Efficiency– Design conditions
• Safety– Personnel and property protection
![Page 22: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/22.jpg)
CommissioningDefinitions• Definition - “The Commissioning Process is a quality-
oriented process for achieving, verifying, anddocumenting that the performance of facilities, systems,and assemblies meets defined objectives and criteria.”
- ASHRAE Guideline 0• Sets clear measurable goals for everyone
• Verifies that the owner’s requirements are beingmet throughout the design and construction phases
• Establishes accountability• Changes the way people perform• Allows designers and contractors to measure
success as well as deficiency
![Page 23: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/23.jpg)
• Training of operationsstaff
• Maximizing energy usage(utilities)
• Higher value of rentableSF
• Reduction in commondeficiencies for typicaldesign / install programs
• Peer review of existingoperating protocols
Value to Property Owners
![Page 24: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/24.jpg)
1 Identify potential issuesduring design
2 Identify/resolve issues duringconstruction
3 Successful Day 1operations. Confirmbuilding equipment andsystems operate andperform properly
4 O&M documentation iscomplete
Value of Commissioning
![Page 25: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/25.jpg)
5 Operating staff is trainedproperly
6 Reduces operating andmaintenance costs
7 Improves IAQ, occupantcomfort and productivity
8 Reduces project closeoutissues
Value of Commissioning
![Page 26: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/26.jpg)
What is the Commissioning Processfor a Chilled Water System?
• Phases– Pre-Design Phase CX– Design Phase CX– Construction Phase CX– Post-Construction Phase CX
![Page 27: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/27.jpg)
Commissioning Pre-Design Phase
• Document/review owner’s projectrequirements
• Scope and budget for commissioning• Select CxA• Create commissioning plan• Working with the owner to select design
strategies and goals
PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS
![Page 28: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/28.jpg)
User Requirements
• Design Intent Document is the place todocument the performance requirementsof the central systems as defined to meetthe needs of the users
![Page 29: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/29.jpg)
Installation Types
• New Installation– All components are new installation
• Existing– Repurposing existing equipment of spaces for
a new design
![Page 30: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/30.jpg)
Design Intent
• The chiller plant is useless as a stand-alone monument. It needs to meet theneeds of the building users in order to beconsidered successful.
![Page 31: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/31.jpg)
Common Design Issues
• Pumps controlled by load differentialpressure (dP), not staged with chillers
• Low Flow Bypass is critical to maintainminimum chilled water flow through thechillers (Overboard/Bypass Valve)
![Page 32: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/32.jpg)
Chilled Water Flow Considerations
• Differential Pressure (dP) pumping control• Low Flow Bypass controls• Chiller staging effect on flow through
chillers• Chiller modulating flow control valves to
balance flow through multiple chillers inoperation
![Page 33: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/33.jpg)
Controls• Limit the speed at which the chilled water
pump VFDs can speed up and down• Limit the time span the chilled water flow
control valve actuators can stroke from min tomax
• Review the system dPs and how the pumpstrack to maintain the lowest from setpoint
• Put in a dead band so the pumps are notalways hunting due to system size andcomplexity
![Page 34: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/34.jpg)
Commissioning - Design Phase
• Document/review basis of design• Refine the scope of commissioning• Perform design review• Update the commissioning plan• Include commissioning requirements in
construction documents– Including pre-functional checklists and
functional performance test procedures
CONSTRUCTION OCCUPANCY & OPSPRE-DESIGN DESIGN
![Page 35: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/35.jpg)
Design Review• Review of the design must be in conjunction
of the OPR.• The review should be done with the mindset
of an operator and not a designer. We needto bring a completely different perspective tothe table. We don’t want to duplicate efforts.
![Page 36: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/36.jpg)
Design Review• Design Review
– “It’s cheaper to change it on paper than afterit’s built”
– Should be completed before CD’s are issued– Otherwise will lead to contractor change
orders– “Remember, we want Cx to save the project
money not cause it to cost more”!
![Page 37: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/37.jpg)
Submittals andDocumentation• Submittals - CxA requests all necessary
documentation required to properlycommission the project through the CM– May include: manufacturer installation, O&Ms,
performance data, control drawings• Pre-functional and Functional Checklists
– Provides a full range of checks to determinethat individual components, equipment andsystems operate in accordance with the plansand specifications
![Page 38: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/38.jpg)
Commissioning - ConstructionPhase
• Update commissioning plan and schedule• Review submittals against commissioning
plan, OPR, and BOD• Review control sequences• Update test procedures• Document construction observations• Develop systems/O&M manuals
DESIGN OCCUPANCY & OPSPRE-DESIGN CONSTRUCTION
![Page 39: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/39.jpg)
Factory Testing
• Review controls• Gather information• Simulate conditions that may not be
possible in field installation• Ask questions
![Page 40: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/40.jpg)
Simulated ControlsTesting
![Page 41: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/41.jpg)
Representing a Bank ofModular Chillers
![Page 42: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/42.jpg)
Sample Test Procedure• Simulate testing conditions not possible/safe in
field
![Page 43: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/43.jpg)
Checklists
• The components of the checklist:– Installation– Pre-functional– Functional and performance testing– Acceptance testing
![Page 44: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/44.jpg)
Checklists• Developing Cx Checklists
– Checklists should document the entirehistory of a piece of equipment as it shouldhave installation, pre-functional andfunctional checks within its fields.
![Page 45: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/45.jpg)
ElectricalConsiderations• Plant Operations-Emergency Power,
critical systems etc. (i.e. server rooms)• Uninterrupted Power Supplies• Plant Safety-Lighting / Exit signs
![Page 46: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/46.jpg)
Installation Review
• Design Details• Specifications• Submittal Requirements• IOMs• Code Compliance• Mock-ups• Good Practice (recommendations)
![Page 47: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/47.jpg)
Installation Comments# Tag Floor /
Coordinate Trade FoundBy
DateFound
ApplicableSpec
Issue / Impact /Recommendation Action
1 HX-402B-4 MR-50 Mechanical AA 02/26/15 Drawing
M501 detail 6Vent not installed athigh point as specified
![Page 48: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/48.jpg)
Pre-Functional
• Static Testing• Testing and Balancing (TAB)• Vendor check-out sheets• Point to Point
![Page 49: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/49.jpg)
Functional
• Sequence of Operations (SoO)• Safeties• Performance• User Interface
![Page 50: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/50.jpg)
Sequence of Operations
![Page 51: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/51.jpg)
Mode Flow Schedule
![Page 52: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/52.jpg)
Control Valve Schedule
![Page 53: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/53.jpg)
Automatic Control Valve
![Page 54: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/54.jpg)
CHW System SampleChecklist
![Page 55: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/55.jpg)
Cx Reports• Field Observation Report (FOR) or Site
Inspection Report– Documents each visit– Filled out each time the site is visited
• Deficiency Sheet– Must be completed with each deficiency– All data should be filled
![Page 56: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/56.jpg)
On Site• Communication - Team leader/PC/Owners Rep• Scheduling your site visit• Pre-planning precautions
– Is a shut down required?– Disruption of service
• Notify CM/owner of your presence• Report any issues found to appropriate PIC• Note deficiencies• Complete field report
![Page 57: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/57.jpg)
Required Resources toCommission• Team Participation and cooperation• Checklist-Detailed bases of field visits• Testing Equipment
o PanametricoHDMoData Loggerso Sensors
![Page 58: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/58.jpg)
Panametrics-Verify Flow Readings
![Page 59: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/59.jpg)
Hydro Data Meter (HDM)
• Pressure readings and the performancecurve:
![Page 60: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/60.jpg)
Hydro Data Meter (HDM)• Pressure readings and the performance
curve:
![Page 61: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/61.jpg)
Hydro Data Meter (HDM)• Circuit Setters
![Page 62: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/62.jpg)
Data Logging
• Utilized for the following Cxactivities:– Trending of relative humidity and
temperature of individual VAVs, AHU,RTU, AC Units, etc.
– Verify motor operation (typicallycondensate pumps, air compressors,fuel oil pumps, etc.)
![Page 63: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/63.jpg)
Additional Test Equipment in CxAgents toolbox
• Sound meters• Multi-meters• Infrared Thermometer• UE2000 Ultraprobe
![Page 64: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/64.jpg)
Commissioning - Occupancy andOperations Phase
• Assist with maintenance managementprogram
• Adjust for occupancy/warranty period• Off-season testing• Optional: lessons-learned meeting• Optional: periodic re-commissioning
DESIGN CONSTRUCTIONPRE-DESIGN OCCUPANCY & OPS
![Page 65: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/65.jpg)
Acceptance• The process of turnover and accepting the
equipment. It is permissible to accept equipmentprovided that the items left to complete areidentified and required to be completed
• When is system complete?• Who signs-off?
― Construction Manager― Installing Contractor― Design Professional― CxA
![Page 66: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/66.jpg)
As-Built Review
• Prior to completion of the project, HEAshould review the as-built documentationfor thoroughness and completion prior togoing to the design team for finalapproval
– How should this be performed?
![Page 67: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/67.jpg)
Occupancy Phase
• Post occupancy• Seasonal testing• Warranty• Training• Ongoing Cx efforts
![Page 68: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/68.jpg)
Warranty Management
• Warranty management is broken into twostages
1. The 10 month back check and interviewprocess that is required by LEED to ensurethe building is working correctly
2. The second part is if in fact there was aissue after the building was in operation, wewould go back to verify the issue
![Page 69: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/69.jpg)
Warranty Phase
• CxA role• Deliverables• Specification• Extended warranty items• Documentation of warranty periods• Equipment and systems acceptance• Warranty issues and review
![Page 70: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/70.jpg)
Seasonal Testing
• Seasonal Testing― Seasonal testing should be done on heating
and cooling systems. This test is done onthe system within its season of operation.Cooling tests in summer and heating tests inthe winter. Try to use “design days”.
― There is the issue of fan coil units and heatpumps operating in the shoulder season.These units should also be checked duringthese off seasons.
![Page 71: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/71.jpg)
Training
• Training Requirements• Training Documents• Syllabus Creating• Documenting Training Sessions
![Page 72: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/72.jpg)
Training• Gives building operators chance to
walkthrough operations and maintenancewith the construction team to relay allapplicable knowledge
![Page 73: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/73.jpg)
Conclusions
• Proper commissioning of your chilledwater system is essential to verify:– System operates per design intent– System run/performs efficiently– The staff are properly trained for turnover– To minimize call back for arising issues
![Page 74: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From](https://reader031.vdocument.in/reader031/viewer/2022022422/5a98e6517f8b9aba4a8d3644/html5/thumbnails/74.jpg)
Email: [email protected]: www.horizon-engineering.com
• New York, NY• Long Island, NY• Albany, NY• Syracuse, NY• Charlotte, NC• St. Louis, MO• Baltimore, MD• Salt Lake City, UT• Detroit, MI• Boston, MA
THANK YOU
QUESTIONS?