Projeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From Design to Occupancy Execução Implementação Realização Anthony Avendano – Horizon Engineering Associates LLP 31/03/2016 – Fortaleza, CE 1

Upload: phungnhu

Post on 02-Mar-2018

216 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Projeto Demonstrativo para o GerenciamentoIntegrado no Setor de Chillers

Commissioning Chilled Water SystemsFrom Design to Occupancy

Execução Implementação Realização

Anthony Avendano – Horizon Engineering Associates LLP

31/03/2016 – Fortaleza, CE

1

Page 2: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

90% of business is commissioning

10 offices; 75+ employees

Established in 199520 years of building commissioning

Expert Knowledge of LEED450+ LEED projects

OUR COMPANY

Who We Are

Professional certifications andregistrations

Strong Operational Background

Page 3: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Objective• What types of Equipment is part of the

Chilled Water System• What are the advantages of

commissioning a chilled water system• What is the commissioning process of

chilled water systems• What is required to effectively commission

a chilled water system

Page 4: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Chilled Water Systems

• Central Plant CHW– CHW distributed to constituents

• Equipment Served– AHUs– FCUs– Secondary Loops– Tertiary loop

Page 5: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

CHW Generation

Page 6: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

CHW System Overview

Page 7: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Types of CHW SystemFlow• There are two basic types of CHW flow

systems1. Constant flow CHW2. Variable Flow CHW

• Constant flow for smaller systems, notused much today due to energy

• Variable flow for larger systems– Can be primary secondary loop– Good for green design

Page 8: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Primary Secondary Loop

Page 9: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Connected Loads - Dual Temperature

• Different types of systems when theheating and cooling distribution systemsare combined

1. Two pipe system2. Four pipe systems

Page 10: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Two Pipe System

Page 11: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Four Pipe System

Page 12: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Chiller Types

• Reciprocating Liquid Chillers

• Centrifugal Chillers

• Modular Chillers (scroll, screw, magneticbearing)

Page 13: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Reciprocating Chiller

Page 14: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Centrifugal Liquid Chillers

Page 15: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Modular ChillersBank of Chillers Compressor Types

Page 16: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Condenser Water• Used to remove heat from chiller and reject to

another location• Examples:o Air Cooledo Cooling Towero Natural Water Source

Page 17: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Cooling Tower - Installed

Page 18: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Heat Exchangers

Page 19: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Free Cooling

Page 20: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

• The United Nations (UN) complex spansover 17 acres and includes 6 buildingstotaling 2.7 million sf, originally built in 1950

• UN’s problems were associated with agingbuilding system and not the basicconstruction, a renovation of the complexwas the most cost-effective way of replacinginefficient equipment.

• UN’s chiller plant utilizes condenser waterby two methods: a river water system and acooling tower condenser water system.

• Under normal operation, river water is useddirectly as condenser water utilizing a waterside economizer mode.

Project Profiles

Page 21: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Why Commission yourChilled Water System?• System Integration

– Individual pieces of equipment are not the wholesystem, e.g., chillers, cooling towers, pumps, heat

exchangers, thermal storage tanks, etc.

• Efficiency– Design conditions

• Safety– Personnel and property protection

Page 22: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

CommissioningDefinitions• Definition - “The Commissioning Process is a quality-

oriented process for achieving, verifying, anddocumenting that the performance of facilities, systems,and assemblies meets defined objectives and criteria.”

- ASHRAE Guideline 0• Sets clear measurable goals for everyone

• Verifies that the owner’s requirements are beingmet throughout the design and construction phases

• Establishes accountability• Changes the way people perform• Allows designers and contractors to measure

success as well as deficiency

Page 23: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

• Training of operationsstaff

• Maximizing energy usage(utilities)

• Higher value of rentableSF

• Reduction in commondeficiencies for typicaldesign / install programs

• Peer review of existingoperating protocols

Value to Property Owners

Page 24: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

1 Identify potential issuesduring design

2 Identify/resolve issues duringconstruction

3 Successful Day 1operations. Confirmbuilding equipment andsystems operate andperform properly

4 O&M documentation iscomplete

Value of Commissioning

Page 25: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

5 Operating staff is trainedproperly

6 Reduces operating andmaintenance costs

7 Improves IAQ, occupantcomfort and productivity

8 Reduces project closeoutissues

Value of Commissioning

Page 26: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

What is the Commissioning Processfor a Chilled Water System?

• Phases– Pre-Design Phase CX– Design Phase CX– Construction Phase CX– Post-Construction Phase CX

Page 27: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Commissioning Pre-Design Phase

• Document/review owner’s projectrequirements

• Scope and budget for commissioning• Select CxA• Create commissioning plan• Working with the owner to select design

strategies and goals

PRE-DESIGN DESIGN CONSTRUCTION OCCUPANCY & OPS

Page 28: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

User Requirements

• Design Intent Document is the place todocument the performance requirementsof the central systems as defined to meetthe needs of the users

Page 29: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Installation Types

• New Installation– All components are new installation

• Existing– Repurposing existing equipment of spaces for

a new design

Page 30: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Design Intent

• The chiller plant is useless as a stand-alone monument. It needs to meet theneeds of the building users in order to beconsidered successful.

Page 31: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Common Design Issues

• Pumps controlled by load differentialpressure (dP), not staged with chillers

• Low Flow Bypass is critical to maintainminimum chilled water flow through thechillers (Overboard/Bypass Valve)

Page 32: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Chilled Water Flow Considerations

• Differential Pressure (dP) pumping control• Low Flow Bypass controls• Chiller staging effect on flow through

chillers• Chiller modulating flow control valves to

balance flow through multiple chillers inoperation

Page 33: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Controls• Limit the speed at which the chilled water

pump VFDs can speed up and down• Limit the time span the chilled water flow

control valve actuators can stroke from min tomax

• Review the system dPs and how the pumpstrack to maintain the lowest from setpoint

• Put in a dead band so the pumps are notalways hunting due to system size andcomplexity

Page 34: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Commissioning - Design Phase

• Document/review basis of design• Refine the scope of commissioning• Perform design review• Update the commissioning plan• Include commissioning requirements in

construction documents– Including pre-functional checklists and

functional performance test procedures

CONSTRUCTION OCCUPANCY & OPSPRE-DESIGN DESIGN

Page 35: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Design Review• Review of the design must be in conjunction

of the OPR.• The review should be done with the mindset

of an operator and not a designer. We needto bring a completely different perspective tothe table. We don’t want to duplicate efforts.

Page 36: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Design Review• Design Review

– “It’s cheaper to change it on paper than afterit’s built”

– Should be completed before CD’s are issued– Otherwise will lead to contractor change

orders– “Remember, we want Cx to save the project

money not cause it to cost more”!

Page 37: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Submittals andDocumentation• Submittals - CxA requests all necessary

documentation required to properlycommission the project through the CM– May include: manufacturer installation, O&Ms,

performance data, control drawings• Pre-functional and Functional Checklists

– Provides a full range of checks to determinethat individual components, equipment andsystems operate in accordance with the plansand specifications

Page 38: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Commissioning - ConstructionPhase

• Update commissioning plan and schedule• Review submittals against commissioning

plan, OPR, and BOD• Review control sequences• Update test procedures• Document construction observations• Develop systems/O&M manuals

DESIGN OCCUPANCY & OPSPRE-DESIGN CONSTRUCTION

Page 39: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Factory Testing

• Review controls• Gather information• Simulate conditions that may not be

possible in field installation• Ask questions

Page 40: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Simulated ControlsTesting

Page 41: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Representing a Bank ofModular Chillers

Page 42: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Sample Test Procedure• Simulate testing conditions not possible/safe in

field

Page 43: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Checklists

• The components of the checklist:– Installation– Pre-functional– Functional and performance testing– Acceptance testing

Page 44: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Checklists• Developing Cx Checklists

– Checklists should document the entirehistory of a piece of equipment as it shouldhave installation, pre-functional andfunctional checks within its fields.

Page 45: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

ElectricalConsiderations• Plant Operations-Emergency Power,

critical systems etc. (i.e. server rooms)• Uninterrupted Power Supplies• Plant Safety-Lighting / Exit signs

Page 46: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Installation Review

• Design Details• Specifications• Submittal Requirements• IOMs• Code Compliance• Mock-ups• Good Practice (recommendations)

Page 47: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Installation Comments# Tag Floor /

Coordinate Trade FoundBy

DateFound

ApplicableSpec

Issue / Impact /Recommendation Action

1 HX-402B-4 MR-50 Mechanical AA 02/26/15 Drawing

M501 detail 6Vent not installed athigh point as specified

Page 48: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Pre-Functional

• Static Testing• Testing and Balancing (TAB)• Vendor check-out sheets• Point to Point

Page 49: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Functional

• Sequence of Operations (SoO)• Safeties• Performance• User Interface

Page 50: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Sequence of Operations

Page 51: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Mode Flow Schedule

Page 52: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Control Valve Schedule

Page 53: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Automatic Control Valve

Page 54: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

CHW System SampleChecklist

Page 55: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Cx Reports• Field Observation Report (FOR) or Site

Inspection Report– Documents each visit– Filled out each time the site is visited

• Deficiency Sheet– Must be completed with each deficiency– All data should be filled

Page 56: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

On Site• Communication - Team leader/PC/Owners Rep• Scheduling your site visit• Pre-planning precautions

– Is a shut down required?– Disruption of service

• Notify CM/owner of your presence• Report any issues found to appropriate PIC• Note deficiencies• Complete field report

Page 57: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Required Resources toCommission• Team Participation and cooperation• Checklist-Detailed bases of field visits• Testing Equipment

o PanametricoHDMoData Loggerso Sensors

Page 58: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Panametrics-Verify Flow Readings

Page 59: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Hydro Data Meter (HDM)

• Pressure readings and the performancecurve:

Page 60: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Hydro Data Meter (HDM)• Pressure readings and the performance

curve:

Page 61: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Hydro Data Meter (HDM)• Circuit Setters

Page 62: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Data Logging

• Utilized for the following Cxactivities:– Trending of relative humidity and

temperature of individual VAVs, AHU,RTU, AC Units, etc.

– Verify motor operation (typicallycondensate pumps, air compressors,fuel oil pumps, etc.)

Page 63: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Additional Test Equipment in CxAgents toolbox

• Sound meters• Multi-meters• Infrared Thermometer• UE2000 Ultraprobe

Page 64: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Commissioning - Occupancy andOperations Phase

• Assist with maintenance managementprogram

• Adjust for occupancy/warranty period• Off-season testing• Optional: lessons-learned meeting• Optional: periodic re-commissioning

DESIGN CONSTRUCTIONPRE-DESIGN OCCUPANCY & OPS

Page 65: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Acceptance• The process of turnover and accepting the

equipment. It is permissible to accept equipmentprovided that the items left to complete areidentified and required to be completed

• When is system complete?• Who signs-off?

― Construction Manager― Installing Contractor― Design Professional― CxA

Page 66: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

As-Built Review

• Prior to completion of the project, HEAshould review the as-built documentationfor thoroughness and completion prior togoing to the design team for finalapproval

– How should this be performed?

Page 67: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Occupancy Phase

• Post occupancy• Seasonal testing• Warranty• Training• Ongoing Cx efforts

Page 68: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Warranty Management

• Warranty management is broken into twostages

1. The 10 month back check and interviewprocess that is required by LEED to ensurethe building is working correctly

2. The second part is if in fact there was aissue after the building was in operation, wewould go back to verify the issue

Page 69: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Warranty Phase

• CxA role• Deliverables• Specification• Extended warranty items• Documentation of warranty periods• Equipment and systems acceptance• Warranty issues and review

Page 70: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Seasonal Testing

• Seasonal Testing― Seasonal testing should be done on heating

and cooling systems. This test is done onthe system within its season of operation.Cooling tests in summer and heating tests inthe winter. Try to use “design days”.

― There is the issue of fan coil units and heatpumps operating in the shoulder season.These units should also be checked duringthese off seasons.

Page 71: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Training

• Training Requirements• Training Documents• Syllabus Creating• Documenting Training Sessions

Page 72: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Training• Gives building operators chance to

walkthrough operations and maintenancewith the construction team to relay allapplicable knowledge

Page 73: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Conclusions

• Proper commissioning of your chilledwater system is essential to verify:– System operates per design intent– System run/performs efficiently– The staff are properly trained for turnover– To minimize call back for arising issues

Page 74: Commissioning Chilled Water Systems From Design ... - · PDF fileProjeto Demonstrativo para o Gerenciamento Integrado no Setor de Chillers Commissioning Chilled Water Systems From

Email: [email protected]: www.horizon-engineering.com

• New York, NY• Long Island, NY• Albany, NY• Syracuse, NY• Charlotte, NC• St. Louis, MO• Baltimore, MD• Salt Lake City, UT• Detroit, MI• Boston, MA

THANK YOU

QUESTIONS?