    ITEM DESCRIPTION QTY PRICE AMOUNT

    CONCRETE WORK

    Reinforced in-situ concrete (1:2:4 -19mm aggregate);

    A Cement bags for beams 5 12.00 60

    B Trips of sand (6m) double axle 1 280.00 280

    C Trips of quarry chippings (6m ) double axle 1 550.00 550

    Reinforcement

    D 12mm diameter in columns 6 15.00 90

    E 8mm diameter in links 3 10 30

    F Binding wire (roll) 30

    Formwork

    G 50mm nails (pound) 1 8 8

    H 75mm nails (box) 1 12 12

    J 100mm nails (box) 1 15 15

    CONCRETE WORK 1075

    Carried to summary

    ROOFING

    K Roofing sheet 83 28.00 2324.00

    L Ridge cap, 450mm girth 60 3.00 180.00

    ROOFING

    Carried to summary 2504

    1/1

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    2/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    CARPENTRY

    Sawn treated hardwood

    A 50 x 150mm Rafters 57 12 1,764.00

    B 50 x 75mm Purlins 18 10 180.00

    C 50 x 50mm Battens 70 7 490

    D Ceiling noggings 65 7 455

    E Roofing nails (bx) 3 20.00 60

    F Felt (1 roll) 60

    G 50mm nails (pound) 1 12 12

    H 75mm nails (box) 2 18.00 36

    J 100mm nails (box) 2 18.00 36

    CARPENTRY

    Carried to summary 3093

    JOINERY

    K 25 x 300mm fascia board 29 15 312.00

    Doors(panelled)

    L 900 x 2100mm 6 80.00 480

    Ironmongery

    M Brass butt hinges 6 5.00 30

    N Mortice locks 6 40.00 240

    JOINERY

    Carried to summary 1062

    METALWORK

    P 5000.00

    Q 400.00

    METALWORK

    Carried to summary 1/2 5400

    Provisional sum of GH5000.00 for portable metal gateswith lock

    Provisional sum of GH400.00 for fixing metal gates

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    3/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    ELECTRICAL INSTALLATION

    A Item 800.00

    ELECTRICAL INSTALLATION

    Carried to summary 800

    PLASTERWORK AND OTHER FINISHES, ETC

    B Cement bags for plastering blockwalls 27 12 324

    C Cement bags for concrete floor 7 12 84

    Floor tiles

    D 450 x 450mm ceramic floor tiles / m ( 87m) 1,740.00

    E Tile grout 3 8.00 24.00

    F Tile cement (Permafix) 7 8.50 59.50

    G Ceramic skirting (pcs) 356 1.50 534.00

    H Plastic T&G panel for ceiling (86m) 1,112.00

    PLASTERWORK AND OTHER FINISHES, ETC

    Carried to summary 3878

    GLAZING

    Aluminium glazed sliding windows (Italian)

    J 4050 x2100mm (sliding door) 3 1000 3000

    K 650 x 1200mm (sliding window) 2 390.00 780

    M 600 x 1500mm (sliding window) 1 410 410

    GLAZING

    Carried to summary 4190

    1/3

    Provisional sum of GH800.00 for Electricalwiring,Trunking and Fittings.

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    4/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    PAINTING AND DECORATION

    A 3 Coats Leyland Emulsion paint (bkt) 7 18.00 126.00

    B Gloss oil paint (gal) 4 18.00 72

    C Turpentine (gal) 2 25.00 50

    D Putty filler (bkt) 1 17.00 17

    E Solognium Wood preservative (gal) 1 25.00 25

    F Desban wood preservative (gal) 1 16.00 16

    PAINTING AND DECORATIONCarried to summary 306

    1/4

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    5/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    SUMMARY

    (SUPERSTRUCTURE)

    CONCRETE WORK 1075

    ROOFING 2504

    CARPENTRY 3093

    JOINERY 1062

    METAL WORK 5400

    ELECTRICAL INSTALLATION 800

    3878

    GLAZING 4190

    PAINTING AND DECORATION 306

    22308

    ADD

    Preliminaries includes;

    10% 2231

    ADD

    Labour and supervision 33% 7361

    ADD

    Contingencies 10% 2231

    TOTAL COST 34130

    ALL PRICES ARE FROM THE OPEN MARKET,TEMA

    (APRIL, 2011)

    1/5

    PLASTERWORK AND OTHER WALL AND CEILINGFINISHINGS IN-SITU FINISHINGS.

    Transportation, onloadind & offloading & stacking ofmaterials on site, water for works,site clearance etc.)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    6/34

    E -TEMA

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    7/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    8/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    9/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    10/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    11/34

    ESTIMATE FOR THE CONSTRUCTION OF SCALE BUSINESS OFFICE AT COMM.1-TEM

    ITEM DESCRIPTION QTY PRICE AMOUNT

    ( A.) SUBSTRUCTURE

    FILLING

    A 1 350 350

    B 1 280 280

    CONCRETE WORK

    Plain in-situ concrete (1:3:6 -38mm aggregate);

    C Cement bags for blinding 75mm thick 1 12.00 12

    D Cement bags for strip foundation 6 12.00 72

    Reinforced in-situ concrete (1:2:4 -19mm aggregate);

    E Cement bags for concrete floor bed. 17 12.00 204

    F Cement bags for column bases 5 12.00 60

    G Cement bags for columns 3 12.00 36

    H Trips of sand (12m) double axle 1 280.00 280

    J Trips of stones(12m) double axle 1 350.00 350

    K Trips of quarry chippings (12m ) double axle 1 550.00 550

    Reinforcement

    L 12mm diameter in columns 14 15.00 210

    M 8mm diameter in links 5 10 50

    N Binding wire (roll) 1 60.00 60

    Formwork

    P Wawa boards for profile and formwork 16 12.00 192

    Q 25 x 150mm Wooden pegs 18 2 36

    c/f 2742

    1/1

    ITEM DESCRIPTION QTY PRICE AMOUNT

    Trips of gravel for hardcore filling (12m) double axle, compactin 150mm layers thick(Amasaman)

    Trips of sand for backfilling around foundation (12m) doubleaxle(Amasaman)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    12/34

    Formwork cont'd 2742

    A 50 x 100mm timber scantlings 4 9.00 36

    B 50mm nails (pound) 1 8 8

    C 75mm nails (box) 1 18.00 18

    D 100mm nails (box) 1 18.00 18

    BLOCKWORK

    E 150mm thick block pieces 445 1 623

    F Cement bags for laying blockwalls 10 12.00 120

    SUBSTRUCTURE

    Carried to summary 3565

    1/2

    (B.) SUPERSTRUCTURE

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    13/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    CONCRETE WORKS

    A Cement bags for columns 10 12.00 120

    B Cement bags for lintel 11 12.00 132

    C Trip of sand (12m) double axle 1 280.00 280

    D Trip of quarry chippings (12m ) double axle 1 540.00 540

    Reinforcement

    E 12mm diameter in columns 13 15.00 195

    F 12mm diameter in lintels 16 15.00 240

    G 8mm diameter in links 10 10.00 100

    CONCRETE WORKS

    Carried to summary 787

    BLOCKWORK

    H 150mm thick block pieces 869 1.40 1217

    J Cement bags for laying blocks 20 12.00 240

    BLOCKWORK

    Carried to summary 1457

    ROOFING

    CORRUGATED OR TROUGHED ROOFING

    K 20 28.00 560.00

    L Ridge cap, 450mm girth 52 3.00 156.00

    M Roofing nails (bx) 2 20.00 40

    N Felt (1 roll) 50

    ROOFING

    Carried to summary 1/3 806

    ITEM DESCRIPTION QTY PRICE AMOUNT

    0.6mm long span corrugated aluminium sheet roofing asdescribed:-

    Roof covering with two corrugations side lap fixed tohardwood purlins at 1050mm centres. 1200 X 2400mm

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    14/34

    CARPENTRY

    Sawn treated hardwood

    A 50 x 150mm Purlins 18 9 1,764.00

    B 50 x 75mm Rafters 18 10 180.00

    C 50 x 50mm sprockets 2 7 14

    CARPENTRY

    Carried to summary 1958

    JOINERY

    D 25 x 300mm fascia board 9 15 312.00

    Doors(panelled)

    E 1400 x 2100mm 1 190 190

    F 900 x 2100mm 2 80.00 160

    Ironmongery

    G Brass butt hinges 6 5.00 30

    H Mortice locks 4 40.00 160

    JOINERY

    Carried to summary 852

    METALWORK

    J 1700.00

    METALWORK

    Carried to summary 1700

    PLUMBING INSTALLATION

    K Toilet roll holders 1 5 5

    L TWYFORD W.C. suite 1 230.00 230

    M TWYFORD Wash hand basin (pedestal) 1 160.00 160

    N 500

    PLUMBING INSTALLATION

    Carried to summary 1/4 895

    Provisional sum of GH1700.00 for fixing burglar proofing toSliding door w2indows

    Provisional sum of GH500.00 for plumbing installation .

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    15/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    ELECTRICAL INSTALLATION

    A Item 800.00

    ELECTRICAL INSTALLATION

    Carried to summary 800.00

    PLASTERWORK AND OTHER FINISHES, ETC

    B Cement bags for plastering blockwalls 27 12 324

    C Cement bags for screeding concrete floor 5 12 60

    Floor tiles

    D 400 x 400mm ceramic floor tiles / m ( 320m) 21 25.00 525.00

    E Tile grout 5 8.00 40.00

    F Tile cement (Permafix) 10 8.50 85.00

    Wall tiles

    G 8 18.00 1,660.00

    C/F 2,694.00

    H Tile grout 3 8.00 24.00

    J Tile cement (Permafix) 6 8.50 51.00

    K Plastic T&G panel for ceiling/ m (386m) 21 12.50 262.50

    PLASTERWORK AND OTHER FINISHES, ETC

    Carried to summary 5726

    GLAZING

    Aluminium glazed sliding windows (Italian)

    L 1800 x2100mm (sliding door) 1 580.00 580

    M 2700 x 1200mm (sliding window) 1 390.00 390

    1/5 c/f 970

    Provisional sum of GH800.00 for Electrical wiring,Trunkingand Fittings.

    200 x 300mm ceramic floor tiles / m ( 166m)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    16/34

    ITEM DESCRIPTION QTY PRICE AMOUNT

    b/f 970

    A 1800 x 1200mm 3 260.00 780

    B 700 x 600mm 1 60.00 60

    GLAZING

    Carried to summary 1810

    PAINTING AND DECORATION

    C 3 Coats Leyland Emulsion paint (bkt) 7 18.00 126.00

    D Gloss oil paint (gal) 1 18.00 18

    E Turpentine (gal) 1 25.00 25

    F Putty filler (bkt) 1 17.00 17

    G Solognium Wood preservative (gal) 1 25.00 25

    H Desban wood preservative (gal) 1 16.00 16

    J 150mm wide painting brush for emulsion paint 2 3.00 6

    K 150mm wide painting brush for gloss oil paint 2 1.50 3

    SUPERSTRUCTURE

    Carried to summary 236

    1/6

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    17/34

    SUMMARY

    ITEM DESCRIPTION QTY PRICE AMOUNT

    SUBSTRUCTURE 3565

    (SUPERSTRUCTURE)

    CONCRETE WORK 787

    BLOCKWORK 1457

    ROOFING 806

    CARPENTRY 1958

    JOINERY 852

    ELECTRICAL INSTALLATION 800.00

    5726

    GLAZING 1810

    PAINTING AND DECORATION 236

    17996

    ADD

    Preliminaries includes;

    10% 1800

    ADD

    Labour and supervision 33% 5939

    ADD

    Contingencies 10% 1800

    TOTAL COST ###

    ALL PRICES ARE FROM THE OPEN MARKET,TEMA

    (MARCH, 2011)

    1/7

    PLASTERWORK AND OTHER WALL AND CEILINGFINISHINGS IN-SITU FINISHINGS.

    Setting out and excavation of works, transportation, offloading& stacking of materials on site, water for works,site clearanceetc.)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    18/34

    A

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    19/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    20/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    21/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    22/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    23/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    24/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    25/34

    ESTIMATE FOR PROPOSED TWO STORY RESIDENCE AT PANTAN ,ACCRA

    ITEM DESCRIPTION QTY PRICE AMOUNT

    ( A.) SUBSTRUCTURE

    FILLING

    A 11 380 4180

    B 1 280 280

    CONCRETE WORK

    Plain in-situ concrete (1:3:6 -38mm aggregate);

    C Cement bags for blinding 75mm thick 2 12.00 24

    D Cement bags for strip foundation 45 12.00 540

    Reinforced in-situ concrete (1:2:4 -19mm aggregate);

    E Cement bags for concrete floor bed. 193 12.00 2316

    F Cement bags for column bases 25 12.00 300

    G Cement bags for columns 25 12.00 300

    H Trips of sand (12m) double axle 2 280.00 560

    J Trips of stones(12m) double axle 1 350.00 350

    K Trips of quarry chippings (12m ) double axle 3 550.00 1650

    Reinforcement

    L 12mm diameter in column bases 37 15.00 555

    M 16mm diameter in columns 29 20.00 580

    P 10mm diameter in links 21 10 210

    Q Binding wire (roll) 1 60.00 60

    Formwork

    R Wawa boards for profile and formwork 39 12.00 468

    S 25 x 150mm Wooden pegs 77 2 154

    c/f 11972

    Trips of gravel for hardcore filling (12m) double axle,compact in 150mm layers thick(Amasaman)

    Trips of sand for backfilling around foundation (12m)double axle(Amasaman)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    26/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    27/34

    1/2

    (B.) SUPERSTRUCTURE

    Item Description Qty Price Amount

    SUPERSTRUCTURE (GROUND & FIRST FLOORS)

    CONCRETE WORKS

    Reinforced in-situ concrete (1:2:4 -19mm aggregate);

    A Cement bags for columns 51 12.00 612

    B Cement bags for lintel and beam 86 12.00 1032

    C Cement bags for concrete slab 136 12.00 1632

    D 2 180.00 360

    E Trips of sand (12m) double axle 2 280 560

    F Trips of quarry chippings (12m ) double axle 4 550.00 2200

    Reinforcement

    `

    G 16mm diameter in columns 129 20 2580

    H 16mm diameter in beams and lintels 198 15 2970

    J 12mm diameter in suspended concrete slab 337 15 5055

    K 10mm diameter in links for columns 91 10.00 910

    L 10mm diameter in stirrups in beams and lintels 200 10.00 2000

    M Binding wire (roll) 25kg 1 60.00 60

    Formwork

    N Vertical sides and soffit of beams and lintels 60 12.00 720

    P Vertical sides of column 45 12.00 540

    Q Soffit of slabs 60 12.00 720

    R Sides and soffit of stairs 10 12.00 120

    S 50 x 100mm timber scantlings 66 9.00 594

    T 50 x 100mm timber scantlings 23 9.00 207

    Precast moulded Circular columns,300mm diameter forentrance porch

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    28/34

    c/f 2901

    1/3

    Item Description Qty Price Amount

    Formwork cont'd 2901

    A 50mm nails (pound) 2 12 24

    B 75mm nails (box) 4 18.00 72

    C 100mm nails (box) 2 18.00 36

    CONCRETE WORKS

    Carried to summary 14979

    BLOCKWORK

    D 100mm thick block pieces 7,865 1 11011

    E Cement bags for laying blocks and on concrete roof slab 81 12.00 972

    BLOCKWORK

    Carried to summary 11983

    ROOFING

    F 13,870.42

    (Tel; +233-021-810938/9)

    G Silicon (bx) 5 100.00 500

    H 38mm (2") roofing nails (bx) 6 20.00 120

    J Screws and Rebates 60

    ROOFING

    Carried to summary 14550

    CARPENTRY

    Sawn treated hardwood

    K 50 x 150mm Purlins 109 12 1,764.00

    L 50 x 75mm Jack Rafters 86 9 65.00

    M 50 x 75mm Valley Rafters 23 9 70.00

    Provisional sum of GH13,870.42 for fixing 0.40mmMETALEX Aluzinc M Panel, ridge and eave cap,eave andside trims,0.50mm Chromadek gutter, and M clips.

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    29/34

    N 50 x 50mm sprockets 30 6 80

    CARPENTRY

    Carried to summary 1/4 1979

    Item Description Qty Price Amount

    JOINERY

    A 50 x 150mm door frame 17 12 204.00

    B 25 x 300mm fascia board 41 12 312.00

    Doors(panelled)

    C 150 x2100mm 1 350 350

    D 900 x 2100mm 10 150 1500

    E 750 x 2100mm 8 90 720

    Ironmongery

    F Brass butt hinges 21 5.00 105

    G Mortice locks 19 45.00 855

    JOINERY

    Carried to summary 3530

    METALWORK

    G 1 4500.00 4500

    (+233-021-666791)

    J 3,500.00

    METALWORK

    Carried to summary 8000

    PLUMBING INSTALLATION

    K Toilet roll holders 7 10.00 70

    L Towel rails 4 20.00 80

    M TWYFORD W.C. suite 7 250.00 1750

    N TWYFORD Wash hand basin (pedestal) 7 160.00 1120

    Provisional sum for PASICO Turn-key shutter verticalsliding garage door,(2850 x 2100mm)

    Provisional sum of GH3,500.00 for fixing burglar proofingto doors and windows.

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    30/34

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    31/34

    N Tile cement (Permafix) 106 8.50 901.00

    c/f 16,159.00

    1/6

    Item Description Qty Price Amount

    Plaster work con't 16159

    Wall tiles

    A 14.00 1,652.00

    B Tile grout 8 8.00 64.00

    C Tile cement (Permafix) 27 9.50 256.50

    F Plastic T&G panel for ceiling/ m (501m) 11.50 5,762.00

    PLASTERWORK AND OTHER FINISHES, ETCCarried to summary 24428

    GLAZING

    Aluminium glazed sliding windows (Italian)

    E 1500 x 1200mm 2 450 900

    F 1800 x 1200mm 15 500 7500

    G 1200 x 1200mm 3 350 1050

    H 900 x 600mm 7 300 2100

    150 x150 x100mm glass block (coloured) 533 6 3198

    GLAZING

    Carried to summary 14748

    PAINTING AND DECORATION

    J Leyland Emulsion paint (bkt) 38 21.00 798.00

    K Gloss oil paint (gal) 4 18.00 72

    L Turpentine (gal) 2 25.00 50

    M Putty filler (bkt) 4 17.00 68

    N Solognium Wood preservative (gal) 2 25.00 50

    200 x 300mm ceramic floor tiles / m ( 118m)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    32/34

    P Desban wood preservative (gal) 2 16.00 32

    c/f 1020

    1/7

    Item Description Qty Price Amount

    Painting and decoration con't 1020

    A Wood lacquer (gal) 3 25.00 75

    B 150mm wide painting brush for emulsion paint 5 7 35

    C 150mm wide painting brush for gloss oil paint 5 5 25

    ###

    SUPERSTRUCTURE

    Carried to summary ###

    Allow the provisional sum of GH 10,000.00 for Balustradeand fixing.

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    33/34

    1/8

    SUMMARY

    Item Description Qty Price Amount

    SUBSTRUCTURE 16643

    (SUPERSTRUCTURE)

    CONCRETE WORK 14979

    BLOCKWORK 11983

    ROOFING 14550

    CARPENTRY 1979

    JOINERY 3530

    ELECTRICAL INSTALLATION 4500

    24428

    GLAZING 14748

    PAINTING AND DECORATION 11155

    118495

    ADD

    Preliminaries includes;

    10% 11849

    ADD

    Supervision 15% 17774

    Labour 35% 41473

    ADD

    Contingencies 10% 11849

    TOTAL COST ###

    PLASTERWORK AND OTHER WALL AND CEILINGFINISHINGS IN-SITU FINISHINGS.

    Setting out and excavation of works, transportation,offloading & stacking of materials on site, water forworks,site clearance etc.)

  • 8/7/2019 COMPLETION OF THREE STORES AND GARAGE AT GBETSELE

    34/34

    ALL PRICES ARE FROM THE OPEN MARKET,TEMA