2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
![Page 3: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/3.jpg)
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•There are no approved Change Orders at this time
•Contingency Budget is 0% spent
•Contract allowance approved totals $0
•Project Team is following approximately $114,205 in pending issues
![Page 4: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/4.jpg)
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Colors have been selected materials
are being ordered and work will begin
starting Christmas Break.
Transportation Building
• Foundations around the perimeter of
the Addition have been installed and
back filled.
Middle School
• Turf Field construction is anticipated
to begin in January.
Senior High School
• A temporary road from the Tennis Court
to the H.S. Staging Area has been
installed.
• A temporary wall has been installed
along the Main Entrance.
• Trees near the Main Entrance building
pad have been removed along with the
sidewalk and masonry wall.
•Temporary walls have been installed for
the Art Room and demo has begun.
![Page 5: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/5.jpg)
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Work will begin starting Christmas
Break.
Transportation Building
• Footers and Foundations will be
completed by the end of December.
•Structural steel is scheduled to arrive
the first week of January.
Middle School
• Turf Field construction is anticipated
to begin in January.
Senior High School
• Foundation work for the Main Entrance
is scheduled to be completed by mid
January.
• Art Room demo and abatement will
begin Christmas Break.
![Page 6: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/6.jpg)
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
![Page 7: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/7.jpg)
Demo – High School Art Room
![Page 8: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/8.jpg)
Temporary Walls – High School Art Room
![Page 9: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/9.jpg)
Cutting Trees– High School Main Office
![Page 10: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/10.jpg)
Demo Concrete Sidewalk– High School Main
Office
![Page 11: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/11.jpg)
Demo Front Area– High School Main Office
![Page 12: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/12.jpg)
Demo Brick– High School Main Office
![Page 13: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/13.jpg)
Temp Walls at Lobby– High School Main
Office
![Page 14: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/14.jpg)
Demo and Fence – High School Tennis Courts
![Page 15: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/15.jpg)
Demo Hedge Row – Middle School Turf Field
![Page 16: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/16.jpg)
Fencing – Middle School Turf Field
![Page 17: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/17.jpg)
Digging Footers – Transportation Building
![Page 18: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/18.jpg)
Pouring Foundation Walls – Transportation
Building
![Page 19: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/19.jpg)
Strip Forms & Backfill – Transportation
Building
![Page 20: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation](https://reader033.vdocument.in/reader033/viewer/2022053008/5f0c43857e708231d43489a7/html5/thumbnails/20.jpg)
Stripping for Building Pad - Transportation
Building