honeoye falls-lima central school district€¦ · manor intermediate •colors have been selected...

21
Honeoye Falls - Lima Central School District 2016 Additions and Alterations Phase 2 Project Update November 2018

Upload: others

Post on 24-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Project Update

November 2018

Page 2: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

2016 Additions and Alterations Phase 2

Referendum Value $29,986,084

Incidental Budget $ 4,632,681

Construction Contingency $ 1,564,311

Contracts Awarded $22,848,873

State Contract $ 940,219

Page 3: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Construction Contingency Budget Update

•Construction Contingency Budget $1,564,311

•There are no approved Change Orders at this time

•Contingency Budget is 0% spent

•Contract allowance approved totals $0

•Project Team is following approximately $114,205 in pending issues

Page 4: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Manor Intermediate

• Colors have been selected materials

are being ordered and work will begin

starting Christmas Break.

Transportation Building

• Foundations around the perimeter of

the Addition have been installed and

back filled.

Middle School

• Turf Field construction is anticipated

to begin in January.

Senior High School

• A temporary road from the Tennis Court

to the H.S. Staging Area has been

installed.

• A temporary wall has been installed

along the Main Entrance.

• Trees near the Main Entrance building

pad have been removed along with the

sidewalk and masonry wall.

•Temporary walls have been installed for

the Art Room and demo has begun.

Page 5: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Manor Intermediate

• Work will begin starting Christmas

Break.

Transportation Building

• Footers and Foundations will be

completed by the end of December.

•Structural steel is scheduled to arrive

the first week of January.

Middle School

• Turf Field construction is anticipated

to begin in January.

Senior High School

• Foundation work for the Main Entrance

is scheduled to be completed by mid

January.

• Art Room demo and abatement will

begin Christmas Break.

Page 6: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Progress Photos

Page 7: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo – High School Art Room

Page 8: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Temporary Walls – High School Art Room

Page 9: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Cutting Trees– High School Main Office

Page 10: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo Concrete Sidewalk– High School Main

Office

Page 11: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo Front Area– High School Main Office

Page 12: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo Brick– High School Main Office

Page 13: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Temp Walls at Lobby– High School Main

Office

Page 14: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo and Fence – High School Tennis Courts

Page 15: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Demo Hedge Row – Middle School Turf Field

Page 16: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Fencing – Middle School Turf Field

Page 17: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Digging Footers – Transportation Building

Page 18: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Pouring Foundation Walls – Transportation

Building

Page 19: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Strip Forms & Backfill – Transportation

Building

Page 20: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Stripping for Building Pad - Transportation

Building

Page 21: Honeoye Falls-Lima Central School District€¦ · Manor Intermediate •Colors have been selected materials are being ordered and work will begin starting Christmas Break. Transportation

Honeoye Falls-Lima Central School

District

Questions?