Page 1: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Project Update

October 2019

Page 2: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2016 Additions and Alterations Phase 2

Referendum Value $29,986,084

Incidental Budget $ 4,632,681

Construction Contingency $ 1,564,311

Contracts Awarded $22,848,873

State Contract $ 940,219

Page 3: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Construction Contingency Budget Update

•Construction Contingency Budget $1,564,311

•Additional State Contract Purchases $ 176,223

•Approved Change Orders $ 432,812

•Remaining Construction Contingency $ 955,276

•Construction Project is 64% Complete

•Contingency Budget is 39% spent

•Contract allowance approved totals $0

•Project Team is following approximately $746,281 in pending issues

Page 4: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Manor Intermediate

• Construction in Rooms 110, 108,

106, 117, The Art Room and the

Discovery Lab continue.

• Wall tile and ceiling grid has been

installed in Toilet Rooms 202 and 206.

• Casework is being installed in the Art

Room and Discovery Lab.

Transportation Building

• The Addition has been turned over to

the District and is being moved into.

• Once the move is complete

construction will begin in the existing

bays.

Senior High School

• Construction continues in the Flex Space and

Conference Room on the 2nd Floor.

• Construction is ongoing in the New Art Room,

Flexible Learning Lab and saw cutting has

begun in the New Cafeteria.

• Ceiling Tile has been installed in the New

Lobby and demo has begun in the Girls Pool

Locker Room.

Page 5: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Lima Intermediate

• Block work for the elevator shaft and

the dividing wall between rooms 210

and 206 is nearly complete.

• Roofing work is complete

Middle School

• The Turf Field is substantially complete and a

punchlist is being created.

• The Projection Screen has been installed,

wired and the work for the proscenium is being

scheduled.

Page 6: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Manor Intermediate

• Construction is nearly complete in

the Art Room, Toilet rooms outside the

Art Room and the Discovery Lab.

• Rooms 110, 108 and 106 will

continue with the completion of

drywall; electrical is being roughed in

along with plumbing and the VRV

System is being piped.

• Construction in room 302 will be

nearly complete with the installation of

casework and flooring.

Senior High School

• Ceilings and lights in room 211 and the

corridor on the 2nd floor will be installed.

• Electrical work is being roughed in the

Art Room and will be followed by floor

mitigation, casework and flooring.

• Saw-cutting and under slab plumbing

and electrical work will be installed in the

Kitchen; framing drywall and electrical

rough-in will continue.

• Sidewalk in the Courtyard will be

installed.

Page 7: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Middle School

• The projection screen proscenium is

scheduled to be installed over

Christmas Break.

• DiFiore will punchout the Turf Field

and begin removing temporary fencing

and equipment.

Lima Elementary

• Masonry work for the elevator shaft will

continue along with work in room 210,

206 and 116.

• Ductwork will begin being installed in

rooms 210 and 206.

• The installation of the elevator is

scheduled to begin in November.

Page 8: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Progress Photos

Page 9: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Main Entrance - High School

Page 10: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Main Entrance – High School

Page 11: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Main Entrance Vestibule – High School

Page 12: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

High School Lobby

Page 13: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Girls Pool Locker Room – High School

Page 14: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

2nd Floor Addition (201A) – High School

Page 15: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Courtyard – High School

Page 16: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Art Room – High School

Page 17: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Art Room – High School

Page 18: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Turf Field – Middle School

Page 19: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Repair Bays – Transportation Building

Page 20: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Parking Lot Addition - Transportation Center

Page 21: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Repair Bays – Transportation Building

Page 22: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Art Room – Manor

Page 23: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Art Room – Manor

Page 24: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Faculty Lounge – Manor

Page 25: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Screening Topsoil – Middle SchoolSensory Room – Manor

Page 26: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Work Room – Manor

Page 27: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Discovery Room – Manor

Page 28: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Projection Screen – Middle School Auditorium

Page 29: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Room 210 – Lima

Page 30: Honeoye Falls-Lima Central School District · Senior High School •Construction continues in the Flex Space and Conference Room on the 2nd Floor. •Construction is ongoing in the

Honeoye Falls-Lima Central School

District

Questions?