Introduction to Wireless
Product Acceptance
Optimization Solution
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 2/41
Contents
• Overview
• Solution Introduction
•
FAQs• Negotiation Cases
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 3/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 3
Difficulties in Project Acceptance (Test)
The Ac ceptance Manual is a collection of test cases. For specific projects, however,
many cases may be redundant. On-site
engineers may not know how to identify and
delete redundant cases or choose test cases.
Therefore, risks of uncertainty exist.
Acceptance supporting documents (such as
factory inspection reports and R&D internal test
reports or documents) are missing or hard toobtain.
Existing test case selection tools cannot select
suitable cases correctly like on-site
engineers.
Acceptance contract clauses are unclear.
Disputes with customers in later delivery phase
puts us in an unfavorable position.
Acceptance standards are determined throughnegotiations with customers. However, we lack
negotiation strategies or proper measures
when customers raise unreasonable
requirements.
1 Materials: Hard to select proper test
cases among massive test cases
2 Documents: Lack supporting
documents or hard to obtain
3 Tools: Inapplicable to guide on-site
engineers to select proper test items
Five shortcomings in ability development
4 Clauses: Unclear clauses causing
disputes with customers
5 Strategies: No guidance strategy for
negotiations
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 4/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 4
How Does This Solution Help
Focusing on product acceptance (provisional acceptance), this solution solves
problems related to materials, supporting documents, tools, clauses, and
negotiation guidance strategies, minimizes the on-site acceptance, shortens the
acceptance period, and fastens payment collection.
Materials:
Optimize acceptance information
and further classify test packages
in acceptance scenarios
Strategies:
Define acceptance negotiation
guidance strategies to support
on-site negotiations
Documents:
Prepare supporting documents and
ensure that the documents can beobtained by on-site engineers
Clauses:
Draft acceptance clauses
to restrict customer test
requirements
Tools:
Develop auxiliary tools, associate
feature sales and acceptance, and
enhance test case risk management
Minimize the acceptance, shorten the acceptance period, and fasten payment
collection
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 5/41
Contents
• Overview
• Solution Introduction
•
FAQs• Negotiation Cases
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 6/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 6
Solution Introduction
Test Packages
Acceptance Supporting Documents
Test Case Selection Tools
Clauses Negotiation Guidance Strategies
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 7/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 7
Classifying the Test Cases in the Acceptance Manual
into Test Packages
Divide the original
Acceptance Manual into
four test packages and one
strategy package according
to test case attributes and
test procedures.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 8/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 8
Structure of a Test Package
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 9/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 9
Associating Test Packages with Acceptance Process
Accepta
nce
Activity
• Factory
inspection report
(optional)
• Industry
certification
report (optional)Packing list
• List of materials
……
• Product
function/feature test
• Network
deployment service
acceptance
• Single-site
verification
•
Equipmentinstallation report
• Self-check report
……
• Network KPI
test
• System KPI
test ……
• Outstanding
problem
settlement
• Trial run
Test
package
<Specialized
certification
package>
<Feature verification
package>
<Site acceptance
package>
<KPI test
package> -
<Strategy package>
SupplyAcceptance
Provisional Acceptance Network
Optimization
Acceptance
FinalAccepta
nceDemonstration
AcceptanceSites Acceptance
Acceptance
Process
The provisional acceptance is classified into demonstration acceptance and sites acceptance.
The demonstration acceptance is used to test functions and features of products. The sites acceptance is used to test
engineering service quality and basic services.
Demonstration acceptance and sites acceptance can be performed in any order or at the same time.
Note: Engineers are not prompted to perform demonstration acceptance unless customers require
testing product functions at the acceptance stage.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 10/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 10
Associating Test Packages with Acceptance Process-
Demonstration Acceptance Demonstration acceptance is a new concept aiming to complete product
function/feature tests within a small range and avoid large-scale tests siteby site. The small range can be test beds, trial sites, and validation
networks.
Test Bed
NodeBRNC
BTSBSC
Laboratory
RNCNodeB
Overall Network
Trial Sites Within an Overall Network
Trial Sites
Type A
Type BType C
RNCNodeB
RNC
NodeB
Overall Network Validation Network
Validation Network
• The test bed is a laboratory simulated
network. The hardware and software
configurations of this network are the same
as those on the actual network and can
represent the functions of the actual
network.
•Trial sites refer to
certain sites to be
constructed on the
network. The
hardware andsoftware
configurations of these
sites are the same as
those on the actual
network and can
represent the
functions of the actual
network.•The validationnetwork refers to a
subnet of the networkto be constructed. Thehardware andsoftwareconfigurations of thissubnet are the sameas those on the actualnetwork and canrepresent thefunctions of the actualnetwork.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 11/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 11
Test Package Delivery Owner and Precautions
Test PackageDelivery
Owner Precaution
Specialized
certification package
Supply
chain/R&D
1. Optional. If customers have test requirements, provide the factory inspection
report first.
2. If customers require tests, guide customers to allow tests at Huawei
headquarters. In this case, quotation is required.
Feature verification
package
GTS/R&D
1. Optional. If customers have the requirement, provide internal test reports in
priority to avoid repeated tests.2. If tests must be performed on site, control the tests within a small range, for
example, in test beds, trial sites, and validation networks, to avoid large-scale tests
site by site.
3. Some test cases may fail to be verified due to immature industry chain,incomplete product implementation, unobservable effect, or theoretical ultimate
capacity. For such test cases, only a commitment to provide clarification
documents (emulation and theory analysis) can be made.
Site acceptance
packageGTS
1. Guide customers to perform tests based on a certain percentage, for example,
10%.
2. If tests involve expensive devices, quotation is required or customers provide the
devices.
KPI test package GTS This solution focuses on device acceptance (provisional acceptance) withoutinvolving network acceptance. Only KPI test cases are provided.
Strategy package -
Customers may have test requirements beyond the acceptance range, for
example, IOTs, RF tests, new solution/feature tests, and network acceptance. A
strategy package contains relevant guidance strategies to avoid impacts of the
preceding tests on the acceptance.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 12/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 12
Solution Introduction
Test Packages
Acceptance Supporting Documents
Test Case Selection Tools
Clauses Negotiation Guidance Strategies
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 13/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 13
Acceptance Supporting Documents
•The acceptance supporting documents include two test packages and four types of reports.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 14/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 14
End-to-End Feature Test Report
End-to-end process of a feature
Feature
• R&D engineers shall
provide test reports on theoptional and special (test
cases of features hard to
be executed) features in
the feature verification
package in priority. The test
reports of all features will
be finally available when
the features are released.
• These reports can be
shown to customers during
negotiations, reflecting the
strict product quality test
procedures of Huawei and
persuading customers toavoid repeated tests during
product acceptance.
Step 1: R&D
engineers design test
cases based on
features and provide
internal test reports or
documents.
Step 3: On-site engineers
negotiate with customers to
avoid tests based on the
internal test reports and
documents provided by R&D
engineers.
Step 2:
Marketingpersonnel
sell features.
ReleaseSales
Service
delivery
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 15/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 15
How to Obtain Acceptance Supporting Documents
Factory inspection report
Wireless product contact person: Zeng Jun (ID: 00106221), Wireless Test & ATE Product Dept
Download address: http://10.72.128.225/texpert/Default.aspx Industry certification report
See the External Document Archiving Database Query Guide V2.0.ppt .
Download address:
http://support.huawei.com/support/pages/kbcenter/view/product.do?actionFlag=detailProductSimple&we
b_doc_id=SC0000526336&doc_type=123-2
Version test report and feature test report
These reports are released together with test cases (test packages). Download address:1. Chinese edition (including strategy guidance):
http://support.huawei.com/support/pages/kbcenter/view/product.do?actionFlag=detailProductSimple&we
b_doc_id=SC0000526336&doc_type=123-2
2. English edition:
http://support.huawei.com/support/pages/kbcenter/view/product.do?actionFlag=detailProductSimple&we
b_doc_id=SE0000414297&doc_type=123-2
Note: Industry certificates are applicable to all kinds of products. Different release test reports
and feature test reports are available for different kinds of products. Only the download address
of the UMTS test package is given. See Appendix for download addresses of test reports of
other products.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 16/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 16
Solution Introduction
Test Packages
Acceptance Supporting Documents
Test Case Selection Tools
Clauses Negotiation Guidance Strategies
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 17/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 17
Key Improvements to Test Case Selection Tools
1. Risk management of feature
test cases
Feature test cases are packaged
according to the difficulty of test
execution, and test risk degrees
are marked by "basic", "optional",
and "special".
2. Associate front end (sales)and back end (acceptance
and delivery) and provide
automatic links to test cases
from Feature ID or Model in
BOQ.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 18/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 18
Case Management in Excel Format—Easy to View Test
Case Details
View the details of a test case by
clicking Test Name
• Able to know details of a test caseat any time
• Easy to execute tests and select
test cases
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 19/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 19
Case Management in Excel Format—Select Test Cases to
Generate Word Files
Use macro to generate a test case and a signature form in Word format
1. A test cases is selected except that the Select flag is null or set to No or Cancel.
2. The editing operations are similar to those of an ordinary Excel sheet, for example,
copy, paste, add, and delete. Run macro to generate a test case description file
and a signature form in Word format.
S i gn a t ur e
F or m
A
c c e p t an c e
M
an u al
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 20/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 20
Case Management in Excel Format—Execution Result
Identifier and Statistics
Automatically generate test case
execution results
• Test case execution results are
marked in different colors.• Execution result statistics are
performed automatically on a
daily or weekly basis.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 21/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 21
Case Management in Excel Format—Test Case Selection Tools
Select test cases automatically:
1. In the Selecting Test Case dialog box, determine the baseline document (Excel format) and test case package asprompted.
2. Set conditions. As shown in the figure above, select the test cases whose Model in BOQ is included in the model list and
Priority is High. After the test cases meeting preset conditions are selected, marks are automatically filled in Selection
Mark of the selected test cases. You can start a new search and combine the search results or start another search in the
search results.
3. The selected test cases can be used to generate test case description files and signature forms in Word format.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 22/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 22
Solution Introduction
Test Packages
Acceptance Supporting Documents
Test Case Selection Tools
Clauses Negotiation Guidance Strategies
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 23/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 23
Technical Clauses Regarding Acceptance
No on-site acceptance is required for items that are clearly specified in standards
or protocols. (For example, for sensibility and standard signaling, third-partycertification reports and compatibility analysis reports can be provided to replace
tests.)
Tests that require special test instruments (such as power meters, special
spectrum testers, and voice/image/stream quality evaluation tools) are not
performed on site. No acceptance is required for ultimate functions (for example,
xx subscribers in a single cell). (Internal test reports can be provided for
clarification, or witness tests can be performed with R&D engineers for important
items).
No commitments shall be made to verify all sold features on site. (Some customers
even request us to test the features of other vendors. Internal test results and
clarification documents can be provided to replace the feature verification.)
No commitments shall be made to test items that require third-party cooperation
(for example, terminal interworking and service platform compatibility; MVI test
services can be provided to meet carrier requirements). Standard test cases can
be provided. Test services can be sold separately to meet extra test requirements
of customers.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 24/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 24
Acceptance Responsibility Division Clauses
Clearly specify that the carrier is the responsible person for
equipment interconnection and the equipment supplier is
responsible for solving equipment problems. (In principle, no IOT is
performed during acceptance.)
Clearly specify that the carrier should prepare all third-party toolsand devices required for tests (mainly trace tools). (In principle, no
other test tools are recommended. Guide customers to prepare the
tools.)
The acceptance certificate is still acquirable if the acceptance isblocked or delayed by non-supplier reasons.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 25/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 25
Notes:
Application scenarios of clauses: At the bidding stage, if acceptance standards are not clearly determined with customers,
clauses restricting the scope of tests shall be added in contracts to prevent some risks
and avoid being passive when confirming acceptance standards with customers later.
How to use the clauses: The technical clauses that are important and widely applicable should be included in main
contracts, usually in Condition part.
The technical clauses that are important and specific should be included as an
acceptance attachment of contracts, also in Condition part.
Responsibility division clauses are included as an acceptance attachment in Roles and
Responsibilities part of contracts.;
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 26/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 26
Solution Introduction
Test Packages
Acceptance Supporting Documents
Test Case Selection Tools
Clauses
Negotiation Guidance Strategies
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 27/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 27
General Negotiation Principles
Use the fewest test packages to meet customer requirements.
1
Make clear that the acceptance aims to prove the normal service provisioning of equipment,
instead of verifying features.
2
Make clear the delivery modes of acceptance: certificates, test reports, clarification
documents, tests at Huawei HQ, and on-site tests.
3
Huawei shall provide paid test services which are claimed to be independent of acceptance
and undertaken as a separate project operation.
4
All test packages are concepts used internally and should be known as "acceptance
test packages" for customers.
5
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 28/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 28
Negotiation Scenario 1: All Feature Tests
Requirement Description Risk Analysis Recommended Guidance Strategy
Carriers require verifying
all features before the
equipment is put into
commercial use, which is
the most common
requirement.
Some carriers even
require verifying all
features at each site.
1. Features are
classified into very
small categories and
the on-site test
workload is too heavy.
2. Features of Huawei
are not clearly
classified, and some
features are hard or
even impossible to be
tested on site.
Strategy 1:
Using documents to
replace tests
1. Guide relevant engineers to provide release test
reports. The test reports should contain statistics data
that proves the verifications performed internally.
2. Guide relevant engineers to provide feature
verification reports, including test cases (logs should be
available in reports for tracking).
3. Test contents are within the range of baselines.
Clarification documents are provided if on-site
verification conditions are not met.
Strategy 2:
Performing tests within
a smaller range
On-site tests are allowed. The demonstrationacceptance mode is recommended, and the test
environment can be test beds, trial sites, or validation
network. No repeated tests at each site are permitted.
Strategy 3:
Performing acceptance
based on a certain
percentage (Note)
The acceptance at actual sites is allowed only in
sampling test manner, for example, based on a
percentage of 5% to 10%.
Note:
1. In principle, not all features need to be tested. Only the features that are purchased by customers
and to be put into commercial use need to be tested.2. Feature tests should not be performed at
actual sites. Strategy 3 is a compromise made with customers only when no other approach is
available.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 29/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 29
Negotiation Scenario 2: IOTs
Requirement
DescriptionRisk Analysis Recommended Guidance Strategy
Generally, carriers require
that suppliers provide the
equipment supporting
interconnection with the
existing network equipment
and the previous
interconnection reports.
Some carriers even fail to
obtain support from original
suppliers.
The protocol compliance of
inter-equipment
interconnection cannot be
settled through only efforts
of Huawei.
With NDAs signed, IOT and
MVI reports shall not be
provided for a third party
without permission.
Due to competition
purposes, interconnection
equipment suppliers may
provide no cooperation or
even block the acceptance.
Strategy 1:
Using reports to
replace tests
If Huawei equipment is interacted with the
equipment of important carriers or mainstreamsuppliers, make NVIOT clarification with carriers
and guide carriers to raise the IOT report
requirement.
For interconnection requirements in other scenarios,
refer to MVI reports (without NDA) and commercial
application cases.
Strategy 2:
Restricting the testrange and specifying
responsibilities
Equipment interconnection must be completed for
network commissioning, but not all IOTs need to be
performed. Interconnection is required to meet onlycommercial application requirements through close
cooperation among three parties. The PAC is still
acquirable if the interconnection is delayed by non-
Huawei reasons.
Strategy 3:
Providing IOTs as a
test service
independent of
acceptance
If carriers require all IOTs, promote the selling of
MVI test services and obtain cooperation from
interconnected equipment suppliers.
Note:
The test service is a professional service that is operated independent of project acceptance and
used to meet various test requirements of customers. In terms of acceptance negotiation strategies,
the test service is a way to meet requirements and reach a balance with customers by means of
quotation.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 30/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 30
Negotiation Scenario 3: Capacity Specification Tests
Requirement
DescriptionRisk Analysis Recommended Guidance Strategy
Some carriers pay a great
concern to equipment
capacity and require
relevant tests.
Some carriers even requireverifying the ultimate
specifications in real
scenarios.
Capacity specifications are
usually the equipment
processing capabilities
obtained under theoretical
baseline conditions, which
are hard to be tested on site.
At present, the equipment
capacity is very large.
Ordinary test tools cannot be
used to obtain thespecifications of the main
equipment, special test tools
cannot be used for on-site
tests due to restrictions of
shipment, customs
clearance, costs, and
personnel skills.
Strategy 1:
Obtaining test-free
permission
Provide sufficient evidences showing the difficulty in
ultimate capacity specification tests and guide
customers to cancel such test requirements.
Strategy 2:
Using reports to
replace tests
Promise to provide internal test reports to reduce
on-site test workload.
Strategy 3:
Returning to Huawei
HQ for test
Guide carriers to perform witness tests with R&D
engineers at Huawei HQ.
Note:1. The changes of capacity specification tests are complex. No commitments shall be made to meet
special traffic model and networking requirements unless carriers perform the tests.
2. Any commitment related to tests involved in strategy 2 and strategy 3 shall not be made before
being confirmed and agreed by R&D personnel. Tests involved in strategy 3 shall be quoted.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 31/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 31
Negotiation Scenario 4: RF Index Tests
RequirementDescription Risk Analysis Recommended Guidance Strategy
Some carriers require
performing RF index tests
on site, even including
electrical performance and
environment requirements.
Some tests are required to
comply with local standards.
Index tests require complex
test tools and high costs and
are hard to be performed on
site.
Test personnel are not
familiar with local standards,standards are inconsistent,
and certification costs are
high.
Strategy 1:
Providing international
organization
certification reports
Standard tests should comply with third-party
organization certification reports, and no on-site
tests are performed. Guide customers to provide
certificates or reports.
Replace local standards with corresponding
international standards.
Strategy 2:Providing factory
inspection reports
For test items that vary with modules, such asRF indexes, factory inspection reports can be
provided as the index satisfaction evidence.
Strategy 3:
Returning to Huawei
HQ for test
Guide carriers to perform witness tests with R&D
engineers at Huawei HQ.
Note:
1. For on-site tests, clearly specify that carriers are responsible for preparing test tools and
performing tests on only one or two modules.
2. Confirm strategy 2 with the production contact person; confirm strategy 3 with the R&D
contact person at Huawei HQ.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 32/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 32
Negotiation Scenario 5: Deep Test Requirements
Requirement
DescriptionRisk Analysis Recommended Guidance Strategy
During the acceptance
workshop, carriers perform
finitist and theoretical
analyses, increasing test
requirements abruptly.
Some carriers also have
networking, configuration,
and commercial strategies,
and even require FOA
tests.
The purpose of these tests
are to find commercial
application schemes, which
is already beyond the
acceptance scope.
The scope of FOA must be
strictly controlled;
otherwise, it may be mixed
with pre-commercial
application and the
commercial application may
be conducted before PAC is
obtained, making us
passive.
Strategy 1:
Performing
technical
clarification
Tests are not necessary so long as commercial
application schemes pass the technical clarification
during workshop.
Strategy 2:Conducting training
If test items are added for personnel training, the tests
can be differentiated from acceptance according totraining operations.
Strategy 3:
Providing "test
services"
If on-site tests are required, a balance can be reached
by selling "test services".
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 33/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 33
Overall Strategy Model
Strategy package(IOT and ultimate equipment capability tests)
Specialized certification
package(professional certification reports/tests)
Feature verification
package(wide product feature tests)
Site acceptance
package(service acceptance)
Networkacceptance
The overall strategy model
is a procedure of filtering
customer requirements,
with increasingly higher test
difficulties and risks from
bottom to top. Tests at
upper layers require morestrict control. The overall
strategy model aims to
finally simplify the site
acceptance through the
filtering at the three lower
layers.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 34/41
Contents
• Overview
• Solution Introduction
•
FAQs • Negotiation Cases
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 35/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 35
Q1: Application Stage and Personnel of the Solution
Stage Role Activity
Contract
bidding stage
Engineering bidding
project manager
1. Includes the acceptance standards and test cases completed by the technical
owner based on this solution in the contract.
2. Negotiates on the acceptance standards with customers under assistance of the
technical owner.
3. Tries to include the suggested clauses of the solution (clauses can be selected
according to project situations) in the contract if acceptance standards cannot be
clearly determined with customers at this stage.
Technical owner
1. Specifies strategies according to acceptance items in the solution, and uses test
case selection tools to customize test cases for acceptance as an attachment of the
contract according to the product function range specified in the contract.
2. Helps the engineering bidding project manager to negotiate with customers on test
standards and includes the test cases as an attachment of the contract.
Contractdelivery stage
Engineering delivery
project manager
1. If acceptance standards are not clearly specified in the contract, determines the
acceptance standards with customers at the delivery preparation stage according to
this solution.
2. Determines acceptance standards with customers under assistance of the
technical owner.
Technical owner
1. If acceptance standards are not clearly specified in the contract, specifies relevant
strategies according to the acceptance standards in this solution, and customizes test
cases for acceptance as an attachment of the contract according to the product
function range specified in the contract.
2. Helps the engineering project manager to negotiate with customers.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 36/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 36
Q2: How Is This Solution Included in the Contract at
the Pre-Sales Stage?
Responsibility
division interface
Project management
proposal
Engineering bidding documentAcceptance flow
Acceptance milestone
Acceptanceproposal
Construction
period schedule
… …
Engineering service and project
management proposalsAcceptance scope
Acceptance clauses
Acceptance certificate
Acceptance standard/test
case
……
After bidding document negotiation, the acceptance standards or test
cases agreed by both Huawei and the customer are included in the
contract as a part of the acceptance solution.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 37/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 37
Q3: How to Use this Solution at the After-Sales Stage?
If test cases are not specified or not clearly specified in the contract,
test standards must be determined with the customer and both
parties must sign for confirmation at the delivery preparation stage
before the acceptance is started.
No acceptance should be performed before acceptance standards
are clearly determined.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 38/41
Contents
• Overview
• Solution Introduction
• FAQs
• Negotiation Cases
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 39/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 39
Case 1:
Acceptance steps determined by the
customer of project R in country I:
1. LAB Acceptance
2. FOA Acceptance
3. Installations, Integration and Site
Acceptance
4. RF Cluster Acceptance
5. Market Acceptance
6. SDCA Level Acceptance
The success of the tests in a
previous step is the precondition for
the tests in the next step.
1667 basic test itemsfor LAB/FOA
Results after communication with the customer:
• Nearly half of the test items are delivered in other modes, greatly reducing the on-site test workload
and risks.
7/29/2019 Introduction to Wireless Product Acceptance Optimization Solution-V0.3-20091111.ppt
http://slidepdf.com/reader/full/introduction-to-wireless-product-acceptance-optimization-solution-v03-20091111ppt 40/41
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 40
Case 2
Test Items Required by the Customer of Project V in Country V: The customer requires testing all features including the OSS and RAN and completing the acceptance
within 30 days after installation.
Risk Analysis The workload to test all features is heavy, and some test conditions are not met on site.
The time schedule is tight, and failure to complete the tasks on time may incur penalty.
Results after Communication with the Customer: Perform feature tests in batches and test the features to be put into commercial use on the existing
network before the PAC is obtained.
Test other features in three months after the PAC is obtained. If test conditions are not met on site,
Huawei can provide internal test reports.
Launch acceptance PAC
Three months
RAN: 160 features
OSS: 133 features
RAN: Internal test reports
can be provided for 154
features