Xavier PallàsBimetric
itec.cat/lean
WHAT IS LPS ?The Last Planner System manages the relationships, conversations and commitments that together enable program and production planning decisions to be made collaboratively at the lowest possible level. (Mossman 2014)
LAST PLANNER® SYSTEM (LPS)
THE LPS PACKAGE
• Pull session
• Six Week Look Ahead Plan (6WLAP)• Weekly Work Plan (WWP)• KPI’s. Percent Plan Complete (PPC) and Variance Chart• Constraint Log• Stand-up meetings• Pull Schedule Review Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
LPS PROCESS
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
1st PLANNER SCHEDULE
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
1. PULL SESSION
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Six Week Lookahead Plan (6WLAP)
Prepare the plan6 weeks
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Six Week Lookahead Plan (6WLAP)
Prepare the plan
• The team must assure stable workflow for the tasks planned
Detail tasks for better definition as needed (sub tasks and location sequence)Sequence and durations adjustments as neededIdentify resources needed for every taskIdentify constraints
• Publish the plan and share with the team (weekly)
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Six Week Lookahead Plan (6WLAP)
Manage constraints
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Weekly Work Plan (WWP)
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Weekly Work Plan (WWP)
Statistics
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Weekly Work Plan (WWP)
Statistics
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
Weekly process
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
LPS en una empresa constructora
• Alineación y empoderamiento de la cadena de producción
• Un proceso claro y disciplina en su aplicación
• Información clara y disponible del proceso de obra
• Fácil monitorización desde gerencia
• Evaluación de proveedores
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean
LPS en una empresa constructora
• Formación interna y externa
• Resistencia al cambio. perseverancia, colaboración, compromiso, transparencia
• Implicación de la DF y la propiedad
Lean LPS · 05/2016 · Lean Construction Barcelona by ITeC · itec.cat/lean