ID Task Name Duration Start Finish
1 PHASE I 11 days Fri 09/01/15 Fri 23/01/15
2 Project allocation 1 day Fri 09/01/15 Fri 09/01/15
3 Literature survey 6 days Mon 12/01/15Mon 19/01/15
4 Finalisation of objective and methodology 1 day Tue 20/01/15 Tue 20/01/15
5 Biodiesel feedstock selection 3 days Wed 21/01/15Fri 23/01/15
6 PHASE II 22 days Mon 26/01/15Tue 24/02/15
7 Collection of feedstock 2 days Mon 26/01/15Tue 27/01/15
8 Mechanical extraction of oil 1 day Wed 28/01/15Wed 28/01/15
9 Study the fatty acid composition of oil 6 days Thu 29/01/15 Thu 05/02/15
10 Process optimisation 6 days Fri 06/02/15 Fri 13/02/15
11 Optimization of Reaction time ,temperature 6 days Mon 16/02/15Mon 23/02/15
12 Optimization of catalyst type and conce: 1 day Tue 24/02/15 Tue 24/02/15
13 PHASE III 21 days Wed 25/02/15Wed 25/03/15
14 Biodiesel production 15 days Wed 25/02/15Tue 17/03/15
15 Determining the Properties of biodiesel 6 days Wed 18/03/15Wed 25/03/15
16 PHASE IV 21 days Thu 26/03/15 Thu 23/04/15
17 Engine performace and emission test 5 days Thu 26/03/15 Wed 01/04/15
18 Injection pressure optimization 6 days Thu 02/04/15 Thu 09/04/15
19 Corelation of Nox formation 10 days Fri 10/04/15 Thu 23/04/15
20 PHASE V 36 days Fri 24/04/15 Fri 12/06/15
21 Prepration and Submission of Draft Report to Guide 12 days Fri 24/04/15 Mon 11/05/15
22 Submission of Report to ARAI 1 day Mon 25/05/15Mon 25/05/15
23 Final presentation at ARAI 8 days Wed 03/06/15Fri 12/06/15
M F T S W S T M F T S W S T M F T
22 Dec '14 19 Jan '15 16 Feb '15 16 Mar '15 13 Apr '15 11 May '15 08 Jun '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: Projectplan
Date: Tue 10/02/15