Page 1: Operating Performance Update

INTERNAL

Operating Performance Update

S&C Draft of 5/26/10

Page 2: Operating Performance Update

2INTERNAL

Production Milestones• June 26, 2012

First Nickel test briquettes were sintered.

• August 18, 2012 Single largest batch of slurry sent from the Mine (18,980 t), ex-

ceeding the Financial Completion target of 674 t/h.

• September 9, 2012 First Cobalt test briquettes were sintered.

• September 13, 2012 Operating permit granted.

• November 1, 2012 5 Autoclaves on line with dual slurry feed pumps

• November 8, 2012 First international shipment of refined nickel (40 t)

• November 13, 2012 First international shipment of refined cobalt (168 t)

2

Page 3: Operating Performance Update

3INTERNAL

Production Achievements to November 30, 2012

3

• Mixed Sulphides to Refinery:

Ni+Co contained, t 6,900

• Nickel Reduced, t

5,512

• Cobalt Reduced, t

488

• Amsul Produced, t

10,695

Note: The Project achieved “Commencement of Commercial Production” as described in the Finance Documents on November 26, 2012.

Page 4: Operating Performance Update

INTERNAL

PAL Overview

• Autoclaves PAL Autoclave Operating Hours

• Operated approximately 1,788 hours in November

Ore Throughput in the PAL Autoclaves• Processed 191,085 tonnes in November

• PAL Mixed Sulphide Production Produced approximately 1,763 tonnes of mixed sul-

phides (ni+co contained) in November

4

Page 5: Operating Performance Update

5INTERNAL

Refinery Overview

5

• Sulphide Leaching In November we processed 1,694 tonnes of nickel and

cobalt contained in mixed sulphides

• Nickel Reduction In November we reduced 1,592 tonnes of nickel pow-

der

• Cobalt Reduction In November we reduced 164 tonnes of cobalt pow-

der

• Metals Handling Produced 1,199 tonnes of nickel briquettes in No-

vember Produced 100 tonnes of cobalt briquettes in Novem-

ber

Page 6: Operating Performance Update

6INTERNAL

Operating Performance – PAL Ramp-Up Curve

6

Page 7: Operating Performance Update

7INTERNAL

Operating Performance – Refinery Ramp-Up Curve

7

Page 8: Operating Performance Update

8INTERNAL

Operating Performance – Ore Throughput

8

Page 9: Operating Performance Update

9INTERNAL

Operating Performance – Nickel Produced

9

Page 10: Operating Performance Update

10INTERNAL

Nickel Quality Analysis

10

• Nickel meets LME spec for all elements except silicon.

• Silicon contamination has occurred from late October and into November as Si level in Refinery solution has increased.

• Refinery is currently progressing initiatives to purge silicon from the circuit.

Page 11: Operating Performance Update

INTERNAL

Questions?

S&C Draft of 5/26/10