Page 1: PHENIX Central Region

Robert PakDOE Review

Jan. 19, 2005

dxVTX

Page 2: PHENIX Central Region

Robert Pak 2DOE Review

Jan. 19, 2005

VTX

HBD

PHENIX Central Region

From VTX Proposal (dims

in mm)

IntegrateDetector

Upgrades

Page 3: PHENIX Central Region

Robert Pak 3DOE Review

Jan. 19, 2005

HYTEC Structural Results

• GFRP sandwich composite M55J for the base structure• substantial gain in the stiffness to

weight ratio• similar rad length and strength• most widely used standard

• Outer frame structure should be single diameter

• Structural end disks to prevent deformation of the structure under dynamic load inputs

Page 4: PHENIX Central Region

Robert Pak 4DOE Review

Jan. 19, 2005

HYTEC Cooling Results• Use ladder, or stave, concept supported at its ends by composite rings

• Stave structure comprises a C-C thermal plane • OMEGA shaped composite bonded to back of thermal plane adds stiffness • Cooling tube bonded to the back of the C-C thermal plane with C-C tube support

• Use Al cooling tubes 3mm in diameter supplied with a 23 g/s single-phase perfluorocarbon fluid, C5F12

Page 5: PHENIX Central Region

Robert Pak 5DOE Review

Jan. 19, 2005

VTX Spec Sheet

Barrel Section radius length strips/pixel heat(W/cm 2̂) area(cm 2̂) power(W) voltage current(amps)layer 1 2.5 cm 21.8 cm pixel 0.7 W 279 195 1.8V 108layer 2 5 cm 21.8 cm pixel 0.7 W 557 390 1.8V 217layer 3 10 cm 31.8 cm strip 0.35W 1963 687 2.5V 275layer 4 14 cm 38.2 cm strip 0.35W 3403 1191 2.5V 476

total 6202 2463 1076Endcap (north and south) z-start(+-) radius tilt = 22 deg

disk 1 20 cm 6.6 cm pixel 0.1 W 678 21.6 1.8V 12disk 2 26 cm 10.6 cm pixel 0.1 W 1374 34.6 1.8V 19.2disk 3 32 cm 18 cm pixel 0.1 W 2255 47.5 1.8V 26.4disk 4 38 cm 18 cm pixel 0.1 W 2255 47.5 1.8V 26.4

total 6562 151.2 84

Already consider barrel and endcaps• aid to visualizing integration• streamline engineering

For next round with HYTEC

Page 6: PHENIX Central Region

Robert Pak 6DOE Review

Jan. 19, 2005

Mechanical Engineering for VTX

• Core design group assembled• PHENIX BNL Engineer D. Lynch:

• Work on PHENIX central region, which includes VTX• Engineering specific to VTX being done at LANL by

W. Sondheim & J. Boissevain• In consultation with PHENIX BNL engineer (off project)• Point of contact with HYTEC

• D. Lee & R. Pak to provide oversight

Page 7: PHENIX Central Region

Robert Pak 7DOE Review

Jan. 19, 2005

Pretty Picture

From J. Boissevain

Page 8: PHENIX Central Region

Robert Pak 8DOE Review

Jan. 19, 2005

w/ the Endcaps

Page 9: PHENIX Central Region

Robert Pak 9DOE Review

Jan. 19, 2005

Be Beam Pipe• Desirable to get as close as possible to collision vertex

w/o adding considerable radiation length• In discussion w/:

• PHENIX BNL Engineer (P. Kroon)• 0.3 +/- 0.1cm clearance between beam pipe and 1st Si layer to get

VTX concentric with the beam

• CAD Head of Vacuum Group (D. Hseuh)• 3cm diameter probably OK• Require NEG coating

• AP Upgrades Coordinator (W. Fischer)• Physical aperture of at least 5 transverse rms beam sizes (allowing

for 5mm orbit error) is OK

Page 10: PHENIX Central Region

Robert Pak 10DOE Review

Jan. 19, 2005

Be Beam Pipe Quote

Off project

Page 11: PHENIX Central Region

Robert Pak 11DOE Review

Jan. 19, 2005

Mylar Sleeve

• Proper grounding & isolation of Si detector• Image charge from circulating beam• Aluminized Mylar sleeve around Be beam pipe

• Few m’s thick to hold down material budget• Grounded w/ braid through magnet• No interference with other sub-systems; nothing else

between beam pipe and 1st pixel layer

Page 12: PHENIX Central Region

Robert Pak 12DOE Review

Jan. 19, 2005

VTX Mechanical Support Structure

• Frame for barrel & endcaps (HYTEC and LANL)• External support structure in central magnet (BNL)• Mechanical tolerances/distortions:

• < 25 m internally• 100 m relative to the rest of the detector

• From CAD Survey Group (F. Karl):• 50 – 100 m on the bench• 100 – 200 m in the hall

Page 13: PHENIX Central Region

Robert Pak 13DOE Review

Jan. 19, 2005

VTX Mech Support Structure (cont)

• Clamshell Design:• Separates into two halves along the vertical axis

• Modular Design:• Easily removable from IR• Allow for staged instrumentation

• Mounted off of pole tips/nose cone calorimeter• To maintain specified tolerances

Page 14: PHENIX Central Region

Robert Pak 14DOE Review

Jan. 19, 2005

Routing for VTX Services

Power, cooling and signal services are

brought in at both ends,using the entire perimeter

Page 15: PHENIX Central Region

Robert Pak 15DOE Review

Jan. 19, 2005

VTX Auxiliary Systems• Services routed radially at the pole tips:

• Power for Si detectors (proper grounding & isolation):• Si HV & LV power supplies

• Cooling system for Si• Operating temperature: < 10o C

• Improve signal/noise performance• Improve response to radiation dosage

• Dry Air System• Bleed boil off from LN2 buggy into enclosure

• Radiation Monitoring• TLDs & Chipmunks

Page 16: PHENIX Central Region

Robert Pak 16DOE Review

Jan. 19, 2005

Infrastructure for VTX

• Electronics racks• Platforms above central magnet• Cooling for electronics• Power for auxiliary systems (proper grounding &

isolation):• Clean & dirty power• 110V & 208V• UPS

Page 17: PHENIX Central Region

Robert Pak 17DOE Review

Jan. 19, 2005

Mechanical StructureID WBS Task Name Start Duration

209 MILESTONE - Completion of Mechanical Structure Fri 2/16/07 0 days

210 1.4.2 Mechanical Structure Tue 5/3/05 470 days

211 1.4.2.1 Mechanical Structure R&D Tue 5/3/05 140 days

212 1.4.2.1.1 Engineering Design + Simulations Tue 5/3/05 140 days

217 1.4.2.2 Cooling System Mon 2/13/06 90 days

218 1.4.2.2.1 Design Mon 2/13/06 10 wks

219 1.4.2.2.2 Procure Mon 4/24/06 40 days

222 1.4.2.3 Outer Stability Structure Mon 10/3/05 340 days

223 1.4.2.3.2 1st Round Mon 10/3/05 75 days

225 1.4.2.3.3 2nd Round Mon 2/27/06 75 days

227 1.4.2.3.4 procure Mon 9/4/06 100 days

232 MILESTONE - Completion of Mechanical LaddersFri 9/1/06 0 days

233 1.4.2.4 barrel ladder staves Mon 11/14/05 210 days

234 1.4.2.4.1 1st Round ladder staves prototypes Mon 11/14/05 40 days

237 1.4.2.4.2 2nd Round Mon 2/6/06 50 days

240 1.4.2.4.3 procure strip ladders Mon 6/12/06 60 days

245 1.4.2.4.4 procure pixel ladders Mon 6/12/06 60 days

250 1.4.2.5 Barrel Mon 10/3/05 360 days

251 1.4.2.5.2 2nd Round Mon 10/3/05 40 days

253 1.4.2.5.3 procure (barrel) Mon 9/4/06 120 days

258 1.4.2.6 ladder coolant tubes Mon 10/3/05 250 days

259 1.4.2.6.2 1st Round Mon 10/3/05 40 days

261 1.4.2.6.3 2nd Round Mon 2/6/06 40 days

263 1.4.2.6.4 procure Mon 6/12/06 70 days

268 MILESTONE Decision to Procure mechanical laddersFri 6/9/06 0 days

269 MILESTONE Decision to Procure mechanical Fri 9/1/06 0 days

270 1.4.2.7 Mechanical Task Out to Bid Mon 4/17/06 100 days

271 1.4.2.7.1 ladders Mon 4/17/06 2 mons

272 1.4.2.7.2 support structures Mon 6/12/06 3 mons

2/16

9/1

6/9

9/1

Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan2004 2005 2006 2007 2008

Page 18: PHENIX Central Region

Robert Pak 18DOE Review

Jan. 19, 2005

Mechanical Structure Budget

Based on HYTEC cost matrix

Page 19: PHENIX Central Region

Robert Pak 19DOE Review

Jan. 19, 2005

Assembly of VTX

ID WBS Task Name Start Duration

273 MILESTONE - vtx ready for installation Fri 12/14/07 0 days

274 1.4.3 Assembly of ladders onto barrel Mon 6/12/06 395 days

275 1.4.3.1 assembly jig for ladders onto barrel Mon 6/12/06 60 days

276 1.4.3.1.1 design jig Mon 6/12/06 4 wks

277 1.4.3.1.2 fabricate jig Mon 7/10/06 8 wks

278 1.4.3.2 mount pixel ladders on barrel Mon 6/25/07 50 days

279 1.4.3.2.1 align + fix ladders Mon 6/25/07 2 mons

280 1.4.3.2.2 test Mon 7/9/07 2 mons

281 1.4.3.3 mount strip Ladders on barrel Mon 9/3/07 70 days

282 1.4.3.3.1 align + fix ladders Mon 9/3/07 3 mons

283 1.4.3.3.2 test Mon 9/17/07 3 mons

284 1.4.3.4 add outer stability structure barrel Mon 12/10/07 1 wk

12/14

Tech

Tech

Jan Apr Jul Oct Jan Apr Jul Oct Jan2006 2007 2008

Page 20: PHENIX Central Region

Robert Pak 20DOE Review

Jan. 19, 2005

Assembly of VTX Budget

Page 21: PHENIX Central Region

Robert Pak 21DOE Review

Jan. 19, 2005

Infrastructure/InstallationID WBS Task Name Start Duration

285 1.4.4 Infrastructure Thu 12/7/06 144 days

286 1.4.4.1 Installation+support Thu 12/7/06 80 days

287 1.4.4.1.1 Beam-pipe Thu 12/7/06 80 days

288 1.4.4.1.1.1 Procure Beam-pipe Thu 12/7/06 2 mons

289 1.4.4.1.1.2 Beam-pipe support Thu 2/1/07 2 mons

290 1.4.4.1.4 Detector Support Thu 12/7/06 80 days

291 1.4.4.1.4.1 Detector Support in CM Thu 12/7/06 2 mons

292 1.4.4.1.4.2 Installation Fixtures Thu 2/1/07 2 mons

293 1.4.4.2 Services Thu 12/7/06 144 days

294 1.4.4.2.1 Rack Platforms Thu 12/7/06 2 mons

295 1.4.4.2.2 Power+water services for IR, outside of IRThu 12/7/06 3 mons

296 1.4.4.2.3 preparation of IR region Wed 5/2/07 2 mons

297 1.4.5 Installation Tue 5/1/07 214 days

298 IR Open Summer 07 Tue 5/1/07 1 day

299 IR close winter 07 Mon 12/31/07 1 day

300 1.4.5.1 Install vtx in inner region Mon 12/17/07 10 days

301 1.4.5.1.1 Tech Mon 12/17/07 1 wk

302 1.4.5.1.2 survey Mon 12/24/07 1 wk

303 1.4.5.6 preops Mon 1/14/08 6 wks

304 1.4.6 Mechanical system Integration Mon 10/3/05 595 days

305 1.4.6.1 Mechanical System Engineer Mon 10/3/05 595 days

306 1.4.6.1.1 oversight tasks Mon 10/3/05 28.25 mons

307 1.4.6.1.2 Design support from nosecone Thu 1/5/06 12 mons

308 1.4.6.1.3 Design installation fixtures Thu 1/5/06 12 mons

309 1.4.6.1.4 Environmental Safety & Compliance Thu 12/7/06 6 mons

310 1.4.6.1.5 supervise installation Mon 12/17/07 1 mon

311 1.4.6.2 Detailing/drawings Thu 1/5/06 22 mons

Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr2005 2006 2007 2008

Page 22: PHENIX Central Region

Robert Pak 22DOE Review

Jan. 19, 2005

Infrastructure/Installation Budget

Page 23: PHENIX Central Region

Robert Pak 23DOE Review

Jan. 19, 2005

Closing Remarks

• Additional people power:• PHENIX-BNL Operations Group has 8 FTE technicians

and 3 FTE engineers• VTX project will have a number of postdocs & students

participating in these tasks• CA Experiment Support Group provides at least one

mechanical engineer plus trades people (carpenters, riggers and electricians)

Page 24: PHENIX Central Region

Robert Pak 24DOE Review

Jan. 19, 2005

Backups

Page 25: PHENIX Central Region

Robert Pak 25DOE Review

Jan. 19, 2005

VTX Design Criteria for HYTEC • Clamshell Design:

• Separates into two halves along the vertical axis• Detector Coverage:

• Hermeticity: single overlap circumferentially• 160o coverage in each half of barrel section• 4 layers of pixels and/or strip detectors in barrel section• 180o coverage in each half of the endcap sections• 4 layers of pixel detectors in endcap sections

• +/- 40o Envelope maintained around barrel section• Endcap pixel disks, utilities, and barrel detector end support

outside of envelope• Main clamshell support structure inside of envelope, but less

than 0.5% radiation length (RL)

Page 26: PHENIX Central Region

Robert Pak 26DOE Review

Jan. 19, 2005

VTX Design Criteria for HYTEC (cont)• RL of 1% or less for each detector layer (includes:

detectors, structure, and utilities)• Dimensional and structural stability of less than 25 µm

for detectors and 100 µm gravitational structural stability of entire tracker

• Utility Routing:• Along barrel end support for barrel region• Radial at pole tips for the end caps

• Mounting of Tracker:• Off of magnet pole tips• Tracker to behave as a rigid body structure• Operating Temperature: Room temperature (or possibly 0o C)

Page 27: PHENIX Central Region

Robert Pak 27DOE Review

Jan. 19, 2005

HYTEC Cost Matrix

+ 15

+ 20

<10 centigrade

Staging Barrel/Endcap

R&D 2005

DOE Proposal

Updated 1/14/05

Page 28: PHENIX Central Region

Robert Pak 28DOE Review

Jan. 19, 2005

Methods: Contingency

• Design/prototype/testing : 25% contingency each cycle• To cover cost risk that an extra pre-production cycle is

needed • Last design/prototype/testing cycle : 50% contingency

• Testing, assembly, and installation tasks: 50% contingency • Purchases based on vendor quotes: 25% contingency• Other purchases, 50% contingency

Page 29: PHENIX Central Region

Robert Pak 29DOE Review

Jan. 19, 2005

Methods: Overhead

• All numbers quoted for manpower are fully loaded $• Material costs include local overhead + sales-tax• Funds moved from BNL to other institutions charged 9%

BNL admin. overhead