MSSC 2011 Annual Salinity Summit
Charles AhrensVice President / Water Resources and Conservation
Challenges in Brackish Groundwater Desalination
Project Development February 17, 2011
![Page 2: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/2.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 2
Presentation Outline• Why Brackish Desalination?• Project Location• Project Components• Project Challenges• Next Steps• Lessons Learned• Summary
![Page 3: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/3.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 3
Why Brackish Desalination?• Governor’s 2002
Desalination Initiative
• Resource close to San Antonio
• Un-utilized resource
• Diversification
SAWS Brackish Test Site 1
![Page 4: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/4.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 4
Project Location• Located on Aquifer Storage
& Recovery property
• 11,800 acre-feet (Phase 1)
• Potential to expand to 25,000 acre-feet
• 45-mile Integration Pipeline will deliver water to south and west, may be built in phases
![Page 5: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/5.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 5
Project Components• Production / Monitor
Wells
• Reverse Osmosis Treatment Plant
• Pipeline System
• Brine Injection Wells
• Electrical System
![Page 6: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/6.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 6
Project Challenges• Groundwater District
Regulation
• State Water Management
• Concentrate Disposal
• Real Estate
• Public Perception
• Funding SAWS Membrane Pilot Test Unit
![Page 7: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/7.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 7
Project Challenges
• Groundwater District Regulation
• State Water Management
• Region L Plan
• Groundwater Management Areas
![Page 8: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/8.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 8
Project Challenges
• Concentrate Disposal
• SAWS Disposal Options– Surface Water– Deep Well Injection
• Permitting– General Permit
![Page 9: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/9.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 9
Project Challenges• Public Perception• Citizen’s Advisory Panel• Project Opposition• Response to Opposition
– Science Committee– Project starts in Bexar
County– Construct Monitor Wells– Continued information to
political leadership in Bexar County and surrounding Counties
![Page 10: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/10.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 10
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
2012 2013 2014 2015 2016 2017
Original CIP Revised CIP w/ Revised Costs & Schedule
$143.7M
$51M
$115.1M
$93.4M
$117.6M
$98.5M
$77.9M
$91.1M
$56.5M
$45.8M $45.8M
$56.5M
Project ChallengesFunding – Water Resources CIP Budget
![Page 11: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/11.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 11
Project Challenges• Other Funding Sources
• TWDB Water Infrastructure Funds
– $35 Million – low interest deferred loans for Planning and Design
– $24 Million – low interest loans for Construction
• Federal Funds – Bureau of Reclamation
![Page 12: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/12.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 12
Next Steps• Additional Pilot Testing (2011)
• Drill Test Injection Well (2011)
• Engage Program Manager (early 2012)
• Engage Construction Manager at Risk (late 2012)
![Page 13: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/13.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 13
Lessons Learned• Inform political leadership early (preferably before
feasibility work)
• Never underestimate project opposition
• Start land acquisition early
• Determine water quality early
• Pilot membranes early
• Refine concentrate disposal options early
![Page 14: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/14.jpg)
February 17, 2011
Challenges in Brackish Groundwater Desalination Project Development
Page 14
Summary
279,000 AF 222,000 AF
• Project Benefits– Diversification - project relieves pressure on the
Edwards Aquifer– Additional use of
previously purchased System property
– “State-of-the-Art” Treatment
– Phase 1 supplies approximately 5% of SAWS water needs
2020 – Worst Year of DOR
60%
2%4%
7%
5%
22%
Edwards Local Carrizo Western CanyonRegional Carrizo Brackish Desalination ASR
253,000 AF
151,000 AF Edwards102,000 AF Non-Edwards
Note: Excludes Recycle Water
![Page 15: Presentation Outline](https://reader036.vdocument.in/reader036/viewer/2022062521/5681697a550346895de17cb0/html5/thumbnails/15.jpg)