Download - Project Quality Management CEM515 Professor Abdulaziz A. Bubshait STD. MOHAMMED AL-SAQAR ID. 270101
King Fahd University of Petroleum& Minerals
Project Quality ManagementCEM515
Professor Abdulaziz A. Bubshait
STD. MOHAMMED AL-SAQARID. 270101
Problem description
Delay in the adoption of the samples provided by the contractor for the elements that use the terms
.“”best kinds” or “equal
Effects
Delay on close-out date of the project .
Rework.
Reject of work.
FLOW CHART aluminum Sample
STARTInstallati
on of aluminu
m
Contractor Supply
aluminum Sample
consultant approval
Owner approval
Yes
No
No
Start installation
of aluminum
YesFix aluminu
m
Finish
PROCESS MAP
CONTRACTUR
CONSULTANT
OWNER
Supply aluminum
Sample
Approval Sample
Finalapproval
Fix aluminum
Pareto Chart
Series10
5
10
15
20
25
30
35
Rewarkdelay on delivery Reject work
Solution
--use more than one type of specifications that used in the projects
--Narrowing of differences on the interpretation of the specifications.
--Early meetings between the contractor , consultant and owner representative for the identification and selection of items enough time before its implementation.