Purple Line ExtensionSection 1 Construction Community Meeting March 17, 2016
-
8/19/2019 Purple Line Extension Community Presentation 03172016
2/78
Agenda
2
• Western look ahead: Demo and sound wall construction
• La Brea Piling Update
• La Brea Decking phases l, ll ,lll
• Fairfax look ahead: Sound wall construction, tree/ median removal, piling
• La Cienega look ahead: Advance utility relocation, building demo
• Eat Shop Play Wilshire• Art Program Update
• Metro’s Plan to Ease Traffic & Potential Ballot Measure
• Question & Answer
-
8/19/2019 Purple Line Extension Community Presentation 03172016
3/78
Purple Line Extension
Project Alignment
3
3
-
8/19/2019 Purple Line Extension Community Presentation 03172016
4/78
Section 2 and 3
Status
Under Construction Forecasted Schedule
Section 1 Section 2 Section 3
Length 3.9 Miles 2.55 Miles 2.48 Miles
New Stations Wilshire/La BreaWilshire/Fairfax
Wilshire/La Cienega
Wilshire/RodeoCentury City/
Constellation
Westwood/UCLAWestwood/VA
Hospital
Pre-Construction Activities Current - 2016 2015 - 2018 2025 - 2027
Construction 2015 - 2023 2019 - 2026 2027 - 2035
Operations 2024 2026 2035 4
-
8/19/2019 Purple Line Extension Community Presentation 03172016
5/78
PLE Section 1
Alignment
5
5
-
8/19/2019 Purple Line Extension Community Presentation 03172016
6/78
Purple Line Maintenance Facility
Butterfield Property
590 S Santa Fe Avenue
• Located in Arts District
downtown, near 6th St Bridge
• Continuation of Abatement work
– Monday thru Saturday
– Work Hours: 7am to 4:30pm
6
-
8/19/2019 Purple Line Extension Community Presentation 03172016
7/78
Tie-in at Western Station
7
Future Western Staging Yard•Northeast corner of Wilshire and Manhattan Place
one block east of Western
•Demolition activities underway. Maintenance and
debris removal remain.
– Work Hours: 7am to 4pm, Monday thru
Friday•Fencing and signage placed at site
•Sound wall construction will follow building
demolition.
•Additional activities in
Western area include
pot holing and street
restoration
-M-F, 9am-3:30pm
-Sat-Sun, 8am-6pm
Demolition Activities
-
8/19/2019 Purple Line Extension Community Presentation 03172016
8/78
Crenshaw Yard Staging Site
Wilshire/Crenshaw • Used throughout Section 1 utility relocation and construction
• Mitigation efforts and maintenance:
– Crenshaw Gate Entrance re-worked and improvements made
• Temporary fence with sound blankets in place
– Lorraine Gate temporarily closed until further notice – “No Metro Contractor Parking on City Street” signs
– Noise awareness training, nightly noise readings
– Maintenance inside and outside of yard
8Signage at the Crenshaw Yard and Storm Drain Barriers 8
-
8/19/2019 Purple Line Extension Community Presentation 03172016
9/78
La Brea Station
Rendering shows length of the La Brea underground station boxon Wilshire Blvd from Orange Dr to Detroit St 9
-
8/19/2019 Purple Line Extension Community Presentation 03172016
10/78
Purple Line Extension
La Brea Schedule
10
*As of October 2015. Subject to Change
-
8/19/2019 Purple Line Extension Community Presentation 03172016
11/78
La Brea Station
Pile Installation
11
• On Wilshire from Orange Dr. to Detroit St.• Pile installation includes:
– Rig to construct 95ft (L) deep
– Crane lifting 95Ft (L) , 24 Inch H-piles into
holes
– 1-2 piles per day, 390 piles total
– Drilling, pile installation and backfilled
concrete completed same day
• All work occurs behind a k-rail (concrete barriers).
• Operation anticipated to take approximately 4-6
months on each side of the street.
• Typical work hours 7am-11pm with potential
nighttime work hours from 11pm to 7am.
• Wilshire is reduced to two lanes in each direction• Additional closures may be needed.
-
8/19/2019 Purple Line Extension Community Presentation 03172016
12/78
La Brea Station
ConstructionPre-Trenching and Pile Installation for North side ofWilshireContinuous thru April 2016*
• Orange Dr to Detroit St
• Work hours: 7am to 11pm with potential nighttime work hours
from 11pm to 7am.
• La Brea intersection
• Work hours: 9pm Friday to 6am Monday, lane reductions
Pre-Trenching and Pile Installation for South side of
WilshireApril 2016-July 2016*
• Orange Dr to Detroit St
• Work hours: 7am to 11pm with potential nighttime work hours
from 11pm to 7am.
• Transition to south side may require a weekend closure or lane
reductions of Wilshire Blvd from Detroit to Highland. *
• Will require directional closures on La Brea and intermittent
closures of Orange Dr and Sycamore
12
*Dates and work activities subject to change
-
8/19/2019 Purple Line Extension Community Presentation 03172016
13/78
La Brea Station
Appendage Piles• Appendage piles are the ancillary piles for the structures on the sides of the station box.• Located on the north and south side of Wilshire Blvd
• Appendage structures include:
• Vent shafts, exit stairwells, and station entrance at La Brea
• Appendage piles are smaller and shorter (40-60ft.) than the station box piles.
• 112 Appendage Piles
13
-
8/19/2019 Purple Line Extension Community Presentation 03172016
14/78
Appendage PilesSchedule
North side of Wilshire Appendage pilesFebruary-March 2016
• North side Orange Dr. appendages: 2 weeks-currently
underway
• North side La Brea Ave. appendages: 2 weeks-currently
underway
• North side Sycamore Ave. appendages: 3 weeks
South side of Wilshire Appendage Piles• South side appendage structures to start May
2016
Traffic control• Side streets will be closed to thru traffic at
Wilshire
•Access from 6
th
, 8th
, and alleys will be maintained• Sycamore Ave. and Orange Dr. will not be fully
closed concurrently at any time
• Intermittent sidewalk closures
14
Appendage Pile Work at Orange Dr
-
8/19/2019 Purple Line Extension Community Presentation 03172016
15/78
Staging Yard Activities andEquipment
• Daytime operation: 7am to 4pm
• Majority of wall work completed
except at location where pile
installation and decking occur
• Sound wall is 20 feet high• Maintenance of equipment
• Deliveries
Mitigations
• Must comply with COLA noise
requirements
• Noise Control Signage
• Low Impact Back up alarms
• Acoustical Insulation
• Metro 5 Step Noise Plan
La Brea Station
La Brea Staging Yards
15
Eat Shop Play promotions and construction phase
artwork
N La Brea Staging Yard Pile Work
-
8/19/2019 Purple Line Extension Community Presentation 03172016
16/78
La Brea Station
Decking Overview
Decking• On Wilshire, between Orange Dr. and Detroit St.
• Construction of a concrete deck, curb to curb
• Sidewalks be maintained, or pedestrian detours created
• Decking will serve as the temporary street surface
• Traffic will travel on the installed deck panels while the
station is constructed underground• La Brea Station:
– Approx. 1,000 feet long
– Approx. 70 feet wide
– Approx. 60 feet deep
• Will follow pile operations; anticipated to begin June
2016• Will work closely with First Responders on emergency
access and safety
16
16
-
8/19/2019 Purple Line Extension Community Presentation 03172016
17/78
La Brea Station
Decking Weekend Closures – Start June 2016
Green: La Brea to Highland• Phase 3: 16 weekends
Purple: La Brea to Detroit• Phase 1: Three weekends, Detroit to La Brea
• Phase 2: Three weekends, La Brea intersection
17
-
8/19/2019 Purple Line Extension Community Presentation 03172016
18/78
La Brea Station
Decking Schedule
June 2016 through Fall 2016Approximately 22 weekend closures (no work 4th of July or Labor Day weekends)
• Work scheduled in three phases.
• Fridays 10am: Wilshire (Phase 1 and 3) or La Brea (Phase 2) reduced to one lane each
direction
• Friday 8pm: Full closure of Wilshire (Phase 1 and 3) or La Brea (Phase 2)
• Monday 6am: Streets open
• Work occurs 24/7
Phase 1: Three weekends, Detroit to La Brea
Phase 2: Three weekends, La Brea intersection
Phase 3: 16 weekends, La Brea to Highland
18
*Dates and work activities subject to change
-
8/19/2019 Purple Line Extension Community Presentation 03172016
19/78
La Brea Decking Phase 1
3 Weekends-Detroit St to La Brea
19
-
8/19/2019 Purple Line Extension Community Presentation 03172016
20/78
Phase 1 Detour
Detroit-La Brea Closure DRAFT
20
WB: Westbound Wilshire
to northbound La Brea to
westbound 6th St to
southbound Fairfax to
Wilshire
EB: Eastbound Wilshire to
northbound Fairfax to
eastbound 6th St to
southbound La Brea to
Wilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
21/78
La Brea Decking Phase 2
3 Weekends, La Brea Intersection
21
-
8/19/2019 Purple Line Extension Community Presentation 03172016
22/78
Phase 2 Westbound Detour
La Brea/Wilshire Intersection Closure DRAFT
22
WB: Westbound Wilshire
to northbound Highland to
westbound 6th St
westbound to southbound
Fairfax to Wilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
23/78
Phase 2 Eastbound Detour
La Brea/Wilshire Intersection Closure DRAFT
23
EB: Eastbound Wilshire to
northbound Fairfax to
eastbound 6th St to
southbound Highland to
Wilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
24/78
La Brea Decking, Phase 3
16 Weekends: La Brea to Highland
24
-
8/19/2019 Purple Line Extension Community Presentation 03172016
25/78
Phase 3 Detour
La Brea to Highland DRAFT
25
EB: Eastbound Wilshire to
northbound La Brea to
eastbound 6th St to
southbound Highland to
Wilshire
WB: Westbound Wilshire to
northbound Highland to
westbound 6th St to
southbound La Brea toWilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
26/78
La Brea Station Decking
Community Outreach
26
• Robust Marketing Campaign
• Social Media: Facebook, Twitter, Nextdoor
• Advertising: print, radio, online
• Media Coverage: press release
• Business and resident outreach
• Meetings with local groups, leaders• Elected Official Briefings
• Safety Presentations
• School Presentations
• Community Partnerships
• Board of Public Works Approval - April
I-405 Freeway Closure “Carmageddon”
-
8/19/2019 Purple Line Extension Community Presentation 03172016
27/78
Jet Grouting
● Jet grouting is a construction process that uses high-pressure airand grout to create a deep soil-concrete block.
● The purpose of jet grouting is to reinforce and strengthen the
soil with concrete to support tunneling and cross-passage
excavation.
27
-
8/19/2019 Purple Line Extension Community Presentation 03172016
28/78
Jet Grouting Locations
• Jet Grouting will occur at 16 locations
along Wilshire between La Cienega and
Western.
• There will be no more than two jet-
grouting operations being performed atone time.
• Approximately 6 weeks at each location.
28
1. On Wilshire between Rossmore and Arden
2. On Wilshire between Arden and Lucerne
3. On Wilshire between Citrus and Mansfield
4. On Wilshire between Highland and McCadden Pl
5. On Wilshire between Cochran and Cloverdale
6. On Wilshire between Plymouth and Windsor
7. On Wilshire between Norton and Bronson
8. On Wilshire between St Andrews and Grammercy
9. On Wilshire between Crenshaw and Lorraine
10. On Wilshire between Wilton and Van Ness
11. On Wilshire between La Jolla and Sweetzer
12. On Wilshire between La Jolla and Sweetzer
13. On Wilshire between Crescent Heights and La Jolla
14. On Wilshire between Burnside and Dunsmuir
15. On Wilshire between Spaulding and Ogden
16. On Wilshire between Fairfax and Crescent Heights
*Dates and work activities subject to change
-
8/19/2019 Purple Line Extension Community Presentation 03172016
29/78
Jet Grouting Layout & Activities
• Potholing, street level excavation
• Vertical drilling
• Trucking
• Cement silos, pumps, generators
29
-
8/19/2019 Purple Line Extension Community Presentation 03172016
30/78
Jet Grouting Layout
• Lanes reduced to two lanes each direction at Jet grouting locations
30
-
8/19/2019 Purple Line Extension Community Presentation 03172016
31/78
Jet Grout Schedule
• A jet grout soil test began this past week
behind concrete barriers at
Wilshire/Detroit and will occur in the
staging yard at Fairfax/Ogden in Spring
2016.
• Jet grouting will start on Wilshire Blvd in
the La Brea area in June 2016.
• Wilshire between Rossmore and
Arden
• Wilshire between Arden and Lucerne
• Construction notices will be sent and
outreach will be conducted for each
location
31
*Dates and work activities subject to change
-
8/19/2019 Purple Line Extension Community Presentation 03172016
32/78
Deck OpeningsWhat:• Deck openings are openings of the street-
deck for the purpose of delivering materials
for underground construction.
• Deck openings will be done at locations of the
deck that are designed to open and close.
• Deck openings will occur periodically, on an
as needed basis.• Deck panels are 8ftx14ft
When:• Following decking, late summer/early fall of
2016 .
• Through the duration of the project.
How:• Off-peak hour (M-F, 9am-3:30pm) lane
closures to allow the removal of panels.
32
-
8/19/2019 Purple Line Extension Community Presentation 03172016
33/78
Deck Openings
Construction Activities Requiring
• Concrete placement
• Maintenance of deck beams, panels and utilities
• Deliveries into excavation/station - rebar, struts,lumber, MEP equipment, shoring and formwork
panels, construction equipment, ventilation,
utilities, waterproofing
• Station backfilling
• Installation of new and replacement utilities
33
-
8/19/2019 Purple Line Extension Community Presentation 03172016
34/78
Fairfax Station
Rendering shows length of the Fairfax underground station box
on Wilshire Blvd from west of Fairfax to just west of Ogden Dr.34
Fairfax Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
35/78
Fairfax Station
Schedule*Schedule is subject to change. Updated as of January 2016.
35
F i f S i
-
8/19/2019 Purple Line Extension Community Presentation 03172016
36/78
Fairfax Station
Advance Utility Relocation
• Remaining AUR telecommunicationwork
• Potholing continues
• Work hours:
o Monday thru Friday: 9am-3:30pm
o Friday: 10pm-8am
o Saturday: 8am-5pm
36
Photos of recent AUR work for Fairfax Station
Photos of recent AUR work at Wilshire/Fairfax
Fairfax Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
37/78
Fairfax StationDemolition at Ogden Staging Yard
37
Next Steps:• Sound wall and driveway construction
begins in April
-
8/19/2019 Purple Line Extension Community Presentation 03172016
38/78
Ogden Staging Yard
Sound Wall Construction
● Construction of sound wall
and driveways scheduled to
start in April
● Work hours: 7am-5pm
● Sound wall is 20-24 ft
● Eat Shop Play promotionsand construction phase
artwork will be added to
the walls
38
O d S d W ll
-
8/19/2019 Purple Line Extension Community Presentation 03172016
39/78
Ogden
Sound
Wall
Height
&
Plans
39
O d Y d
-
8/19/2019 Purple Line Extension Community Presentation 03172016
40/78
Ogden Yard
Safety Measures & Mitigations
.
Examples fromWilshire/La Brea
Staging Yard
40
-
8/19/2019 Purple Line Extension Community Presentation 03172016
41/78
Fairfax Tree and Median Removal
• Tree removal starts in April, estimated 1 week duration
• Median removal starts after tree removal, 3 weeks
• Work hours: 9:00am-3:30pm M-F, 8:00am-6:00pm Sat/Sun
• 38 street trees will be removed. Potential to protect in place
3 of 38.
• Trees replaced at a ratio of 2:1 at the end of the project
• Banner highlighting future landscape will be place on
Ogden sound wall
• 3 medians to be removed from Fairfax to Spaulding.
41
-
8/19/2019 Purple Line Extension Community Presentation 03172016
42/78
Wilshire/Fairfax Street & Median Tree
Removal Locations
42
l h d l
-
8/19/2019 Purple Line Extension Community Presentation 03172016
43/78
Wilshire Street & Median Tree Removal
Locations
43
-
8/19/2019 Purple Line Extension Community Presentation 03172016
44/78
Fairfax Median Removal Locations
44
-
8/19/2019 Purple Line Extension Community Presentation 03172016
45/78
Future Landscape Medians at Fairfax
45
-
8/19/2019 Purple Line Extension Community Presentation 03172016
46/78
Wilshire/Fairfax Bus Stop Relocations
46
-
8/19/2019 Purple Line Extension Community Presentation 03172016
47/78
Food Truck Relocation
April 1st - relocation for food trucks 1 block east of current location
Existing food truck location 47
Fairfax Traffic Reconfiguration
-
8/19/2019 Purple Line Extension Community Presentation 03172016
48/78
Fairfax Traffic Reconfiguration
Piling Preparation
● Earliest start is June 2016 (if construction stars align!)● Start date depends on DWP cable pulling, 3rd party relocations.
● Install traffic reconfiguration over a single weekend implementing lane
reductions. Ogden crosswalk to shift from west leg to east leg.
● Piling anticipated to start on North side of Wilshire Blvd between Ogden
and San Diego Way.● Wilshire will be reduced to two lanes in each direction.
● Potential off-peak lane reductions to one lane in each direction.
● All left turn pockets will remain open at Wilshire and Fairfax during north
side pile operations only.
48
F i f St ti
-
8/19/2019 Purple Line Extension Community Presentation 03172016
49/78
Fairfax Station
Pile Installation Overview
47
• Pile installation includes:
– Rig to construct 95ft (L) deep
– Crane lifting 95Ft (L) , 24 Inch H-piles into
holes
– 1-2 piles per day, approx. 370 piles
– Drilling, pile installation and backfilled
concrete completed same day
• All work occurs behind a k-rail (concrete barriers).• Operation anticipated to take approximately 4-6
months on each side of the street.
• Typical work hours 7am-11pm with potential
nighttime work hours from 11pm to 7am.
• Wilshire is reduced to two lanes in each direction
• Additional closures may be needed.PHOTO
49
-
8/19/2019 Purple Line Extension Community Presentation 03172016
50/78
La Cienega Station
Rendering shows length of the La Cienega underground station
box on Wilshire Blvd from La Cienega to Tower Dr.50
L Ci Utilit R l ti
-
8/19/2019 Purple Line Extension Community Presentation 03172016
51/78
La Cienega Utility Relocation
30 Months *Schedule is subject to change. Updated as of January 2016.
51
La Cienega Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
52/78
La Cienega Station
Advanced Utility Relocation
• Electrical, Water, Sewer, Storm Drain and Gas work continues along thealignment on Wilshire from La Cienega to San Vicente.
Photos of recent AUR work for the La Cienega Station
52
La Cienega Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
53/78
La Cienega Station
Advanced Utility Relocation
Current AUR activities continue duringdaytime and evening hours.
Days and Hours*
o Monday thru Friday: 7am – 4pm
o Saturday or Sunday: 8am – 6pm
o Night Time Hours:
• 8pm – 6am or
• 12am – 7am
* Hours vary for events at The Saban Theatre
53
La Cienega Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
54/78
La Cienega Station
Gale Yard
• Demolition of buildings on Gale andWilshire May 2016
• Future Gale Staging Yard
• Beverly Hills Fire Department may use
abated properties for fire drill exercisesprior to demolition
• Updates will be provided to the
community when drills are scheduled
54
La Cienega Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
55/78
La Cienega Station
La Cienega Yard
• Future La Cienega Staging Yard
Buildings to be demolished,
anticipated May 2016
55
La Cienega Station
-
8/19/2019 Purple Line Extension Community Presentation 03172016
56/78
La Cienega Station
Weekend Work
Photo
56
• January 16th thru May 28th work occursin intersection at Wilshire and La Cienega
• Weekends, Friday thru Sunday
• Detours and turning restriction will
depend on location of construction. – Wilshire, at least one lane open in each
direction
– La Cienega, at least one lane open in each
direction
• Days and Hourso Start: Friday 10pm or 1am*
o End: Sunday by 6pm*start time depends on the Saban Theatre performance schedule
Eat, Shop, Play Wilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
57/78
Eat, Shop, Play Wilshire
ESP Spotlight- East Segment
5757
Hancock Park Veterinary Clinic5178 Wilshire Blvd. Los Angeles, CA 90036
(One block from future La Brea Station.)
They provide superior customer service, excellent medicine and
fantastic bedside manner to all pets. The team displays unrivaled
commitment to clients through continuing education,
technological advances in veterinary medicine and service, and
most importantly, administering compassionate care to all petsentrusted to them.
Metro Discount: Mention “Metro” or “Purple Line Extension” and
receive $20 off exam fee.
More Information: Please visit HancockParkVetClinic.com or call
323.936.6952.
Eat Shop Play Wilshire
http://hancockparkvetclinic.com/http://hancockparkvetclinic.com/
-
8/19/2019 Purple Line Extension Community Presentation 03172016
58/78
58
Eat, Shop, Play WilshireESP Spotlight- West Segment
Prospect Gourmand
Prospect Gourmand is a farm to table concept, using
local farmers market ingredients to enhance the palate
with the flavors of the season. This American eclectic
cuisine is balanced with French technique, and seasonal
California fare.
Go Metro 272 S. La Cienega Blvd,
Beverly Hills, CA 90211
Mention Metro for a complimentary non-
alcoholic beverage with your meal!
For more info visit:
http://www.prospectgourmand.com/fine-
local-cuisine/
Eat Shop Play Wilshire
http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/http://www.prospectgourmand.com/fine-local-cuisine/
-
8/19/2019 Purple Line Extension Community Presentation 03172016
59/78
59
Eat, Shop, Play WilshireQuarterly Drawing
• Next drawing will occur March 29, 2016• Spend $25 at participating business
• Win cash prizes
SPONSORED BY:
La Brea and Wilshire Business Stroll
Saturday, April 2, 2016
10am to 10pm
Eat Shop Play Wilshire
-
8/19/2019 Purple Line Extension Community Presentation 03172016
60/78
60
Eat, Shop, Play WilshireFortune Fridays
• Support local businesses &
spread the word on social media
about your positive experience
for a chance to win $50!
Participation is easy!
• Use “#EatShopPlay” and
“#Wilshire” in your positive social
media posts.
• “Like” & “Follow” our pages to
see the winner announcementsevery Friday!
-
8/19/2019 Purple Line Extension Community Presentation 03172016
61/78
61
-
8/19/2019 Purple Line Extension Community Presentation 03172016
62/78
Upcoming BIF Workshops
Purple Line Extension, Phase 1
Wednesday, April 20, 2016
6:30pm -7:30pm
RED Real Estate (1st Floor)
5150 Wilshire Blvd., Los Angeles, CA 90036*Street Parking Only
Wednesday, June 29, 2016
11:30am -12:30pmBREATHE LA (1st Floor, Conference Room)
5858 Wilshire Blvd., Los Angeles, CA 90036*Street Parking Only
62
For more information visit
www.pcrcorp.org or contact Angela
Winston, Program Manager at
213.739.2999, ext 223
http://www.pcrcorp.org/http://www.pcrcorp.org/
-
8/19/2019 Purple Line Extension Community Presentation 03172016
63/78
Metro’s Plan to Ease Traffic
March 2016
85
-
8/19/2019 Purple Line Extension Community Presentation 03172016
64/78
Metro’s Unique Role
• 1,433-square mile service area across 88 cities
• From the desert to the beaches, Metro provides
transportation to a region the size of Rhode Island –that’s 10 million Angelenos
• Provides funding for local streets, city improvements
86
-
8/19/2019 Purple Line Extension Community Presentation 03172016
65/78
Metro’s Progress in Easing Traffic
• Metro provides 450 million rides a year
– 99 miles of rail and subway
– 2,200 buses providing service on through 170 routes
• Metro is expanding through the public’s
investment – Two rail lines opening in 2016
– Three additional rail lines in construction
– Several highway improvements underway
• Metro has a strong foundation to plan for
future transportation needs
87
-
8/19/2019 Purple Line Extension Community Presentation 03172016
66/78
Still Much More to Do
• LA County expected to grow by another 750,000people in the next 10 years
• Expanding LA County’s transportation network:
– More highway and transit alternatives, local improvements,
and resources to keep services in good operating condition
• It’ll take a combination of local, federal and private
dollars to fund future transportation improvements
88
-
8/19/2019 Purple Line Extension Community Presentation 03172016
67/78
• Additional local sales tax investment will allow Metroto deliver more projects sooner rather than later
• The Governor recently signed into law SB767,
authorizing Metro to put a sales tax measure on a
future ballot• Metro is considering pursuing a sales tax election in
November for an additional ½ cent
More Local Investment Paves the Way
89
-
8/19/2019 Purple Line Extension Community Presentation 03172016
68/78
• 5 cents on a $10 purchase• $50 a year to invest in easing traffic
− Buying a coffee drink once a week costs $260/year
− Eating fast food once a week costs $420/year
• Modest investment will bring major benefits
− More transportation alternatives
− More ways to connect through technology
−
More community improvements
− More quality time, more time for you
What This Means for You
90
-
8/19/2019 Purple Line Extension Community Presentation 03172016
69/78
Why Now?
• We spend an average of 70 hoursa year stuck in traffic
• Time is money – the longer it
takes to build out transportation
improvements the moreexpensive it will be
• If we don’t plan now for future
growth, gains of recent years willgive way to more traffic
congestion
91
-
8/19/2019 Purple Line Extension Community Presentation 03172016
70/78
Annual Revenue Assumptions
• New ½ cent tax = $860 million/year – FY18-FY39 – ½ cent building on top of existing Measure R
• New ½ cent and Measure R together – $1.7 billion/year – FY40-FY57 – 1 cent replaces Measure R tax rate
• New revenues would begin in FY18
$120 billion in YOE dollars would be generated over the
40-year program
92
-
8/19/2019 Purple Line Extension Community Presentation 03172016
71/78
Potential Ballot Measure • Transforming transportation will include projects in all
sub-regions of Los Angeles County
• Metro conducted a bottoms-up process with the nine
sub-regions of the county, which submitted projects
for evaluation
93
-
8/19/2019 Purple Line Extension Community Presentation 03172016
72/78
Potential Ballot Measure
• Metro is evaluating the major transit and highwayprojects through established Performance Metrics
• These metrics are based on industry best practices and
reflects feedback from Board Members and regional
stakeholders
94
-
8/19/2019 Purple Line Extension Community Presentation 03172016
73/78
Proposed Performance Metrics Themes & Weights
• Improve travel times and reliability; increase active transportation
• Increase service to the transit dependent, cyclists, youths, pedestrians, seniors,
and people with disabilities; increase those served by Metro; improve first-last
mile
• Enhance personal and public safety; reduce incidents
• Create jobs; increase goods movement; invest in disadvantaged communities
• Reduce greenhouse gases; improve air quality; positively impact public health
95
-
8/19/2019 Purple Line Extension Community Presentation 03172016
74/78
Project Evaluation Process
• The evaluation process will be the foundation fordeveloping the Expenditure Plan
• The plan will include cost estimates and schedules for
the major construction projects
• This process provides an opportunity to potentially
accelerate some Measure R projects while keeping
other existing projects on their current schedule
96
-
8/19/2019 Purple Line Extension Community Presentation 03172016
75/78
Next Steps
• Project Evaluation and Financial Modeling– December 2015-March 2016
• Expenditure Plan Recommendation to Board – March
• Public Comment – March-June
• Board Decision on November Tax Vote – June
97
-
8/19/2019 Purple Line Extension Community Presentation 03172016
76/78
Thank you
98
-
8/19/2019 Purple Line Extension Community Presentation 03172016
77/78
Next Meeting
99
Section 1 Construction Community MeetingThursday, May 19, 2016
6:30-8:30pm
John Burroughs Middle School Auditorium
600 S. McCadden Pl., Los Angeles, CA 90005
Beverly Hills Specific Community Meeting
Tuesday, March 29, 2016
La Cienega Tennis Center
5:30-7:00pm
h
-
8/19/2019 Purple Line Extension Community Presentation 03172016
78/78