Download - Revwerqer

Transcript
  • PROJECT : NESTLE CDO UPGRADINGLOCATION : CAGAYAN DE ORO, CITYOWNER : NESTLE PHILIPPINES, INC.CONTRACTOR : Bauer International Phils., Inc.SUBJECT : Construction Schedule

    14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26

    I. General Requirements

    1 Design and Approval of Construction Drawings, & other Documentation

    2 Health & Safety

    3 Mobilization

    4 Temporary Facilities

    II Mechanical Works

    1 Procurement of Imported Equipment( Blowers,, Diffusers,Submersible Mixers and Instrumentations)

    2 Fabrication of Lamella Clarifier, Flocculation Loop and and Retrievable Diffusers

    3

    4 Installation of Lamella Clarifiers , Acidification and pH Adjustment System

    5 Installation of Submersible Mixers

    6 Testing & Commissioning of Lamella Clarifier, acidification and ph Adjustment System

    6 Installation of Blower ,Retrievable Air diffusers and Air Distribution Line

    V Testing & Commissioning

    1 Pre-commissioning

    2 Effluent Sampling

    2 Lecture, Training, & Orientation

    VI Demobilization

    VII As-Built Drawings

    ACTIVITIESAUGUST SEPTEMBER

    6 7 8 91 2 3 4 5

    Delivery of Equipment and Materials to Cagayan De Oro

    JULY

    10 11

  • 27 29 20 1 2 3 4 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22 23 24 25 27 28 29 30 31 1 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19 20 21 22 24 25 26 27 28 29 1 2 3 4 5 6 8 9 10 11 12 13

    Approved By:

    Authorized Representative

    OCTOBER

    2213 14 15 19 20 2116 17 18

    DECEMBERNOVEMBER

    12


Top Related