revwerqer
DESCRIPTION
rewct432cTRANSCRIPT
-
PROJECT : NESTLE CDO UPGRADINGLOCATION : CAGAYAN DE ORO, CITYOWNER : NESTLE PHILIPPINES, INC.CONTRACTOR : Bauer International Phils., Inc.SUBJECT : Construction Schedule
14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26
I. General Requirements
1 Design and Approval of Construction Drawings, & other Documentation
2 Health & Safety
3 Mobilization
4 Temporary Facilities
II Mechanical Works
1 Procurement of Imported Equipment( Blowers,, Diffusers,Submersible Mixers and Instrumentations)
2 Fabrication of Lamella Clarifier, Flocculation Loop and and Retrievable Diffusers
3
4 Installation of Lamella Clarifiers , Acidification and pH Adjustment System
5 Installation of Submersible Mixers
6 Testing & Commissioning of Lamella Clarifier, acidification and ph Adjustment System
6 Installation of Blower ,Retrievable Air diffusers and Air Distribution Line
V Testing & Commissioning
1 Pre-commissioning
2 Effluent Sampling
2 Lecture, Training, & Orientation
VI Demobilization
VII As-Built Drawings
ACTIVITIESAUGUST SEPTEMBER
6 7 8 91 2 3 4 5
Delivery of Equipment and Materials to Cagayan De Oro
JULY
10 11
-
27 29 20 1 2 3 4 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22 23 24 25 27 28 29 30 31 1 3 4 5 6 7 8 10 11 12 13 14 15 17 18 19 20 21 22 24 25 26 27 28 29 1 2 3 4 5 6 8 9 10 11 12 13
Approved By:
Authorized Representative
OCTOBER
2213 14 15 19 20 2116 17 18
DECEMBERNOVEMBER
12