RF work plan
• Test first large amplifier at Daresbury– Electric checks are being made now– Driver amplifiers being retested now– Expect results mid Dec 09
• Study of requirements/desires for MICE hall RF layout, coax systems, component sizes and method to construct under MICE hall floor – starting Jan 10 – report after 3 months
• CAD visualisation of RF layout required
![Page 2: RF work plan](https://reader035.vdocument.in/reader035/viewer/2022071718/56812cec550346895d91b01e/html5/thumbnails/2.jpg)
• If funding allows – rebuild and test of large amplifier 2 beginning April 2010 – 6 months
• Disassembly of first large amplifier system and power supplies, transport to RAL, install in MICE hall and prepare for test in area, autumn 2010
• Prepare report into RF layout installation for step 5 and specification of design for step 6 if changes are needed