RF work plan • Test first large amplifier at Daresbury – Electric checks are being made now – Driver amplifiers being retested now – Expect results mid Dec 09 • Study of requirements/desires for MICE hall RF layout, coax systems, component sizes and method to construct under MICE hall floor – starting Jan 10 – report after 3 months • CAD visualisation of RF layout required

Upload: howard-herrera

Post on 31-Dec-2015

12 views

Category:

Documents


2 download

DESCRIPTION

RF work plan. Test first large amplifier at Daresbury Electric checks are being made now Driver amplifiers being retested now Expect results mid Dec 09 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: RF work plan

RF work plan

• Test first large amplifier at Daresbury– Electric checks are being made now– Driver amplifiers being retested now– Expect results mid Dec 09

• Study of requirements/desires for MICE hall RF layout, coax systems, component sizes and method to construct under MICE hall floor – starting Jan 10 – report after 3 months

• CAD visualisation of RF layout required

Page 2: RF work plan

• If funding allows – rebuild and test of large amplifier 2 beginning April 2010 – 6 months

• Disassembly of first large amplifier system and power supplies, transport to RAL, install in MICE hall and prepare for test in area, autumn 2010

• Prepare report into RF layout installation for step 5 and specification of design for step 6 if changes are needed