Sausalito Ferry Landside Improvements Project
Update
SAUSALITO CITY COUNCIL MEETING
SEPTEMBER 24, 2019
BACKGROUND
Phase 1GGBHTD Builds Temp Ferry Landing
Golden Gate Bridge Highway Transportation District Project
Summer 2020 – June, October, November
Phase 2 GGBHTD Rebuilds Existing DockMove Ferry Back to Rebuilt Dock
Golden Gate Bridge Highway Transportation District Project
Summer 2021 – June, October, November
Phase 3Demolition of Temporary Dock
Golden Gate Bridge Highway Transportation District Project
Summer 2022 – June, October, November
City of Sausalito – Ferry Landside Improvements
Study Area – Visioning Phase (Package A
Vision plus Parking Area Improvement Required per the Grant
– Design (Package B)
• $2.4 million Federal Grant Pass through from GGBHTD Grant
• Improvements to access for Citizens of Sausalito and Commuters
• Maintain and Improve experience for tourists and residents
• Parking and Connectivity Improvements
Estimated Timeline (Plaza Design/Construction)
• October 2019 – Award of Professional Service Contract• Summer 2020 - Preferred Alternative Development for Plaza
Improvements• Fall 2020 – Spring 2021 - Federal Approval Process• Fall 2020 – Spring 2021 - Environmental Approval• Spring 2021 - Completion of Design Package• Spring 2021 - December 2021 - Construction
Timeline (Visioning Plan)
• October 2019 – Award of Professional Service Contract• Spring 2020 – Public Outreach Meetings and General Planning • Summer 2020 - Preferred Alternative Development for Plaza
Improvements
Current Status
• City Requested Proposals from Qualified Consultants (June 2019)
• City Received three proposals from qualified firms (July 2019)
• Consultant Interviews held for selecting consultants (September 2019)
Proposal Harris and AssociatesBKF EngineersSWA
• Harris’s Quote• Package A Visioning + 30% Design
$672,113
• Package B Visioning + Full Design $1,428,900
Current BudgetFTA Grant $2,000,000GGBHTD $400,000City Funds $100,000
Total = $2,500,000
Preliminary Cost Estimates
Ferry Landside Construction • Design (12.5%) $230,000• Construction $1,900,000• Contingency (10%) $190,000• Construction Management (~10%) $180,000
Total = $2,500,000
Minimal Improvements within
the Ferry Landing Area
No funding in this case for Visioning Package A
Preliminary – Modification may be needed
Options and Direction
City Council Assistance and Direction
Direct staff to negotiate with Harris to reduce their cost for Package B to be in relative conformance with the budget and proceed with the work.
Rebid this portion of the project.
Questions and Comments