Audubon Park K-8 School Board Member Nancy Robbinson
40% Construction Community MeetingOctober 25, 2017 @ 6:00 PM
Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Welcome! Please sign in on your mobile device:
http://communitymeeting.ocps.net/
1
Orange County Public Schools
Audubon Park K-8 40% Construction Meeting AgendaOctober 25, 2017 – 6:00pm – Audubon Park Elementary School
• Welcome – School Board Member Nancy Robbinson
• Introductions – Lauren Roth, Facilities Communications
• Project UpdateArchitect: Baker Barrios ArchitectsConstruction Manager: WELBRO Building Corporation
• Questions and Answers
• Adjournment
2
Audubon K-8 Site Aerial
Orange County Public Schools
3
N
Orange County Public Schools
Site Plan: First Floor Overall Plan
Project Data
Capacity: 1,350 Student Stations
Building Area: 169,041 SF
Parking Provided: 183 Spaces
Site Area: 13.25 Acres
EHPA Shelter
North
4
Orange County Public Schools
View of Entry & Administration Building 5
Orange County Public Schools
Front of School / Parent Drop-off 6
Orange County Public Schools
Construction Update and Milestones• Notice to Proceed (NTP) was issued March 17, 2017.• Tilt wall panels were completed on August 18, 2017.• Critical path structural steel erection was completed on September 25, 2017.• Roofing work has started and scheduled to dry-in by November 14, 2017.• Window installation to start in October.• Exterior painting has started and is scheduled to complete in October. • Interior work is in progress.• Project will be 40% complete as of October 31, 2017.• Project remains on schedule for Substantial Completion on June 15, 2018.
7
Orange County Public Schools
Aerial Photo – April 10, 2017 8
Orange County Public Schools
Aerial Photo – May 10, 2017 9
Orange County Public Schools
Aerial Photo – June 9, 2017 10
Orange County Public Schools
Aerial Photo – July 11, 2017 11
Orange County Public Schools
Aerial Photo – August 10, 2017 12
N
Orange County Public Schools
Aerial Photo – September 7, 2017 13
Orange County Public Schools
Tilt Panel RebarSlab on Grade Pour
14
Orange County Public Schools
Tilt Panel Erection
15
Orange County Public Schools
Steel Erection Roof Deck
16
Orange County Public Schools
Locker Room Pour Elevated Slabs
17
Orange County Public Schools
Exterior Painting
18
Questions & Answers
19