dpr 25042013 1of2
TRANSCRIPT
-
7/30/2019 DPR 25042013 1of2
1/1
Prepared by : Nasser Jamal. Page 1 0f 2Date : Thus 25/04/2013
Weather : 07.00 - 12,00 : Clear 13.00 - 18.00 : Clear
NO Work Description Area Target Previous Today Cumul've Remarks
A1 Unloading/Stringing Area A-B 41 38 38 waiting approval cold bends
2 Area B-C 61 57 0 57 Job Push pull in progress
3 Area C-D 10 10 10 Compeleted stringgin g4 Area D--E 41 41 41 Compeleted stringging
5 Area E---F 24 24 24 Compeleted stringging
6 Area F---G 44 39 39 waiting approval drawing
7 Area G---H 32 32 32 Waiting Road crossing drawing approval
8 Area H to PPA 65 60 60 waiting approval cold bends
TOTAL JOINT 318 301 301 Cumm 301 out of 318
B1 WELDING JOINT Area A-B 41 36 0 36 Remaining work ; 05 joints,waiting pipe bends.
2 Area B-C 61 56 0 56 Remaining work ; 05 joints, Job in progress
3 Area C-D 10 10 10 Completed
4 Area D--E 41 41 41 Completed
5 Area E---F 24 22 22 Remaining work ; 02 joints,at road crossing
6 Area F---G 44 36 36 Remaining work ; 08 joints,waiting pipe bends
7 Area G---H 32 30 30 Remaining work ; 02 joints,at road Crossing
8 Area H to PPA 65 53 53 Remaining work ; 12 joints,at road crossing & sand box
TOTAL JOINT 318 284 0 284 Cummulative : 284 out of 318 joints
C1 Radiography Area A-B 41 36 36
2 Area B-C 61 49 0 49
3 Area C-D 10 10 10
4 Area D--E 41 41 41
5 Area E---F 24 22 22
6 Area F---G 44 33 0 33
7 Area G---H 32 32 0 32 Note : Acc 266 jts out of 275 joints.
8 Area H to PPA 65 53 0 53
316 TOTAL JOINT 318 276 0 276 Cummulative 276 out of 318 joints,
DESCRIPTION AREA LENGHT PREV TODAY CUMUL Remarks
D1 COATING Area A-B 41 36 0 36 Remaining 05 jts,waiting pipe bends
2 Area B-C 61 45 0 45 Remaining 16 jts,waiting xray result
3 Area C-D 10 10 0 10 compeleted
4 Area D--E 41 41 0 41 compeleted
5 Area E---F 24 22 22 Remaining 02 jts, at road crossing
6 Area F---G 44 33 0 33 Remaining 11 jts,waiting pipe nends
7 Area G---H 32 29 0 29 Remaining 03 jts,waiting xray result
8 Area H to PPA 65 42 5 47 Remaining 18 jts,waiting xray result
318 258 5 263 note; done 263 out of 318
E1 METERING UNITS AREA 1 TOTAL PREV TODAY CUMUL Remarks
F1 CIVIL WORK AREA 1 0
G CONSTRUTINON AREA 1
H PIPING AREA 1
I INSTR & ELECTRIC AREA 1
Remarks
DESCRIPTION AREA UNITS PREV TODAY CUMUL
1 PIG LAUNCHER PLATFORM Area 2 01 unit 0 0 0
2 Install Pig Launcher Area 2 01 unit 0 0 0
3 Install PIPE RACK Area 2 15 unit 15 0 15 Erection done
4 Install 8"Pipe support Area 2 15 unit 15 0 15 done5 Install 8" p/L frm SDV to PL Area 2 8 jts 0 0 0
6 Install 6" Kicker Line Area 2 10 jts 0 1 1
7 Install 4" Vent Line Area 2 3 jts 0 0 0
8 Install 3" Drain Line Area 2 9 jts 0 0 0
9 Install 2"/1" IG supply Area 2 Lot 0 0 0
11 Install 6"out let Metering Area 2 6 jts 0 0 0
TODAY ACTIVITIES;
From 07.00- 12.00
From 13.00- 17.00
Radiography done 276 jts,out of 318 - Acc, 266 jts out of 318 jts.
Stringing,done 301 Lenghts out of 318 Lenght
Area 2/PPA/KRS ; Scaffolding work at Pipe rack area 1.
Stringing 6" Vent line to above pipe rack,in progress.
Fit up 6" Vent line at above pipe rack inprogress
Area C to B (push pull), stand by a waiting Xray Result.
Welding done 284 jts,out of 318 - Acc, 266 jts out of 318 jts.
Coating Repair at area jts H to PPA, -done 263 out of 318 jts.
i/p
i/p
DAILY ACTIVITY REPORT
In progress