dsm esco funding standard offer package standard product package presented by : clive nicosia...
TRANSCRIPT
DSM ESCO FUNDINGSTANDARD OFFER PACKAGESTANDARD PRODUCT PACKAGE
Presented by : Clive NicosiaDesignation : Energy Service Manager Eastern Region
Date : February 2011
2 2
Medupi
Financial & Economic Impact
Project Schedule
Project Summary
► Greenfields Project – Lephalale (Limpopo Province)
► 6 Unit Coal Fired Power Station
► Planned capacity 4,764MW
► Projected project cost to completion ~R125.5bn
► Estimated 95% impact on Lephalale town GDP
► ~ 70% contracts awarded
► Construction commenced March 2007
► First Unit planned to be handed over April 2012
► Subsequent Units at 8 month intervals thereafter
► Last Unit planned for handover during August 2015
Kusile
Financial & Economic Impact
Project Schedule
Project Summary
► Greenfields Project – Delmas (Mpumalanga Province)
► 6 Unit Coal Fired Power Station
► Planned capacity 4,800MW
► Projected project cost to completion ~R141.5bn
► Estimated 25% impact on Delmas town GDP
► ~ 41% contracts awarded
► Construction commenced Mid 2008
► First Unit planned to be handed over June 2014
► Subsequent Units at 8 month intervals thereafter
► Last Unit planned for handover during October 2017
Ingula
Financial & Economic Impact
Project Schedule
Project Summary
► Greenfields Project – Ladysmith (KwaZulu Natal Province)
► 4 Unit pumped storage power station
► Planned capacity 1,352MW
► Projected project cost to completion ~R21.8bn
► Estimated 1% impact on Ladysmith town GDP
► ~ 75% contracts awarded
► Construction commenced Mid 2006
► First Unit planned to be handed over January 2013
► Subsequent Units at 3 month intervals thereafter
► Last Unit planned for handover during November 2013
Build Programme Project Summaries: Medupi, Kusile & Ingula
SOURCE: Eskom Build Programme; 30 April 2010 Project Assurance Reports
3
Eskom Funding (1)
ESCo Standard Offer Standard Product
Turnaround time 6-18 months <1 month <1 week
Size Project > 1MW 50kW < Project<5MW 1kW < Projects < 100kW
Eskom Payment ValueIndividual project
calculationStandard value per kWh saved
(per technology)
Standard value per item calculated based on savings
potential
Contract priceCustomer & Eskom
(< NERSA benchmark)
Pre-determined price per technology
(Rebate Calculator and subject to NERSA guidelines)
Pre-determined price per technology
(subject to NERSA guidelines)
Payment mechanism Progress payments40% on implementation
20% pax3 (based on M&V)
100% on installation (based on pre-determined
“standard” savings)
Investment committee decision
Per project approvalBulk approval per technology (Technology List – TESCOT
approved)
Bulk approval per technologyIndividual calculation per item by
TESCOT
Procurement decisionPer project based on
submissionBulk approval for IC approved
programme
N/A(rebate paid as per delegation of
authority)
Legal agreement NECStandardised, simplified legal
agreement No legal contract
Commitment letter from client
4
ESCo Standard Offer Standard Product
Awarding of “contract”
Per project based on submission
“First come first serve basis” “First come first serve basis”
Conditions of legal contract
NEC(with negotiable conditions)
Standard SOP customised contract
No legal contractCommitment letter from client
Customer financial evaluation
Per project based on submission
Only for projects above R400k
N/A
Customer technical evaluation
Per project via IDM PEC based on submission
IDM PEC evaluation per project
Not applicable (based on pre-approved
technology list)
Major differenceProject based
(each submission is a project)Contract based
(bulk approval in principle)Contract based
(bulk approval in principle)
Eskom Funding (2)
DSM ESCO FUNDINGDSM ESCO FUNDING
• Appoint an Energy Services Company (ESCo) to identify opportunities, compile proposal for submission to Eskom DSM for funding, implement and maintain DSM project in the customer’s plant. Commercial entities may also, on the other hand, register a project directly with DSM.
• The ESCo must be registered on the DSM database before any project will be accepted.
• ESCos need to be technically competent and financially sustainable to enter into performance contracts and maintain projects over the long-term.
• Preliminary task are performed at no cost to the client.
• Letter of intent to be issued to the appointed ESCo.
Project EvaluationProject Evaluation
Eskom DSM will undertake:
• Technical evaluation of the project
• Financial evaluation of the project
• Prepare documentation and present to Eskom investment committee for approval
• Prepare documentation and present to Eskom Tender committee for approval
• DSM agreement and NEC placement
• Pre Measurements and Verification
• Eskom DSM evaluation lead time is up to 10 months
STANDARD OFFER PACKAGE
• Pre-determined rebate 0.34c/kWh for the delivery of verified energy savings
• Rebate shall be payable over a period of 3 years
• This does not replace the existing EEDSM process. The ESCo can therefore elect to propose a project using the normal EEDSM process or the Std Offer Process
• Applicable for Industrial & Commercial end users Reduce energy consumption between 6am and 10pm Monday to Friday only.
• This reduction must undergo M&V
• Energy reduced after 10pm and before 6am on weekdays and on weekends will not be considered towards the payment for energy reduction.
• The pre-approved technology that will be piloted for the std offer will be the replacement or retrofitting of old luminaries (fitting) lamps and inefficient ballasts to the efficient luminaries and efficient ballast's.
• The project developer shall ensure that the approved technology complies with all laws and regulations relating to the installation, working environment and lux levels
Requirements:
• Reduce energy consumption between 6am and 10pm Monday to Friday only.
• This reduction must undergo M&V
• Energy reduced after 10pm and before 6am on weekdays and on weekends will not be considered towards the payment for energy reduction.
• The pre-approved technology that will be piloted for the std offer will be the replacement or retrofitting of old luminaries (fitting) lamps and inefficient ballasts to the efficient luminaries and efficient ballast's.
• The project developer shall ensure that the approved technology complies with all laws and regulations relating to the installation, working environment and lux levels.
• This does not replace the existing EEDSM process. The ESCo can therefore elect to propose a project using the normal EEDSM process or the Std Offer Process
• Applicable for Industrial & Commercial end users
Performance Payment Example:
MAD - M&V 592000 kWh per annum
Rebate 34 c/kWh
Payment Term 3 years
Initial Purchase Price R 603,840.00
Initial Payment of 40% R 241,536.00
Performance Payment 1 - Year 1 R 120,768.00
Performance Payment 2 - Year 2 R 120,768.00
Performance Payment 3 - Year 3 R 120,768.00
Standard Product Package
Eskom pays customer a rebate based on standard technologies, pre-determined savings per load factor, post implementation and after disposal of old technologies
Savings and Eskom rebate per technology change will be pre-determined
Only DSM/IDM pre-approved technologies will be given consideration for participation
No formal contract – only signed customer commitment for sustainability
Limited Eskom Procurement involvement
Standard Product projects will ultimately be managed & monitored at regional level.
Energy Advisors and Energy Service Managers will promote & launch the Standard Product process
Key Principles
Energy saving projects will be undertaken by Energy Services Companies (ESCO’s) or Eskom Customers
M&V methodology will be determined and published by the Assurance & Forensic department
Standard Product is aimed at giving the Advisors more options to tackle the market.
Applicable to savings of 1kW to 100kW:
Min Project size:
Demand Savings > 1kW and
Energy Savings > 2MWh.
Load factor > 15%
Max Standard Product rebate: R750,000 per project site (single metered entity)
No splitting of projects
Lighting now, near future heat pumps, showers, insulation.
Capped at LF of 85
Finance: Rebate Calculation Mechanism
23-04-18 12
Input current
technology
Maximum value that could be
paid
Technology payment
factor(TPF)
System generated savings
Input number of units
System gives
approved DSM
options
Technology benchmark
Final value after
invoice & actual costs
assessed
System generated
Energy Advisor input
Note: Rebate limited to the least of = Benchmark x TPF x savings or Actual Project Costs.
Rebate limitations
• Maximum rebate to be paid to customer limited to:
• Least of:
• 1. Actual costs (Customer to provide proof of costs)
• 2. 85% X Technology Benchmark
• 3. TPF X Technology Benchmark
• TPF = Technology Payment Factor
• Rebate could be R/Mw or c/kwh based
IDM domestic heat pump rebate structure
100 L200L
Category 1Rebate = R 3,668Purchase Price = R 12,500
300L
500L400L
Category 2Rebate = R 4,320Purchase Price = R 16,000
100 L 500LHeat Pump tank Ranges
The rebate and purchase prices to remain unchanged until year 2013
Thank you!!
15