earned schedule: principles and practice alex davis earned ... · earned schedule: principles and...
TRANSCRIPT
Earned Schedule: Principles and Practice
Alex Davis
Earned Value SIG
The idea is to determine the
time at which the EV accrued
should have occurred.
…
$
5
? PV
? EV
Time Now
71 2 3 4 6 8 9 10
A
B
SV c
SV tES AT
Introduction
What is Earned Schedule?
– History and background
What are the benefits of using Earned Schedule?
How does Earned Schedule work?
What are the similarities and differences between
Earned Value and Earned Schedule?
How can Earned Schedule be integrated with other
Project Management techniques?
Sanitised examples:
Playing Devil‟s Advocate
Why do I need another project management tool?
I‟ve already got a link between cost and schedule!
Does this technique REALLY provide better decision
making?
I‟ve heard this technique is used on development
projects…but does it work for ongoing operations?
Are you saying that Earned Value doesn‟t work!?
It‟s good as a Project management technique
…however…
– „Classical‟ schedule indicators are not accurate for late finish projects
– Schedule performance analysis is limited in some areas
– Some EVM practitioners pay attention to Cost – not always the schedule
– EVM has, in some areas, become focused in financial management
– Indicators are not directly connected to deliverables
– EV is not required to be synchronous with the schedule
– EVM offers a limited decision-making guidance for project schedule control
Playing Devil‟s Advocate (2)
Earned Schedule – a brief history
The original phrase “Time is money” was first posed by Antiphon
– Greek writer and educator
– Around 430 BC
– “The most costly outlay is time”
This statement was ahead of its time!
In 2006, Dr. Steve Gumley, CEO Defence Materiel Organisation (Australia) stated…
“We need to maintain our attention on schedule delivery. Data tells us that since July 2003, real cost increase in projects accounted for less than 3 percent of the total cost growth. …Therefore, our problem is not cost, it is SCHEDULE.”
Earned Schedule – a brief history
Earned Schedule papers first published in USA
– in 2003
“Schedule is different”, Measurable News
Concept was verified with actual project data
Continued development from 2003 to present
Benefits of using Earned Schedule (1)
You only need PV, EV and AT to perform calculations!
Improves decision making – part of Project, Programme
and Enterprise Management toolset
Integrates and supports risk management activities
Connects EVM to the project schedule
Project Managers have a schedule analysis tool that
improves the confidence in forecasting delivery dates
Adds to trend analysis
Benefits of using Earned Schedule (2)
ES can be applied to any level of the WBS, to include task groupings such as the Critical Path
– Requires creating PMB for the area of interest
– EV for the area of interest is used to determine its ES
Enables comparison of forecasts, total project duration (TP) to Critical Path (CP) duration
– Desired result: forecasts are equal
– When TP forecast > CP forecast, CP has changed
– When CP > TP, possibility of future problems
Benefits of using Earned Schedule (3)
Earned Schedule works!
How do we know?
Evidence from a number of projects
IEAC(t) & SPI(t) studies by K. Henderson, Dr. Vanhoucke & S. Vandevoorde (2003 – present)– Henderson & Vandevoorde validated ES concept with real data
– Using simulation Vanhoucke & Vandevoorde showed ES to be a better schedule predictor than other EVM-based methods
“The results ..confirm ..that the ES method outperforms, on average, the other forecasting methods” - Vanhoucke & Vandevoorde
Takes Earned Value Management into a new dimension
Why use Earned Schedule? Schedule Variance (SV) and Schedule Performance
Indicator (SPI) behave erratically – especially for projects behind schedule
SPI improves and concludes at 1.00 at end of project
Why is this?
EV=BAC at completion
PV=BAC at completion
Hence SPI(£)=1 and SV(£) = 0
Classical Schedule Variance is measured in money –
not time!
Comparison of Schedule Variances
Commercial IT Infrastructure Expansion Project Phase 1
Cost and Schedule Variancesat Project Projection: Week Starting 15th July xx
-160
-140
-120
-100
-80
-60
-40
-20
0
20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Elapsed Weeks
Do
lla
rs (
,00
0)
-16
-14
-12
-10
-8
-6
-4
-2
0
2
We
ek
s
CV cum SV cum Target SV & CV SV (t) cum
Copyright Lipke 2008
Earned Schedule Calculation ES (cumulative) is the:
Number of complete PV time increments EV equals or exceeds PV + the fraction of the incomplete PV increment
ES = C + I where:
C = number of time increments for EV PV (BCWP BCWS)
I = (EV – PVC) / (PVC+1 – PVC)
EVM & ES Duration Forecasting
£
5 71 2 3 4 6 8 9 10
Earned
Schedule
Time Periods
PVcumEVcum
Actual
Time.
Time based schedule performance efficiency: SPI(t) = ES / AT
Copyright Lipke 2008
SV c
SVt
The ES idea is to determine the
time at which the EV accrued
should have occurred
Calculating the Increment I
MONEY (£)
5 6
Time Periods
Copyright Lipke 2008
PV C+1PV C
EV – PV C
PV C+1 – PV C
I - expressed as a fraction of time
Calculating Earned Schedule (1)
Denominator is difference between
two successive PV data points
1st value EV < PV
Variances – which would you believe?Cost & Schedule Variances
-450
-400
-350
-300
-250
-200
-150
-100
-50
0
Time
Mo
ney (
£)
-3.5000
-3.0000
-2.5000
-2.0000
-1.5000
-1.0000
-0.5000
0.0000
SV
(t)
mo
nth
s
SV(£) cum
target SV
SV(t) cum
Note how the “Classical”
SV tends to zero!
Earned Schedule variance
tells a different story!
Variances – which would you believe?Cost & Schedule Variances
-450
-400
-350
-300
-250
-200
-150
-100
-50
0
Time
Mo
ney (
£)
-4.0000
-2.0000
0.0000
2.0000
4.0000
6.0000
8.0000
10.0000
12.0000
14.0000
16.0000
18.0000
SV
(t)
mo
nth
s SV(£) cum
target SV
SV(t) cum
IECD(t)
Delivery Date
Independent Estimate At
Complete (IEAC)
Comparison between EV and ES (1)
Status Earned Value (EV) Earned Schedule (ES)
Actual Costs (AC) Actual Time (AT)
Schedule Variance SV SV(t)
Schedule Performance
Indicator
SPI SPI(t)
Future Work Budgeted Cost for Work
Remaining (BCWR)
Planned Duration for Work
Remaining (PDWR)
Estimate At Complete EAC
(supplier)/(customer)
EAC(t)
Independent EAC
(IEAC)
IEAC(t)
To Complete
Performance Index
TCPI TSPI
Comparison between EV and ES (2)
Status Earned Value (EV) Earned Schedule (ES)
Schedule Variance SV = EV-PV SV(t) = ES-AT
Schedule Performance
Indicator
SPI = EV/PV SPI(t) = ES/AT
Future Work BCWR = BAC-EVcum PDWR= PD-EScum
Estimate At Complete EAC1=AC+(BAC-EV)/CPI EAC(t) = PD/SPI(t)
EAC(t)(2) = AT+(PD-ES)/SPI(t)
To Complete
Performance Index
TCPI = (BAC-EV cum)/(EAC-
ACcum)
TSPI = (PD-ES)/(PD-AT)
TSPI= (PD-ES)/(ED-AT)
Management Report using ESTo Complete Performance Index (time)
The change in the level of efficiency
needed to meet the milestone completion
date as contracted
This is the estimated
completion date
IF PERFORMANCE DOES
NOT CHANGE
This is the milestone
completion date as
contracted
SPI and SPI(t) trend lines
Milestone tracking – ES and PM‟s estimates
Independent Estimate of
Completion Date – Earned
Schedule
Independent Estimate of
Completion Date – PM‟s
estimate
Earned Schedule & RiskStatistical Prediction
from Earned
Schedule
P10, P50 and P90
dates from Schedule
Risk Analysis
Earned Schedule & Benefits – an
example A new auto engine is designed
One measurable benefit - 10% fuel saved for each mile travelled
The customer has 100 vehicles and wishes to fit the new engine to the entire fleet (over time)
As part of the business case, each new engine will be measured for the 1st 1000 miles
The average fuel saving per mile can be calculated against the new running cost
The fleet manager can also calculate the Return On Investment (ROI)
27
ES and Benefits - terminology
Status Earned Value (EV) Benefits Value
Planned Value (PV) Planned Benefit (PB)
Earned Value (EV) Earned Benefit (EB)
Actual Cost (AC) Actual Benefits (AB)
Actual Running Costs (ARC)
Earned Schedule and Benefits
Project planned to
finish here
Project
actually
finished here
Planned
Benefit
delivery starts
here
Earned Benefits – accruals and reverse
logic? When can you measure Actual Benefits?
When you actually measure them?
Or do you accrue them and reconcile later?
And another thing…
CPI = EV/AC
Applying the same to benefits
Benefits CPI (BCPI) = EB/AB
In this example BCPI = 1.11 (unfavourable!?)
Schedule Adherence
Copyright Lipke 2008
Figure 3. Earned Schedule - Bridges EVM to Schedule (Actual)
£
Time
PV
BAC
PD
EV
ES AT
SV(t)
1
3
2
4
5
6
7
8Introduces the use of
the “p-factor”
Potential rework?
ES helps identify
SCHEDULE
ADHERENCE issues
Real Data Results
0.8
0.9
1.0
1.1
1.2
10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percent Complete
Ind
ex V
alu
e
CPI SPI(t) P- Factor P Curve Fit
SPI(t) is good ~0.98CPI is good ~1.05
P @ 20% ~0.93 – high early
P increases to 1.0
ES for short duration projects
ES has been found to give misleading
answers in specific situations
For short duration projects where either
down-time or work-stop are scheduled
Thank you to… Walt Lipke and Kym Henderson
– for use of Earned Schedule training material
The Protected Mobility Team
– For use of sanitized data
Energy and persistence conquer all things
Benjamin Franklin
Available Resources
PMI-Sydney http://sydney.pmichapters-australia.org.au/
– Repository for ES Papers and Presentations
Earned Schedule Website
http://www.earnedschedule.com/
– Established February 2006
– Contains News, Papers, Presentations, ES Terminology, ES Calculators
– Identifies Contacts & Training to assist with application
Wikipedia references Earned Schedule
http://en.wikipedia.org/wiki/Earned_Schedule