earned value

65
You too, can do Earned Value Management! Presented by: Chance Reichel, PMP Boston University Corporate Education Center Session # ADV11

Upload: ntobza

Post on 19-Oct-2015

40 views

Category:

Documents


0 download

DESCRIPTION

earned value in project management

TRANSCRIPT

  • You too, can do Earned Value Management!

    Presented by: Chance Reichel, PMPBoston University

    Corporate Education CenterSession # ADV11

  • 2Situation: I budgeted 5 widgets at 100 hrs per widget.At the end of the year, 400 hrs had been expended.

    Budget vs. Actual Variance

    500 400 100

    GREAT! I'm 100 hrsunder budget!

    Question: Whats wrong with this picture?

    Earned Value Example

  • 3Actual cost is not an indication of work progress, but only an indicator of hours/money spent.

    Ive spent 400 hrs , so Ive accomplished 400 hrs of work?

    0

    100

    200

    300

    400

    500

    600

    J F M A M J J A S O N D

    Time

    H

    o

    u

    r

    s

    Budget Plan

    Actual Cost

    100 hrs Under-run

    Traditional Cost Management Method

  • 4Budget vs. Actual Variance

    500 400 100

    Earned Value adds another dimension to traditional cost management methods

    Earned Value

    Earned Value Management

  • 5Earned Value: an objective measure of how much work has been accomplished

    Budget Plan Earned Value Actual500 300 400

    Situation: I plan to build 5 widgets thisyear. Each widget should take 100 hrs.I will measure earned value based on the number of widgets completed.

    Year End...1

    23

    (3 Widgets * 100 hrs)

    Earned Value Management

    3 widgets completed.

  • 6Budget Plan Earned Value Actual500 hrs 300 hrs 400 hrs

    Schedule CostVariance Variance

    (200) (100)

    Oh boy! I better figure out whatis going on. I've got 200 hrs worth ofwork to catch up on, and I've already overspent by 100 hrs.

    Using Earned Value

  • 7Earned Value Management is an approach to understanding and assessing what a contractor (or Government Activity) is achieving with program dollars.

    Earned Value ManagementBook Definition

  • 8An objective measure of how much work has been accomplished based on the plannedvalue, or:

    What we got for what we spent!

    Earned Value ManagementPractical Definition

  • 9Earned Value Management Is:

    A uniform unit of measure

    A consistent method of analysis

    A basis for cost performance assessment

  • 10

    Earned Value Analysis: What is it?

    Method for comparing value of planned work to value of performed work

    The most common method of performance measurement

    Integrates scope, cost, schedule

  • 11

    EVMEarned Value Management is intended to provide data from a contractors management system to the government in standard data elements that

    Relate time-phased budgets to contract tasks

    Integrate cost, schedule, and technical performance

    Indicate work progress objectively

    Are valid, timely and auditable

    Are from the internal system the contractor uses to manage

    Are at a practical level of summarization

  • 12

    Integrating Project Influences

    Project manager must integrate all aspects of the project to manage the interaction of time, cost, and scope and quality constraints to be able to factor Earned Value correctly!

    ProjectResources

    Time Cost

    Scope and Quality

    Triple Constraint Model

  • 13

    The EV Process

    Plan the Work

    Work the Plan

    ExternalChanges

    Collect Results

    Define the Work

    Analyze Deviations

    TakeCorrective Action

    TakeCorrective Action

    Measure Performance

    Change Control

  • 14

    Definition: Project Scope Statement

    The narrative description of the project scope, including major deliverables, project

    objectives, project assumptions, project constraints, and a statement of work, that provides a documented basis for making

    future project decisions and for confirming or developing a common understanding of project scope among the stakeholders.

    PMBOK Guide, Third Edition, Glossary

  • 15

    Components of the Project Scope Statement

    Requirements Objectives Product Description Boundaries Major Deliverables Acceptance Criteria Constraints Assumptions Initial Project

    Organization

    Initial Defined Risks Schedule Milestones Fund Limitations Cost Estimate Configuration Mgmt.

    Requirements Specifications Approval Requirements

  • 16

    Definition: Work Breakdown Structure (WBS)

    A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project

    objectives and create the required deliverables. It organizes and defines the total

    scope of the project. Each descending level represents an increasingly detailed definition

    of the project work.

    PMBOK Guide, Third Edition, Glossary

  • 17

    Best Management Practice:Steps for Project Decomposition

    Step 1 Identify and record the Project Goal Usually the name of the project

    Step 2 Identify Major Deliverables that represent large areas of project work

    Step 3 Can adequate estimates of both labor and cost resources requirements needed to complete the deliverables be developed?

    Step 4 Continue to Decompose the work so that adequate estimates can be developed

    Step 5 Verify correctness and project suitability

  • 18

    Work Breakdown Structure

    Site Preparation

    Site and Buildings

    PlantBuildings

    Building #1

    Foundation and Substructure

    Building #2

    Technical Support

    Equipment Data

    Superstructureand Finishing

    Energy Laboratory

    06.1.2.1.106.1.2.1.2

    06.1.2.1 06.1.2.2

    06.1.1

    06.1.2

    06.1.3

    06.106.2 06.3

    06.0

    WBS Level0

    1

    2

    4

    5

    6

  • 19

    Detail planning at levels where work is performed allowsmanagements attention to be directed to areas where significant problems are indicated.

    Cost Account 1111MCost Variance (100)Sch Var (200)

    (250)

    (200)

    (150)

    (100)

    (50)

    0

    50Schedule

    Cost

    Benefits of Using Earned Value

  • 20

    An Iterative 3-Step Process

    10040

    60

    1525

    3030

    3. Allocate Budgets

    1. Scope the Work

    2. Schedule the Work $ PM Baseline

    Contract Budget Base

    Time

    Establish the Performance Measurement Baseline

  • 21

    Statement of Work

    EVM Planning Terms

    breaks down into a:

  • 22

    breaks down into a:

    where the work is defined by a:

    Statement of Work

    Work Breakdown Structure

    EVM Planning Terms

  • 23

    breaks down into a:

    where the work is defined by a:

    Who is responsible for Work Breakdown Structure work is identified in a:

    Statement of Work

    Work Breakdown Structure

    Work Breakdown Structure Dictionary

    EVM Planning Terms

  • 24

    breaks down into a:

    where the work is defined by a:

    Who is responsible for Work Breakdown Structure work is identified in a:

    that identifies where the Cost of Work Breakdown StructureLabor & Material will be collected, which is a:

    Statement of Work

    Work Breakdown Structure

    Work Breakdown Structure Dictionary

    Responsibility Assignment Matrix

    EVM Planning Terms

  • 25

    breaks down into a:

    where the work is defined by a:

    Who is responsible for Work Breakdown Structure work is identified in a:

    that identifies where the Cost of Work Breakdown StructureLabor & Material will be collected, which is a:

    However, where the work is actually performed is usually reflected in a:

    Statement of Work

    Work Breakdown Structure

    Work Breakdown Structure Dictionary

    Responsibility Assignment Matrix

    Cost Account

    EVM Planning Terms

  • 26

    breaks down into a:

    where the work is defined by a:

    Who is responsible for Work Breakdown Structure work is identified in a:

    that identifies where the Cost of Work Breakdown StructureLabor & Material will be collected, which is a:

    However, where the work is actually performed is usually reflected in a:

    which is where the work is scheduled, performed, and measured.

    Statement of Work

    Work Breakdown Structure

    Work Breakdown Structure Dictionary

    Responsibility Assignment Matrix

    Cost Account

    Work Package

    EVM Planning Terms

  • 27

    Cost (Control) Account

    Work Packages

    Work Breakdown Structure (WBS)

    MDSS

    Seminar

    Series

    1.0

    Session 1

    2.0

    Session 2

    3.0

    Session 3

    4.0

    Project Management

    1.1

    Seminar Development

    1.2

    SeminarDelivery

    1.1.1

    Existing CoursesSurvey

    1.1.2

    Course Objectives/

    Concepts

    1.1.3

    CourseMaterials

    1.1.3.1

    Slides

    1.1.3.2

    Narratives

    1.1.3.3

    Case Studies

    1.1.3.4

    Exercises

  • 28

    1.1.2Course Outline/Objectives

    1.1.1Existing Course Survey

    1.1.3Course Materials

    1.1Seminar Development

    1.2Seminar Delivery

    1.0Session 1

    2.0Session 2

    3.0Session 3

    MDSSSeminarSeries

    Cost (Control) Accounts

    WBSOBSPresident

    VP Classroom

    VP Web Based

    VP Consulting

    ISD Systems

    Teaching Staff

    Design/Graphics

    Responsible Organizations

    Responsibility Assignment Matrix

  • 29

    RAM Used for Resource Allocation

    ISD Systems Teaching Staff Design/ Graphics

    Total

    Outline Objectives/ Concepts

    $1,400 $1,400

    Research Existing Courses

    $6,000 $6,000

    Prepare Materials $5,000 $5,000

    Total

    $1,400 $6,000 $5,000 $12,400

  • 30

    The Cost or Control AccountA Key Management Control Point

    Specific functional responsibility

    Specific WBS responsibility

    Work planning and assignment

    Performance measurement

    Cost collection

    Variance analysis

    Corrective action

    Basis of data summarization

    BUDGET LEDGER

    MASTER SCHEDULE

    GENERAL WORKAUTHORIZATION

    CONTRACT

    Control AccountWBS # ______________ ORG # ______________

    TASK DESCRIPTION________________________

    SCHEDULE _______________________________

    TOTAL BUDGET ________________

    WORK PACKAGEWP # ________ ORG # __

    DESCRIPTION ______

    SCHEDULE ____________

    BUDGET _______________

  • 31

    Work PackagesDetailed, short-span tasks or material items required to accomplish the CA objectives, typically in the near term.

    Task 1Task 2

    Task 4Task 5

    Task 3Work Packages

    Planning Packages

    Planning PackagesFuture work that has not been detail planned as work packages. They are always scheduled to occur in the future.

    Cost (Control) Account Elements

  • 32

    Three Types of Work Discrete effort

    Specific end product or result Apportioned effort

    Factored effort directly related to discrete tasks (e.g., quality control, inspection)

    Dependent on other work Level of effort

    No final product or result (e.g., liaison, support activities, program management)

    Measure performance with the passage of time

  • 33

    ; X/Y percent0/10025/7540/6050/50

    ; Milestone weights

    ; Milestone weights withpercent complete

    ; Percent CompleteSubjective estimateObjective indicators

    ; Equivalent units

    Discrete Effort

  • 34

    Earned Value for Inspection = 17% * Earned Value for Manufacturing

    Apportioned Effort

    Inspection runs 17% of manufacturing For each manufacturing work package,

    construct an inspection work package Compute earned value for each inspection

    work package

  • 35

    LOE Work Packages must be kept to an absolute minimum

    Level of Effort (LOE)

    Program management will continue for the life of the program

    Discrete work packages dont make sense Apportionment isnt necessary (we already know how

    many people will be charging time) Create level of effort work packages that receive

    automatic earned value each month

  • 36

    CONTRACTPRICE

    CONTRACTBUDGET BASE

    PROFITS ANDFEES

    MANAGEMENTRESERVE

    PERFORMANCEMEASUREMENT

    BASELINE

    WITHHELDFOR

    UNKNOWNS

    UNDISTRIBUTEDBUDGET

    DISTRIBUTED(control accounts)

    WITHHELD FORKNOWN EFFORT

    AUTHORIZED,UNPRICED

    Contract Budget Baseline

  • 37

    Data Element Term AcronymScheduled Work Budgeted Cost for Work Scheduled BCWS

    Earned Value Budgeted Cost for Work Performed BCWP

    Actuals Actual Cost of Work Performed ACWP

    Authorized Work Budget At Completion BAC

    Forecasted Cost Estimate At Completion EAC

    Work Variance Schedule Variance SV

    Cost Variance Cost Variance CV

    Completion Variance Variance At Completion VAC

    EVM Performance Measurement

  • 38

    EVM Performance Measurement

    Budgeted Cost of Work Scheduled (BCWS) The sum of the time-phased budgets

    established for all effort (including in-process work) scheduled to be accomplished within a given time period

  • 39

    TIME

    $

    BUDGET

    PV

    ContractComplete

    EVM Performance Measurement

  • 40

    EVM Performance Measurement

    Budgeted Cost of Work Performed (BCWP)

    The sum of the time-phased budgets for work completed during a specified time period

    BCWP is the value of the work accomplished

    BCWP is also known as EARNED VALUE

  • 41TIME

    $

    BUDGET

    BCWP

    SVBC

    WS

    ContractComplete

    EVM Performance Measurement

  • 42

    EVM Performance Measurement

    Actual Cost of Work Performed (ACWP) The costs actually incurred and recorded in accomplishing

    the work performed (BCWP) within a given time period Labor Material (subcontractor/vendor) Other, computer costs, etc. Indirect Costs

  • 43

    TIME

    $

    BUDGET

    BCWP

    CVBCWS

    ACWP

    ContractComplete

    EVM Performance Measurement

  • 44

    EVM Performance Measurement

    Budget At Completion (BAC) The budgetary goal (excluding MR) for doing

    authorized work; this includes the value of all work packages, planning packages, control accounts and Undistributed Budget

    Note: Total BAC at the contract level including MR = Contract Budget Baseline

  • 45

    EVM Performance Measurement

    Estimate At Completion (EAC) Actual direct costs + indirect costs allocable

    to the contract + the estimate of costs (direct and indirect) for authorized work remaining

    Often quite subjective Usually optimistic

  • 46

    TIME

    $

    BUDGET

    BCWP

    CVBC

    WS

    ACWP

    ContractComplete

    EVM Performance Measurement

    SV

    ESTIMAT

    E

    VAC

  • 47

    EVM Performance Measurement

    Management Reserve (MR) An amount of the total allocated budget withheld

    for management control purposes, rather than designated for the accomplishment of a specific task or set of tasks

    KEY: There is no scope of work associated with management reserve budget

  • 48

    EVM Performance Measurement

    Undistributed Budget (UB) Budget applicable to contract effort which has not

    yet been identified to CWBS elements at or below the lowest level of reporting

    KEY: Only used for the effort associated with contractual changes

  • 49

    Earned Value Variances and Indices

    Schedule Variance (SV)

    SV = EV PV Positive is good, be careful!

    SV% = SV/PV * 100 Positive is good

    SPI = EV/PV 1.00 or greater is good

    Good means on or ahead of schedule

  • 50

    Earned Value Variances and Indices (2)

    Cost Variance (CV)

    CV = EV - AC Positive is good, be careful!

    CV % = CV/EV * 100 Positive is good

    CPI = EV/AC 1.00 or greater is good

    Good means on or under budget

  • 51

    Graphic Performance Report

    Time

    Progress

    PV

    AC

    Cost Variance

    Update Date

    ScheduleVariance

    EV

  • 52

    Cost Variance (CV) = Earned Value (BCWP) - Actual Costs (ACWP)

    Schedule Variance (SV) = Earned Value (BCWP) - Budget Plan (BCWS)

    Efficiency Factors:

    Cost Performance Index (CPI) = Earned Value (BCWP)Actual Costs(ACWP)

    Schedule Performance Index (SPI) = Earned Value (BCWP)Budget Plan (BCWS)

    Percent Complete = Earned Value (BCWP)Budget At Completion (BAC)

    EVM Performance Measures

  • 53

    EAC = (BAC-BCWP) + ACWPPF*

    In English: The estimate at completion takes the remaining budget, applies the performance factor, and adds the actual cost spent to date.

    Basically, this calculation assumes that the indices used to develop the performance factor will remain constant for the remainder of the program.

    *Performance Factor

    EVMS The Estimate at Completion (EAC)

  • 54

    EAC = (BAC-BCWP) + ACWPPF

    Assume:BAC =1,000,000

    BCWP = 200,000

    BCWS = 225,000

    ACWP = 250,000

    Compute an Estimate at Completion using the CPI.

    Earned Value Quiz #2The Estimate at Completion (EAC)

  • 55

    EAC = (BAC-BCWP) + ACWPPF

    Assume:BAC =1,000,000

    BCWP = 200,000

    BCWS = 225,000

    ACWP = 250,000

    Compute an Estimate at Completion using the CPI.

    Earned Value Quiz #2The Estimate at Completion (EAC)

    EAC = (1,000,000 200,000) + 250,000CPI 0.8

    EAC = 1,250,000.

  • 56

    EAC Development Process Compute run out (Cum CPI formula) Evaluate CPI trends Examine differences between budget and network

    targets Evaluate actual manning against base plan Examine progress against base operating plan Evaluate impact of cost reduction initiatives Identify and quantify known engineering/production issues Examine to go performance trends on similar projects at

    similar points

  • 57

    Survey says Over 800 military programs show that NO program has ever

    improved performance better than the following EAC calculation:

    EAC = BACCPI

    at 15% complete point in program.

    No one pays enough attention in theearly stages!

  • 58

    The To Complete Performance Index (TCPI)

    Measures the efficiency necessary to achieve contractor expected final cost

    Formula is based on contractors EAC Contrasted with CPI, the TCPI indicates what change is

    required Provides a basis for exploring contractors basis for his

    EAC Permits assessment of contractors ability to achieve EAC

  • 59

    TCPI Formula

    Ratio of Work Remaining to Cost Remaining Work Remaining = BAC-BCWP Cost Remaining = Contractor EAC-ACWP

    TCPI = BAC-BCWPEAC-ACWP

  • 60

    Graphing Techniques

    Dollars In M

    illions

    Estimates at Completion MEGA HERZ ELEC & VEN F04695-86-C-0050 RDPR FPI

    Element: 3600 Name: PCC

    BACLRECUM CPI

    1992APR MAY JUN JUL AUG SEP OCT NOV DEC

    1993JAN

    5.0

    6.0

    7.0

    8.0

    5.1 5.4 5.1

    5.1 5.4 5.7

    5.1 5.4 5.9

    5.1 5.4 6.0

    5.1 5.5 6.3

    5.1 5.5 5.8

    5.1 5.5 6.5

    5.5 5.7 7.6

    5.5 5.7 6.8

    5.8 6.0 6.8

    MEGA HERZ ELEC & VEN Cost/Schedule VarianceF04695-86-C-0050 MOH-2 RDPR FPI POP: 01 MAR 1992 - 15 SEP 1993

    Percent of D

    ollars

    COST VARIANCESCHEDULE VARIANCE

    1992MAY JUN JUL AUG SEP OCT NOV DEC

    1993JAN

    -30.0

    -20.0

    -10.0

    0.0

    10.0

    20.0

    30.0

    Cost Drivers, Cause

    Dollars In MillionsBCWSBCWPACWP

    CVSV

    0.3 0.2 0.2 0.0 -0.1

    0.6 0.5 0.5 -0.0 -0.1

    1.0 0.9 0.9 -0.0 -0.1

    1.4 1.4 1.5 -0.1 -0.0

    2.2 2.2 2.2 0.0 -0.0

    2.5 2.7 3.0 -0.3 0.2

    4.2 3.8 4.2 -0.5 -0.4

    5.6 5.3 5.6 -0.3 -0.3

    7.3 6.9 7.3 -0.5 -0.4

    At CompletionKTR PO

    20.8 20.8

    20.8 20.8 20.8 23.0 0.0 -2.2

    PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0CURRENT FUNDING: 10.0

    PO EPC: 24.0PROJ FUNDING: 23.0

    AS OF: JAN 93OPR: MR B. TECH

    PROGRAM: Mohawk Vehicle

    0%

    -11%-7%-6%

    Overall cost and schedule trend

    EAC realism

    Graphs show overall trend...are you getting better,

    or worse?

    Graphs show overall trend...are you getting better,

    or worse?

  • 61

    Earned Value Management5 Basic Guidelines

    Organize the project team and the scope of work, using a work breakdown structure. Each task should have a single WBS number and organizational code.

    Schedule the tasks in a logical manner so that lower level schedule elements support subsequent elements and the top level milestones.

    Allocate the total budget resources to time-phased control accounts.

    Establish objective means for measuring work accomplishment. Budget should be earned in the same way that it was planned.

    Control the project by analyzing cost and performance variances,assessing final costs, developing corrective actions, and controlling changes to the integrated baseline.

  • 62

    Earned Value ManagementThe Bottom Line(s)

    EVM is a vital project management tool.

    EVM basics can and should be used on projects of any size.

    Constant streamlining is needed to keep focus on effective use (not just reporting).

  • 63

    EVM Home Page = http://acc.dau.mil/evmhttp://www.dcma.mil = One BookDAU POC: (703) 805-2851 (DSN 655)

    eMail Address: [email protected] Feb 2004

    TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrunTAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTBBAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control

    scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CAPP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;

    may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMALRE Latest Revised Estimate Ktrs EAC or EACKtrSLPP Summary Level Planning Package Far-term activities not yet defined into CAsTCPI To Complete Performance Index Efficiency needed from time now to achieve an EAC

    EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition Guidebook

    MANAGEMENT REQUIREMENTS: Select pair of Contract Clauses based on cost, risk, criticality:EVMS EIA-748 Management System Validated as Consistent with EIA-748 Standard at detailed level

    Non-FFP contracts / agreements for R&D > $73M; & Proc or O&M > $315M (CY00$)Cost/Schedule Status Report (C/SSR) Management System not required to meet EIA-748 Standard;

    Non-FFP contracts / agreements > $6.3M (CY00$) & > 12 months durationIntegrated Baseline Review (IBR) Mandatory for both EVMS & C/SSR within 6 months of Contract Award

    REPORT REQUIREMENTS: Tailor Data Requirements via CDRL, Select One:Cost Performance Report = DI-MGMT-81466 = Formats 1-5 (WBS, Organization, Baseline, Staffing, & Explanations)

    CPR is Mandatory for EVMS EIA-748 contracts & optional for C/SSR contracts Cost/Schedule Status Report = DI-MGMT-81467 = 2 Formats (WBS & Explanations) or Tailored CPR

    Management Reserve

    Work Packages Planning Packages

    OVERRUN AUW

    Control Accounts

    NCC

    UndistributedBudget

    OTB CBB

    TAB Profit / Fees

    PMB

    Summary Level Planning Packages

    Contract PriceEarned Value ManagementGold CardGold Card

    Defense Acquisition University

    VARIANCES Favorable is Positive, Unfavorable is NegativeCost Variance CV = BCWP ACWP CV % = (CV / BCWP) *100 Schedule Variance SV = BCWP BCWS SV % = (SV / BCWS) * 100Variance at Completion VAC = BAC EAC

    PERFORMANCE INDICES Favorable is > 1.0, Unfavorable is < 1.0Cost Efficiency CPI = BCWP / ACWPSchedule Efficiency SPI = BCWP / BCWS

    OVERALL STATUS% Schedule = (BCWSCUM / BAC) * 100% Complete = (BCWPCUM / BAC) * 100% Spent = (ACWPCUM / BAC) * 100ESTIMATE AT COMPLETION #EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]EACCPI = ACWPCUM + [(BAC BCWPCUM) / CPICUM ] = BAC / CPICUMEACComposite = ACWPCUM + [(BAC BCWPCUM) / (CPICUM * SPICUM)]

    TO COMPLETE PERFORMANCE INDEX (TCPI) #TCPIEAC = Work Remaining / Cost Remaining = (BAC BCWPCUM) / (EAC ACWPCUM)

    # To Determine Either TCPI or EAC; You May Replace BAC with TAB

    Management Reserve

    Cost Variance

    Schedule Variance

    ACWP

    BCWP

    BCWS

    $

    EAC

    TimeNow

    Completion Date

    PMB

    TABBAC

    time

  • 64

    In Summary: The EV Process

    Plan the Work

    Work the Plan

    ExternalChanges

    Collect Results

    Define the Work

    Analyze Deviations

    TakeCorrective Action

    TakeCorrective Action

    Measure Performance

    Change Control

  • 65

    Contact Information Name: Chance Reichel, PMP Company: Boston University Corporate

    Education Center Phone

    Contact 1(800) BUTRAIN

    Email [email protected]

    Session # ADV11 : You Too Can Do Earned Value Management