economic analysis (1)
DESCRIPTION
This is a important file for econimistTRANSCRIPT
ECONOMIC ANALYSIS
This chapter is on analyzing the economic feasibility of the project. The key factor of
designing a chemical plant is to maximize profits of the company. Therefore it is vital to
make sure that there will be profits generated and that the project won’t be running at a
loss. Reaching the break even in a short period is critical as it is less risky for investors to
invest and to gain a good profit. Identifying the capital cost, the total revenue and total cost
of the project throughout a time period will lead us in concluding whether this project is
viable or not.
There are numerous cost categories which need to be considered. First comes the capital
cost. It is estimated a construction period of 2 years for this plant. Then estimates for setting
up costs and all the operating costs are identified. The pricing for equipment, raw material
and the final product are in USD $. These figures were converted into LKR by using an
exchange rate of 134.04.
Since there are many aspects to be considered the investment decision cannot be made
based on one economic indicator. Various aspects need to be considered before making the
final decision. The economic indicators used to evaluate this project are the Simple Payback
Time, Return on Investment (ROR), Net Present Value (NPV), and the Internal Rate of Return
(IRR). These different tools have their own advantages and drawbacks. Therefore every
calculation needs to be analyzed accordingly before deciding to take up the investment
decision or not.
Capital investment
The capital investment is the initial cost which is incurred to start up the plant. This is a one
off cost which needs to be recovered from the profits earned during the production process.
This will be distributed among the 2 years of construction of the project. The capital
investment comprises of fixed costs and working capital components
1. Fixed costs
The fixed capital costs can be divided into direct costs and indirect costs.
Type of direct costs Value
Land (70,000/perch * 220perches) 15,400,000
Site Preparation (1.5% of land) 231,000
Buildings and structures 25,000,000
Equipment cost 26,875,020
Piping & fittings 4600000
Installation and wiring (10% of equipment cost)
Total Direct Capital Costs (DCC)
Indirect Costs
Design & Engineering (20% of DCC) 16997117
Contractors fees (5% of DCC) 4249279
Contingency Allowance (1% of DCC) 849856
Total Indirect Capital Costs
Total Fixed Capital Cost
Total Equipment Cost in LKR ($/LKR = 134.04) = 295,000*134.04 = LKR 39,332,350
1. Working capital
Equipment Unit cost $ No. of units Cost $
Feed drum 20000 1 20000
Vapourizer 5000 1 5000
Fired heater 6000 1 6000
Tubular Flow Reactor 16000 1 16000
Furnace 6000 1 6000
Scrubber 10000 1 10000
Cooler 6000 1 6000
Condenser 7500 1 7500
Flash Distillation Column 25000 1 25000
Distillation column 65000 2 130000
Other Equipment 9000
Total Equipment Cost 200500
Working capital is the additional investment needed, over and above the fixed capital, to start
the plant up and operate it to the point when income is earned. It includes the following
components;
1. Start-up.
2. Initial catalyst charges.
3. Raw materials and intermediates in the process.
4. Finished product inventories.
5. Funds to cover outstanding accounts from customers.
Most of the working capital is recovered at the end of the project. The total investment
needed for a project is the sum of the fixed and working capital. The working capital
requirement for a chemical plant is generally 12% of the fixed capital cost.
Fixed Capital Cost (FCC)
Working Capital Cost (12% of FCC)
Total Capital Cost
*The construction period of the plant is estimated to be 2 years. The total capital cost will be
distributed among these 2 years of construction.
Year Capital Cost
0 Land and Site preparation
1 Buildings and Structures, Design and Engineering, Contractors
Fees
2 Equipments, Piping and Fittings, Installation and wiring,
Contingency Allowance, Working Capital