economic level of leakage (ell) - fondazione amga · 1 iwa water loss task force visit italy genova...
TRANSCRIPT
1IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Conferenze sulle Strategie di Gestione delle Perdite Idriche
Economic Level of Leakage (ELL)
Approaches to Estimating and Achieving ELLApproaches to Estimating and Achieving ELL
Stuart Trow – United KingdomLeakage Consultant
andDirector of CaL Solutions Ltd
2IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Estimating ELL
Estimating ELL is one of the first things that should be done Estimating ELL is one of the first things that should be done before starting a major programme of investment in leakage before starting a major programme of investment in leakage managementmanagementELL estimation is an ongoing process ELL estimation is an ongoing process –– not a onenot a one--offoffThis presentation summarises the latest IWA thinking on ELL This presentation summarises the latest IWA thinking on ELL methodologiesmethodologiesI have been involved with leakage management in the UK for 27 I have been involved with leakage management in the UK for 27 years, and with target setting based on ELL for 20 years. Pleaseyears, and with target setting based on ELL for 20 years. Pleasetake the opportunity to ask questions take the opportunity to ask questions [email protected]@aol.com
3IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
An Economic Optimum
If little or nothing is spent on leakage control, the value If little or nothing is spent on leakage control, the value of the water lost will be excessiveof the water lost will be excessiveIf too much is spent on leakage control, the cost will If too much is spent on leakage control, the cost will outweigh the savings which result from the expenditureoutweigh the savings which result from the expenditureBetween these two extremes there is an economic level Between these two extremes there is an economic level of leakage at which the costs and benefits are optimisedof leakage at which the costs and benefits are optimised
4IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Defining ELL
Report 26 1980:Report 26 1980: ““It is clearly uneconomic to ensure that pipelines and It is clearly uneconomic to ensure that pipelines and reservoirs will never leak. It is also clear that there is an ecreservoirs will never leak. It is also clear that there is an economic limit to the onomic limit to the loss of water that should be tolerated through leakageloss of water that should be tolerated through leakage””Managing Leakage Report C 1994:Managing Leakage Report C 1994: ““That level of leakage where the marginal That level of leakage where the marginal cost of active leakage control equals the marginal cost of the lcost of active leakage control equals the marginal cost of the leaking watereaking water””CIWEM Approach CIWEM Approach –– 2003:2003: ““Economic level of leakage can be defined, Economic level of leakage can be defined, -------- as as that level of leakage at which any further reduction would incurthat level of leakage at which any further reduction would incur costs in costs in excess of the benefits derived from the savingsexcess of the benefits derived from the savings””Latest WLTF Definition:Latest WLTF Definition: ““The level of water losses which results from a The level of water losses which results from a policy under which the marginal cost of each individual activitypolicy under which the marginal cost of each individual activity for managing for managing losses can be shown to be equal to the marginal value of water losses can be shown to be equal to the marginal value of water in the supply in the supply zonezone”” In other words: Do everything that makes economic sense and theIn other words: Do everything that makes economic sense and theELL is the level of leakage which results from such a strategyELL is the level of leakage which results from such a strategy
5IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Time and Money
Water supply organisations carry out leakage control in Water supply organisations carry out leakage control in order to save moneyorder to save moneyIt is important to recognise that there are different It is important to recognise that there are different kinds of money; money is time dependentkinds of money; money is time dependentThe time horizon of leakage control expenditure is very The time horizon of leakage control expenditure is very important in the analysis of ELLimportant in the analysis of ELLIt also makes ELL estimation complicatedIt also makes ELL estimation complicatedThe new IWA methodologies attempt to simplify the The new IWA methodologies attempt to simplify the ELL process in a practical way based on experienceELL process in a practical way based on experience
6IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Facts about ELL
ELL is specific to an individual water supply zoneELL is specific to an individual water supply zoneELL is time dependent; shortELL is time dependent; short--run and longrun and long--runrunShort run ELL is a function of:Short run ELL is a function of:
The current variable cost of water (CV)The current variable cost of water (CV)The cost of active leakage control interventions (CI)The cost of active leakage control interventions (CI)The Rate of Rise of unThe Rate of Rise of un--reported leakage (RR) reported leakage (RR)
Long run ELL is a function of:Long run ELL is a function of:The future cost of water The future cost of water –– depending on the available supplydepending on the available supplyThe changes in shortThe changes in short--run ELL due to cost run ELL due to cost -- effective effective investments on the water supply networkinvestments on the water supply network
7IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Diminishing Returns
A fundamental fact about leakage control is that A fundamental fact about leakage control is that every possible leakage control measure follows a every possible leakage control measure follows a law of diminishing returns. law of diminishing returns. As more money is spent, the return in terms of As more money is spent, the return in terms of water saved due to lower losses, becomes water saved due to lower losses, becomes progressively less. progressively less. Some level of each activity will form part of an Some level of each activity will form part of an economic strategy. economic strategy.
8IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Short, Medium and Long Term
Short term measures:Short term measures:Leak detection and repair Leak detection and repair
Medium term measures:Medium term measures:Pressure ManagementPressure ManagementDistrict meteringDistrict metering
Long term measures:Long term measures:Mains and service renewalMains and service renewal
9IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
ALC Cost Curve
Leakage Level
Ann
ual C
ost
Water Cost ALC CostTotal Cost Policy Minimum
Economic Range
10IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
ALC Marginal Cost Curve
Leakage Level
Mar
gina
l Cos
t
Water Cost ALC Cost Policy Minimum
ELL
11IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Short Run vs Long Run ELL
Vary Active Leakage Control:Vary Active Leakage Control:Optimise against variable cost of Water (CV)Optimise against variable cost of Water (CV)This is This is short run ELLshort run ELL
Consider capital investment in leakage management options:Consider capital investment in leakage management options:Pressure control, rehabilitation , Pressure control, rehabilitation , sectorisationsectorisation etc.etc.Hypothesis interventions Hypothesis interventions –– work out discounted cost, work out discounted cost, benefit and derive Average Incremental Cost (AIC)benefit and derive Average Incremental Cost (AIC)Rank and implement in orderRank and implement in orderStrictly need to reassess benefit of schemes after Strictly need to reassess benefit of schemes after implementation of other schemesimplementation of other schemesThis is This is long run ELLlong run ELL
13IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
ELL vs. other Supply Demand Measures
14IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Identify opportunities for achieving
economic management of operating
pressures, to reduce frequencies of new bursts
leaks, and flow rates of running leaks
Calculate Unavoidable Annual Real Losses
(UARL) using average system pressure
Use the IWA water balance to
calculate the Current Annual Real Losses
(CARL) with 95% confidence limits
Measure system pressures:
check for the presence of surges,
identify excess pressure above minimum
standard of service, and any pressure
below the minimum standard of service
Calculate the
Infrastructure Leakage Index
ILI = CARL / UARL
Benchmark the operational performance
in managing Real Losses by comparing
the ILI and ELI with international,
national and sub-system data ILI data
UARL < CARL < EARL
Identify opportunities for achieving
economic infrastructure management
activities:
assets, mains and service connections
Calculate Economic Intervention times and Economic Annual Real Losses
(EARL) using cost of water
Calculate the
Economic Leakage Index
ELI = CARL / EARL
Operate to economic ALC intervention times
Identify economic speed and quality of repairs, extent and size of sectors
Twin-Track approach to Benchmarkingand Management of Real Losses
15IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Squeezing the Box
For any system For any system –– the Economic Level of Leakage comprises 3 the Economic Level of Leakage comprises 3 Principal Components:Principal Components:
1.1. A level of A level of ““backgroundbackground”” losseslosses which results from an optimised which results from an optimised entry and exit policy for DMA management, or exit policies for entry and exit policy for DMA management, or exit policies for regular surveyregular survey
2.2. A level of leakage from A level of leakage from reported burstsreported bursts with optimised repair with optimised repair time policytime policy
3.3. A level of leakage from A level of leakage from unreported (hidden) burstsunreported (hidden) bursts resulting resulting from an economic intervention policy for leak detection and from an economic intervention policy for leak detection and repairrepair
16IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Current Annual Real Losses
© WRP (Pty) Ltd, 2001
Pressure Management
Pressure
Management
Active LeakageControl
Speed and Quality of Repairs
Speed and quality
of repairs
Active Leakage Control
Pipe Materials Management:
selection,installation,
maintenance,renewal,
replacement
Pipeline and Assets
Management: Selection,
Installation, Maintenance,
Renewal, Replacement
UnavoidableAnnual Real
Losses
17IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
IWA WLTF approach: Squeezing the Box
For any system For any system –– achievement of the ELL comprises 4 interachievement of the ELL comprises 4 inter--related activities:related activities:
1.1. An optimised overall An optimised overall Pressure ManagementPressure Management policy:policy:-- identify presence of surges and minimise their adverse effectsidentify presence of surges and minimise their adverse effects-- basic simple reduction of excess pressuresbasic simple reduction of excess pressures
2.2. An optimised An optimised Repair TimeRepair Time policy for all burstspolicy for all bursts3.3. An economic An economic Intervention PolicyIntervention Policy for awareness, location and repair of for awareness, location and repair of
unreported (hidden) bursts unreported (hidden) bursts -- influenced by level of investment in leakage management infrastinfluenced by level of investment in leakage management infrastructure i.e. ructure i.e.
Telemetry/SCADA, Telemetry/SCADA, DMAsDMAs, advanced pressure management, advanced pressure management-- influenced by exit level (background and other leaks remaining influenced by exit level (background and other leaks remaining after after
interventions)interventions)4.4. An economic level of An economic level of InvestmentInvestment in mains and services renewals which takes in mains and services renewals which takes
account of all other factors account of all other factors
18IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
An economic approach to prioritising Pressure Management Areas (PMAs)
0
500
1000
1500
2000
2500
3000
Scheme Reference
Num
ber o
f Pro
pert
ies
in S
chem
e
£0.00
£5.00
£10.00
£15.00
£20.00
£25.00
£30.00
£35.00
£40.00
Cos
t Per
PM
PRA propertycountCost perproperty metre
19IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Repair Times
0 10 20 30 40 50 60 70
Repair Time Days
Add
ition
al C
ost /
Rep
air
Economic?
Uneconomic
20IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Graph 1: Predicting EconomicIntervention Frequency for Regular Survey
Source of data: ALCCalcs
CI/MaC = Intervention survey cost (£/service conn)/ Marginal cost of water (£/m3)
06
121824303642485460667278849096
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100Rate of rise of unreported leaks (S)
(litres/connection/day, per year)
Econ
omic
Per
iod
betw
een
Inte
rven
tions
Te
(mon
ths)
CI/MaC=100 m3/sc
CI/MaC=50 m3/sc
CI/MaC=20 m3/sc
CI/MaC=10 m3/sc
CI/MaC=5 m3/sc
CI/MaC=2 m3/sc
21IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Economic Approach to Coverage by DMAs
0 20 40 60 80 100
% DMA Coverage
Cos
t per
Mld
Sav
ed Uneconomic
Economic
22IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Economic approach toMains and Service Pipe Replacement
Scheme
Leng
th k
m /
Mld
sav
ed
Economic Uneconomic
Limit based on value of water
23IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Selecting Mains for Replacement
Burst Rate Distribution
0
2
4
6
8
10
0% 20% 40% 60% 80% 100%
Cumulative % of network
Busr
t Rat
e no
/km
/yr
24IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Relative costs of reducing leakage (UK, late 1990’s)
25IWA Water Loss Task Force Visit ItalyGenova – Ferrara 15-19 May 2006
Current Annual Real Losses
Potentially Recoverable Real Losses
Economic Level of Real Losses
Unavoidable Annual Real
Losses
Pressure Management
Pressure
Management
Active LeakageControl
Speed and Quality of Repairs
Speed and quality
of repairs
Active Leakage Control
Pipe Materials Management:
selection,installation,
maintenance,renewal,
replacement
Pipeline and Assets
Management: Selection, Installation, Maintenance
, Renewal, Replacement
Economic ILI