Page 1: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF GROUP

PRESENTATION

Decommissioning & Waste Treatment

Lokala säkerhetsnämnden

9/12/2016

Page 2: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

AGENDA

1. EDF GROUP, THE WORLD’S

LEADING ELECTRICITY COMPANY

2. OUR AMBITION IN THE NUCLEAR

DECOMMISSIONING & WASTE

TREATMENT MARKet

EDF 2016 I P.2

Page 3: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF GROUP,THE WORLD’S LEADING ELECTRICITY COMPANY

All electricity-related activities

— Generation

— Transmission & Distribution

— Trading and Sales & Marketing

— Energy services

EDF ranks:

among the top 100 largest companies in the world (Fortune Global 500 2014)

EDF is a leader in low-carbon generation:

102 g/kWh, of which 87% carbon-free generation

— World’s No. 1 nuclear operator

— European No. 1 in generation

from renewables

— European No. 3

in energy services

38.5 MILLION CUSTOMERS

158,200 EMPLOYEES

€75.0 BILLION SALES

€17.6 BILLION EBITDA

€12.7 BILLION NET INVESTMENTS

EDF 2016 I P.3

ELECTRICITY GENERATION

623.5 TWH

Page 4: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.4

EDF GROUP IS THE WORLD’S LEADING NUCLEAR FLEET OWNER

AND OPERATOR

WITH 73 OPERATING UNITS

5 NEW NUCLEAR PROJECTS

72.9 GW installed capacity, 54% of the Group’s net

generation capacity

477.7 TWh generated, 77% of the Group’s output

58 reactors operated in France, 15 in the UK

3 EPR under construction:

- 1 in Flamanville (France)

- 2 in Taishan (China)

2 EPR in project phase

EDF has a long track record of safe reliable nuclear generation

and has a bright future ahead

Page 5: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

AGENDA

1. EDF GROUP, THE WORLD’S

LEADING ELECTRICITY COMPANY

2. OUR AMBITION IN THE NUCLEAR

DECOMMISSIONING & WASTE

TREATMENT MARKET

EDF 2016 I P.5

Page 6: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 6

DECOMMISSIONNING AND WASTE MANAGEMENT ARE KEY TO EDF STRATEGY IN THE

NUCLEAR INDUSTRY

As a responsible nuclear operator,

demonstrate our full control along

the entire life cycle, by efficiently

managing decommissioning projects

and waste generated by our power

plants in operating or dismantlement

phase.

Decommissioning and

Waste Management (DP2D)

Operating

NPPsNew Build

• 58 reactors in

France, 15 in

the UK

• 73 GW installed

capacity

• 478 TWh

generated

• 3 EPRs under

construction in

France and

China

• Others in

project phase

Waste treatment :

Socodei, Cyclife

Development of

solutions for HLW

9 NPPs under

decommissioning

in France

Nuclear

Energy

Trading &

Supply

GridRene-

wablesThermal

Generating low-carbon electricity from

nuclear power and renewables is a

top priority of the CAP 2030 strategy77% of the

Group’s power

output

EDF, the efficient and

responsible electricity

company, the champion

in low-carbon growth

Page 7: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 7

FAVORABLE MARKET OUTLOOK IN THE NUCLEAR DECOMMISSIONING AND WASTE

TREATMENT

USA

Europe

Japan

In the USA

Dismantling market size

x 4

In Europe

In the UK : 14 AGRs to be stopped by

2030

In Germany : 7 PWRs and 2 BWRs to be

stopped by 2022

In Sweden : 1 PWRs and 3 BWRs to be

stopped by 2025

x 2

Dismantling market size

x 3

Waste treatment market size

Japan

x 2

Dismantling market size

Page 8: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 8

OUR AMBITION and COMMITMENTS

A responsible

nuclear firm

• In control of the whole

lifecycle of nuclear power

generation

• Best-in-class for safety

and security standards

A responsible

employer

A responsible

social partner

• Attract and develop skills

• People-centered

• Transparent and reliable

for all stakeholders

Customer

satisfaction

• Develop a customer-

oriented mindset

• Provide differentiating

solutions

Quality &

Efficiency

Innovation to

stay ahead

• Technical excellence

• Sustainable and profitable

business

• Develop sustainable and

cost-effective solutions

• Promote innovation

within the organizations

The European leader in nuclear waste treatment & decommissioning

Corporate Social Responsibility Value Creation&

The acquisition of Studsvik Waste Treatment business division is a key

milestone in The EDF Group’s strategic plan

Page 9: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 9

INTRODUCING , PART OF THE EDF GROUP

A strong player with a European footprint…

Waste Treatment

Melting : up to 8 500 t/yearScrap and metallic large components

Incineration : up to 5 600 t/year

Metal Recycling Facility : up to

2 500 t/year

Pyrolysis : 50 t/year

Decommissioning Services

Decommissioning Scenario & Costing

Waste management strategy

Waste Characterization

Transition Management

Training

…with 900 dedicated and well trained staff to handle

all of your decommissioning and waste treatment

requirements…

…and an ambition to grow into the blossoming

decommissioning and waste treatment market

Page 10: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.10

CYCLIFE is a portmanteau word built with « cycle » and « life ».

Sounding

The name is brief, impacting, modern, positive, almost militant.

Background

- cycle, circle, and associated symbols (round, generous, community)

- sequence repeated, revolution

- character related with the beginning, the original state

-life, energy, movement, dynamic

- recycling

- resources, sustainability

- continuity

CYCLIFE

Welcome home - 08/2016

Page 11: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.11

+ Waste management / Treatment / Recycling to

support operations and decommissioning

OUR REFERENCES ON THE NUCLEAR VALUE CHAIN

Page 12: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.12

EDF HAS A LONG EXPERIENCE IN DECOMMISSIONING AND WASTE

MANAGEMENT

Recently created a dedicated division to accelerate its development in the waste treatment and

decommissioning market.

More than 15 years experience :

EDF has taken 9 units from operating

to decommissioning : 1 Pressurised

Water Reactor, 1 Heavy Water

EDF is a also in preparing AGR

decommissioning that will begin by mid

2020s - all closed in early 2030s

More than 25 years in waste treatment through Socodei (our waste

treatment subsidiary based in France created in 1990)

Melting, incineration, onsite waste treatment operations

EDF plants under decommissioning : 2- Brennilis

Commission date: 1967

Shut-down date: 1985

1- Chooz

Commission date : 1967

Shut-down date: 1991

3- Saint Laurent A

Commission dates :

1969 & 1971

Shut-down dates:

1990 & 1992

5- Bugey 1

Commission

date : 1972

Shut-down

date: 1994

6- Creys-Malville

Commission date : 1986

Shut-down date: 1998

4- Chinon A

Commission dates:

1963, 1965 & 1966

Shut-down dates:

1973 , 1985 & 1990

Waste treatment operations

Heavy Water Reactor

Pressurized Water Reactor

UNGG Reactor

Fast-neutron Reactor

Page 13: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.13

OUR AMBITION IS TO DEVELOP AN INTERNATIONAL PLATFORM IN

DECOMMISSIONING & WASTE TREATMENT

Objectives for our clients :

Use The EDF Group’s skills and assets to offer competitive waste treatment and

decommissioning services

In the long-term, improve overall industrial capacity to match growing market needs

Develop innovative cost effective solutions for waste treatment and decommissioning

Answer growing incitation to recycle nuclear waste in order to preserve storage

capacities

The acquisition of Studsvik Waste Treatment business division is a milestone in The EDF

Group’s strategic plan.

Page 14: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.14

EDF’S DEDICATED DIVISION TO DECOMMISSIONING AND WASTE

MANAGEMENT

EDF CEO

EDF Group Executive Director for Nuclear

& Thermal generation (DPNT)

Decommissioning and

Waste Management Division

(DP2D)

DP2D Division created in 2016

Directly linked to the executive committee of EDF

Now 900 people working on Decommissioning & Waste Management

In charge of EDF’s nuclear dismantlement program worldwide

In charge of :

— EDF’s nuclear dismantlement program worldwide

— Managing waste generated by EDF’s nuclear

power plants

— Managing and developing waste treatment assets

Existing waste treatment assets in

France, Sweden and UK

Page 15: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.15

EDF CONTACTS

Mats Fridolfsson

Managing Director, Cyclife Sweden

[email protected]

Mobile : +46 76 00 09 201

Page 16: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

CYCLIFE SWEDEN AB

Lokala säkerhetsnämnden

09/12/2016

Page 17: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 17Lokala säkerhetsnämnen | 12/2016

MYNDIGHETSÄRENDEN

Tillsynsaktiviteter genomförda under perioden 1 juli – 8 december 2016

Verksamhetsbevakning från SSM inom Transport 25/10

Inspektion inom Safeguard 27/7

Kommande tillsynsaktiviteter

Inga datumsatta SSM-tillsyner

Remisser

Ny föreskrift för fysiskt skydd

Föreskrifter om konstruktion, analys och drift av kärnkraftsreaktorer

Studsviksfondens avskaffande

Övriga ärenden

Diverse övriga ärenden

Page 18: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 18

HÄNDELSER 1 JULI – 8 DECEMBER 2016

Mindre barriärbrott, askfat

Denna händelse har ej medfört något utsläpp

Lokala säkerhetsnämnen | 12/2016

Page 19: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 19

PYROLYSANLÄGGNINGEN

Status, går enligt plan (31/5/2017)

Fortsatt provdrift

Optimering av anläggningen

Lokala säkerhetsnämnen | 12/2016

Page 20: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 20Lokala säkerhetsnämnen | 12/2016

DOSSTATISTIK JULI – NOVEMBER 2016

Doser, mmanSvAckumulerade

doser (jan-xxx)Individ max dos, mSv

Juli 1,51 1,51 (29,04) 0,33

Augusti 4,12 5,63 (33,16) 1,10

September 13,07 18,7 (46,23) 1,42

Oktober 4,07 22,77 (50,30) 0,91

November 2,94 25,71 (53,24) 0,30

Page 21: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

| 21

ÖVRIGA PUNKTER

Avvikelse gällande ytkontaminerade göt

Aktivitet inför 2017 (om SSM beviljar)

Vi har ansökt om medel för rivning av R0 komplexet (3 byggnader)

Lokala säkerhetsnämnen | 12/2016

Page 22: EDF GROUP PRESENTATION - nykoping.se...EDF GROUP PRESENTATION Decommissioning & Waste Treatment Lokala säkerhetsnämnden 9/12/2016 AGENDA 1. EDF GROUP, THE WORLD’S LEADING ELECTRICITY

EDF 2016 I P.22

THANK YOU