edmedm edm fast start, may 23, 2006he3s, steven williamson edm fast start helium-3 services (he3s)...
TRANSCRIPT
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
EDM Fast Start
Helium-3 Services(He3S)
Steven Williamson
May 23, 2006
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Significant Planning Assumptions: Scope
Hardware ABS Injection Volume Purifier Interconnections (ABS Interface, Plumbing to Cells) Fluid Control (Valves, Pressurizer, Volume Displacement)
Tests Injection Purification Pressurization Full System
Installation at ORNL McClintock Purifier
Cell Isolation Valve (V1) Body/Stem/Seat is NOT part of He3S
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
The He3S Work Packages
WBS Work Package Leader6.1 3He Atomic Beam Source (ABS) Steve Lamoreaux6.2 ABS Interface Haiyan Gao6.3 Polarized 3He Collection System Haiyan Gao6.4 3He Injection Test Haiyan Gao6.5 Purifier Mike Hayden6.6 Purifier Volume Displacement Mike Hayden6.7 Purifier/Valve Test Mike Hayden6.8 Pressurizer Steve Williamson6.9 Pressurizer/Valve Test Steve Williamson6.10 Valves Doug Beck6.11 Interconnect Plumbing Jen-Chieh Peng6.12 He3S (Full Subsystem) Test Steve Williamson6.13 He3S Installation in Upper Cryostat Steve Williamson6.14 McClintock Purifier (Bulk Purified 4He) Seppo Penttila
Magenta Not Confirmed
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
The He3S Work Packages
WBS Work Package Leader6.1 3He Atomic Beam Source (ABS) Steve Lamoreaux6.2 ABS Interface Haiyan Gao6.3 Polarized 3He Collection System Haiyan Gao6.4 3He Injection Test Haiyan Gao6.5 Purifier Mike Hayden6.6 Purifier Volume Displacement Mike Hayden6.7 Purifier/Valve Test Mike Hayden6.8 Pressurizer Steve Williamson6.9 Pressurizer/Valve Test Steve Williamson6.10 Valves Doug Beck6.11 Interconnect Plumbing Jen-Chieh Peng6.12 He3S (Full Subsystem) Test Steve Williamson6.13 He3S Installation in Upper Cryostat Steve Williamson6.14 McClintock Purifier (Bulk Purified 4He) Seppo Penttila
Magenta Not Confirmed
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Significant Planning Assumptions:Technical
Technical Assumptions Minimal adaptation of ABS Evaporation purification Two Purifiers Volume Displacement System Pressurization of cell to 1 atm Diffusive 3He flow 0 pumps. 1 V1 valve/cell All actuators use “Heliomatic” mechanism for 300 K to 4 K A certain model for interconnection
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Other Significant Planning Assumptions:
Procurement Hardware is ordered from vendors (build to drawing). Local technical support at collaborating institutions not used. It’s
hard to estimate without a firm design. This is wrong but…
Manpower Engineering by Bartoszek Engineering (more later) Work package leaders assumed, but not all confirmed Local technical support used for installation and testing.
Testing All systems must be successfully tested before arrival at ORNL Tests take place in parallel at different locations.
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Milestones
6.1.7 ABS Complete6.2.7 ABS Interface Complete6.3.8 Collection System Complete6.4.7 Injection Test Completed Successfully6.5.11 Purifier Complete6.6.4 Purifier Volume Displacement Complete6.7.7 Purifier/Valve Test Completed Successfully6.8.4 Pressurizer Complete6.9.8 Pressurizer/Valve Test Completed Successfully6.10.1.4 Cell Isolation (V1) Valve Actuators and Interfaces Complete6.10.2.4 Pressurizer Isolation (V2) Valve Complete6.10.3.4 Pressurizer Standoff (V3) Valve Complete6.10.4.4 Collection Isolation (V4) Valve Complete6.10.5.4 Purifier Control (V5) Valve Complete6.10.6.4 Purifier Isolation (V6) Valves Complete6.11.1.3 Volume Displacement Interconnect Plumbing Complete6.11.2.4 Collection/Purifier Interconnect Plumbing Complete6.11.3.4 Pressurizer/Cell Interconnect Plumbing Complete6.12.8 He3S Test Completed Successfully6.13.4 He3S Installation in Upper Cryostat Complete6.14.7 McClintock Purifier Commissioned
Level 3 Milestones for Hardware CompletionLevel 2 Milestones for Tests
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Interfaces
DAQ Slow controls
Cryostat/Cryogenic Services Mechanical support Instrumentation and motion feed-through 50 K, 4 K, 0.3 K thermal links
Coils and Magnetic shielding Upper cryostat cos() holding field Over-all magnetic model
Measurement Cell Insert Interface to V1 valve body/stem Plumbing connections into inner volume
He3S Interfaces With MANY Subsystems
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Technical Scope Definition Issues
Resolution of many technical issues could totally change the scope (see Technical Assumptions). Example: If evaporation purification found to not be practical
purifier work package would be completely different.
Important materials issue: 3He Friendliness (more info needed – not just for dTPB, but teflon, nylon, DryFilm,…
Interfaces! (Where does He3S end?)
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Equipment Performance Issues
Injection polarization (90%)
Injection efficiency (How much 3He enters the LHe?)
Relaxation time in the collection volume (100 s)
Polarized 3He loading time (1000 s)
Quality of purification (1011 3He atoms/cc)
Time required to purify
Regeneration frequency
Valve lifetime (5000 cycles)
Superfluid leak tightness (valves, joints)
3He friendliness of plumbing (pol = 80% at the cell)
Heat load to DR
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Schedule Estimates
The schedule driven by the manpower allocated to engineering.
The work-package level Gantt chart with no leveling:
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Schedule Estimates
The schedule is driven by the manpower allocated to engineering.
The work-package level Gantt chart with leveling:
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Cost Estimates
WBS Work Package Raw Cost %Cont
Total Cost
6.1 3He Atomic Beam Source (ABS) $76k 15 $87k6.2 ABS Interface $101k 32 $133k6.3 Polarized 3He Collection System $156k 41 $219k6.4 3He Injection Test $92k 20 $111k6.5 Purifier $191k 35 $258k6.6 Purifier Volume Displacement $64k 55 $100k6.7 Purifier/Valve Test $85k 20 $102k6.8 Pressurizer $60k 65 $99k6.9 Pressurizer/Valve Test $79k 18 $93k6.10 Valves $469k 68 $788k6.11 Interconnect Plumbing $113k 44 $163k6.12 He3S (Full Subsystem) Test $204k 27 $260k6.13 He3S Installation in Upper Cryostat $114k 16 $132k6.14 McClintock Purifier (Bulk Purified 4He) $74k 17 $86k
Total $1,879k 40 $2,632k
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
A Typical Work Package
WBS Activity Title Labor ODC %Cont
TEC
6.5.1 Prelim. Purifier Design $23k 40 $33k
6.5.2 Absorption Pumps $10k $11k 52 $32k
6.5.3 Purifier Volumes $10k $11k 19 $25k
6.5.4 Regeneration Instrumentation $6k $2k 19 $10k
6.5.5 Purifier Film Killers $10k $5k 64 $26k
6.5.6 Purifier Concentration Measurement Apparatus
$14k $5k 74 $34k
6.5.7 Purifier Vacuum System/Plumbing $10k $25k 13 $39k
6.5.8 Purifier Mechanical Support $6k $11k 16 $20k
6.5.9 Purifier Thermal Links $10k $2k 16 $15k
6.5.10 Purifier Sensor Instrumentation $7k $9k 40 $23k
Total $109k $82k 35 $257k
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Staffing Plans/Issues
Key People Needed: Work package leaders need to be confirmed. Possibly new
leaders identified Some additional engineering will be necessary
Identifying in-house technical skills and capabilities may allow less outside work – could save money.
Special skills (e.g. glass blowing) may be required.
EDM
EDM Fast Start, May 23, 2006 He3S, Steven Williamson
Procurement Planning
The largest single items to be procured are the valve actuators $30k Need 8 for valves and 2 more for bellows. In actuality these may be built of smaller parts purchased
separately:
Warm actuator $2.5k Feed-through from warm to 4K piston and cylinder $5.0k 4K piston and cylinder in upper cryostat $10.0k4K piston and cylinder on 4K shield $10.0kGaseous Hydraulic plumbing between cylinders $2.5kTotal $30.0k
Next largest items are SQUID electronics and pumps (~$20k)