EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

EDM Fast Start

Helium-3 Services(He3S)

Steven Williamson

May 23, 2006

Page 2: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Significant Planning Assumptions: Scope

Hardware ABS Injection Volume Purifier Interconnections (ABS Interface, Plumbing to Cells) Fluid Control (Valves, Pressurizer, Volume Displacement)

Tests Injection Purification Pressurization Full System

Installation at ORNL McClintock Purifier

Cell Isolation Valve (V1) Body/Stem/Seat is NOT part of He3S

Page 3: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

The He3S Work Packages

WBS Work Package Leader6.1 3He Atomic Beam Source (ABS) Steve Lamoreaux6.2 ABS Interface Haiyan Gao6.3 Polarized 3He Collection System Haiyan Gao6.4 3He Injection Test Haiyan Gao6.5 Purifier Mike Hayden6.6 Purifier Volume Displacement Mike Hayden6.7 Purifier/Valve Test Mike Hayden6.8 Pressurizer Steve Williamson6.9 Pressurizer/Valve Test Steve Williamson6.10 Valves Doug Beck6.11 Interconnect Plumbing Jen-Chieh Peng6.12 He3S (Full Subsystem) Test Steve Williamson6.13 He3S Installation in Upper Cryostat Steve Williamson6.14 McClintock Purifier (Bulk Purified 4He) Seppo Penttila

Magenta Not Confirmed

Page 4: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

The He3S Work Packages

WBS Work Package Leader6.1 3He Atomic Beam Source (ABS) Steve Lamoreaux6.2 ABS Interface Haiyan Gao6.3 Polarized 3He Collection System Haiyan Gao6.4 3He Injection Test Haiyan Gao6.5 Purifier Mike Hayden6.6 Purifier Volume Displacement Mike Hayden6.7 Purifier/Valve Test Mike Hayden6.8 Pressurizer Steve Williamson6.9 Pressurizer/Valve Test Steve Williamson6.10 Valves Doug Beck6.11 Interconnect Plumbing Jen-Chieh Peng6.12 He3S (Full Subsystem) Test Steve Williamson6.13 He3S Installation in Upper Cryostat Steve Williamson6.14 McClintock Purifier (Bulk Purified 4He) Seppo Penttila

Magenta Not Confirmed

Page 5: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Significant Planning Assumptions:Technical

Technical Assumptions Minimal adaptation of ABS Evaporation purification Two Purifiers Volume Displacement System Pressurization of cell to 1 atm Diffusive 3He flow 0 pumps. 1 V1 valve/cell All actuators use “Heliomatic” mechanism for 300 K to 4 K A certain model for interconnection

Page 6: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Other Significant Planning Assumptions:

Procurement Hardware is ordered from vendors (build to drawing). Local technical support at collaborating institutions not used. It’s

hard to estimate without a firm design. This is wrong but…

Manpower Engineering by Bartoszek Engineering (more later) Work package leaders assumed, but not all confirmed Local technical support used for installation and testing.

Testing All systems must be successfully tested before arrival at ORNL Tests take place in parallel at different locations.

Page 7: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Milestones

6.1.7 ABS Complete6.2.7 ABS Interface Complete6.3.8 Collection System Complete6.4.7 Injection Test Completed Successfully6.5.11 Purifier Complete6.6.4 Purifier Volume Displacement Complete6.7.7 Purifier/Valve Test Completed Successfully6.8.4 Pressurizer Complete6.9.8 Pressurizer/Valve Test Completed Successfully6.10.1.4 Cell Isolation (V1) Valve Actuators and Interfaces Complete6.10.2.4 Pressurizer Isolation (V2) Valve Complete6.10.3.4 Pressurizer Standoff (V3) Valve Complete6.10.4.4 Collection Isolation (V4) Valve Complete6.10.5.4 Purifier Control (V5) Valve Complete6.10.6.4 Purifier Isolation (V6) Valves Complete6.11.1.3 Volume Displacement Interconnect Plumbing Complete6.11.2.4 Collection/Purifier Interconnect Plumbing Complete6.11.3.4 Pressurizer/Cell Interconnect Plumbing Complete6.12.8 He3S Test Completed Successfully6.13.4 He3S Installation in Upper Cryostat Complete6.14.7 McClintock Purifier Commissioned

Level 3 Milestones for Hardware CompletionLevel 2 Milestones for Tests

Page 8: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Interfaces

DAQ Slow controls

Cryostat/Cryogenic Services Mechanical support Instrumentation and motion feed-through 50 K, 4 K, 0.3 K thermal links

Coils and Magnetic shielding Upper cryostat cos() holding field Over-all magnetic model

Measurement Cell Insert Interface to V1 valve body/stem Plumbing connections into inner volume

He3S Interfaces With MANY Subsystems

Page 9: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Technical Scope Definition Issues

Resolution of many technical issues could totally change the scope (see Technical Assumptions). Example: If evaporation purification found to not be practical

purifier work package would be completely different.

Important materials issue: 3He Friendliness (more info needed – not just for dTPB, but teflon, nylon, DryFilm,…

Interfaces! (Where does He3S end?)

Page 10: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Equipment Performance Issues

Injection polarization (90%)

Injection efficiency (How much 3He enters the LHe?)

Relaxation time in the collection volume (100 s)

Polarized 3He loading time (1000 s)

Quality of purification (1011 3He atoms/cc)

Time required to purify

Regeneration frequency

Valve lifetime (5000 cycles)

Superfluid leak tightness (valves, joints)

3He friendliness of plumbing (pol = 80% at the cell)

Heat load to DR

Page 11: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Schedule Estimates

The schedule driven by the manpower allocated to engineering.

The work-package level Gantt chart with no leveling:

Page 12: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Schedule Estimates

The schedule is driven by the manpower allocated to engineering.

The work-package level Gantt chart with leveling:

Page 13: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Cost Estimates

WBS Work Package Raw Cost %Cont

Total Cost

6.1 3He Atomic Beam Source (ABS) $76k 15 $87k6.2 ABS Interface $101k 32 $133k6.3 Polarized 3He Collection System $156k 41 $219k6.4 3He Injection Test $92k 20 $111k6.5 Purifier $191k 35 $258k6.6 Purifier Volume Displacement $64k 55 $100k6.7 Purifier/Valve Test $85k 20 $102k6.8 Pressurizer $60k 65 $99k6.9 Pressurizer/Valve Test $79k 18 $93k6.10 Valves $469k 68 $788k6.11 Interconnect Plumbing $113k 44 $163k6.12 He3S (Full Subsystem) Test $204k 27 $260k6.13 He3S Installation in Upper Cryostat $114k 16 $132k6.14 McClintock Purifier (Bulk Purified 4He) $74k 17 $86k

Total $1,879k 40 $2,632k

Page 14: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

A Typical Work Package

WBS Activity Title Labor ODC %Cont

TEC

6.5.1 Prelim. Purifier Design $23k 40 $33k

6.5.2 Absorption Pumps $10k $11k 52 $32k

6.5.3 Purifier Volumes $10k $11k 19 $25k

6.5.4 Regeneration Instrumentation $6k $2k 19 $10k

6.5.5 Purifier Film Killers $10k $5k 64 $26k

6.5.6 Purifier Concentration Measurement Apparatus

$14k $5k 74 $34k

6.5.7 Purifier Vacuum System/Plumbing $10k $25k 13 $39k

6.5.8 Purifier Mechanical Support $6k $11k 16 $20k

6.5.9 Purifier Thermal Links $10k $2k 16 $15k

6.5.10 Purifier Sensor Instrumentation $7k $9k 40 $23k

Total $109k $82k 35 $257k

Page 15: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Staffing Plans/Issues

Key People Needed: Work package leaders need to be confirmed. Possibly new

leaders identified Some additional engineering will be necessary

Identifying in-house technical skills and capabilities may allow less outside work – could save money.

Special skills (e.g. glass blowing) may be required.

Page 16: EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006

EDM

EDM Fast Start, May 23, 2006 He3S, Steven Williamson

Procurement Planning

The largest single items to be procured are the valve actuators $30k Need 8 for valves and 2 more for bellows. In actuality these may be built of smaller parts purchased

separately:

Warm actuator $2.5k Feed-through from warm to 4K piston and cylinder $5.0k 4K piston and cylinder in upper cryostat $10.0k4K piston and cylinder on 4K shield $10.0kGaseous Hydraulic plumbing between cylinders $2.5kTotal $30.0k

Next largest items are SQUID electronics and pumps (~$20k)