EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeSeptember 12, 2017
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
3
Eglinton Station Update
4
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Wet utilities stages 1-4
THESL 1a, 1b
North and east pedestrian tunnels closure
Shoring at Salvation Army site
Fall 2017
• Shoring along the south side of Eglinton (three rigs now in operation)– This is the major activity of 2017; maps attached for each stage
• Underground pedestrian tunnel closure from TTC subway to Riocan Centre
• Toronto Hydro relocation 2b (Hillsdale Ave, Yonge St)
• Toronto Hydro relocation 2a (Eglinton Ave East)
5
Eglinton Station Shoring Phase 1 – Ongoing
6
Eglinton Station – West Tunnel Closure – September
7
Eglinton Station Shoring Phase 2 – November
8
Eglinton Station Shoring Phase 3
9
Eglinton Station Shoring Phase 4
10
Construction Progress Picture
DRILLING AT SOUTHEAST CORNER OF YONGE-
EGLINTON
11
Mount Pleasant Station Update
12
Mount Pleasant Station Construction Update
Fall 2017
• Continue hydro utilities relocation
• Continue support of excavation (piling) on the northwest side of Eglinton Avenue East
• Piling at the northeast side of Eglinton Avenue East
• Relocation of a sewer at the Secondary Entrance
• Installation of a storm sewer on the south side of Eglinton Avenue East
13
Current Construction Staging
NO TURNS IN ALL DIRECTIONSMT PLEASANT &
EGLINTON
Storm Sewer Installation
• Installation of new storm sewer infrastructure is required to accommodate
construction of Mount Pleasant Station
• To accommodate the on-going piling operation and minimize the disruption to
traffic, the work will be performed using a micro-tunneling methodology
• One launch shaft is required to send the tunnel boring machine (TBM) and
pipes, and one receiving shaft is required to extract the TBM
• Lane closures and pedestrian rerouting will be required
• Subject to permit approval, Taunton Road will be closed at Eglinton Ave E for
12 weeks while the launch shaft is in place
Storm Sewer Installation Map
Part 1 - Beginning as early as early October (12 weeks)Part 2 – Beginning as early as December (2 weeks)
PART 1
PART 2
Schedule – Storm Sewer Installation
• Launch Shaft (at Taunton Road):
Beginning as early as early October for approximately 12 weeks
• Receiving Shaft (east of Brownlow Avenue):
Beginning as early as early December for approximately two (2) weeks
• Work Sequence:
– Implement traffic staging for launch shaft
– Construction of launch shaft
– Mobilize TBM
– Pipe installation
– Implement traffic staging for receiving shaft
– Construction of receiving shaft
– TBM extraction
17
Future Construction Staging – Stage 3
18
Future Construction Staging – Stage 4
19
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
20
Mount Pleasant Station Main Entrance
*60% rendering
21
Mount Pleasant Station Secondary Entrance
*60% rendering
Mount Pleasant Station Construction Progress
22
DRILLINGLIFTING REBAR
CAGE
Mount Pleasant Station Construction Progress
23
UTILITIES RELOCATION