emcal meeting cern – july 2 nd 2007 lpsc status 1 j-f muraz lpsc status lpsc status. assembly...

6
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status. Assembly Hall. - Removal starts and is in progress. - Main infrastructure work will be done in November. (floor and wall painting, services installation).

Post on 21-Dec-2015

224 views

Category:

Documents


4 download

TRANSCRIPT

EMCal Meeting CERN – July 2nd 2007 LPSC Status 1 J-F Muraz

LPSC StatusLPSC Status.

Assembly Hall.

- Removal starts and is in progress.

- Main infrastructure work will be done in November.

(floor and wall painting, services installation).

EMCal Meeting CERN – July 2nd 2007 LPSC Status 2 J-F Muraz

Strip Modules handling tool.

- Hydraulic strike ordered and delivered in next few days.

- Structure scheduled for July in our mechanical workshop.

- We do a dummy strip module (real size and weight) in order to test

this tool and the SM assembly procedure.

LPSC StatusLPSC Status.

EMCal Meeting CERN – July 2nd 2007 LPSC Status 3 J-F Muraz

LPSC StatusLPSC Status.

SM Platform.

- Detailed drawings are in progress.

- Scheduled in our mechanical workshop for December

EMCal Meeting CERN – July 2nd 2007 LPSC Status 4 J-F Muraz

LPSC StatusLPSC Status.

SM tilt over mechanism. (needed in vertical Cosmic tests design)

- Basic design is in progress.

Winch

Tilt platform

Cable

EMCal Meeting CERN – July 2nd 2007 LPSC Status 5 J-F Muraz

LPSC StatusLPSC Status.

SM tilt over mechanism. (needed in vertical Cosmic tests design)

- Conceptual design is in progress.

EMCal Meeting CERN – July 2nd 2007 LPSC Status 6 J-F Muraz

LPSC StatusLPSC Status.

Test beam Scintillators paddles:

- Done and tested.