EN-CV interventions during YETS 2015-201622-09-2015
![Page 2: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/2.jpg)
Maintenance
![Page 3: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/3.jpg)
Cooling: yearly maintenance• 3 weeks of stop for the SF, SU, UW
• Mechanical cleaning of the cooling towers
• Mechanical and electrical maintenance
• Bugs fixing
SF
UW
SU
![Page 4: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/4.jpg)
Ventilation: yearly maintenance• No stop but redundancy affected during the maintenance.
• Intervention mostly on the surface.• Tunnel air handling units• Accessible areas (US, UA) air handling units
• Experimental cavern UX air handling units
• Yearly maintenance of the 174 underground units should be finished by TS3 (corrective actions could be needed during YETS)
![Page 5: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/5.jpg)
Planning for EN-CV maintenance - tbc • LHC points Stop Restart
Point 1 14th of December 15 15th of January 16
Point 18 tbd
Point 2 1st of February 16 19th of February 16
Point 3 22th of February 16 26th of February 16
Point 4 11th of January 16 29th of January 16
Point 5 14th of December 15 15th of January 16
Point 6 1st of February 16 19th of February 16
Point 7 22th of February 16 26th of February 16
Point 8 11th of January 16 29th of January 16
![Page 6: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/6.jpg)
Additional works
![Page 7: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/7.jpg)
Point 1 – additional works• ALFA cooled cables in RR13 and RR17• Installation of by-pass on the ATLAS US15 mixed water circuit
• Qualification of the compressed air vessel in SH1 + installation of valve. (stop needed)
• SF1: dismantle and repair cooling towers silencers
• Modification of the firefighting water circuit in SUX1
• USA15: replacement of the ED pumps, filling circuits and installation of additional valve.
![Page 8: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/8.jpg)
Point 18 – additional works• Full replacement of the cryo underground cooling plant in PM18• 4 weeks of stop
• Tbc by the Consolidation for the budget
• Tbc by the cryo and MEF for the time window
![Page 9: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/9.jpg)
Point 2 – additional works• SX2: modification of the pipework to install an Eletta for TE/EPC
• Replacement of the leaking valve in point 3 requesting to stop and empty the sector 2-3
• Work in UW25 to replace flexible sleeves and modify pipework
• Replacement of the raw water blocked valve in UL26
• Replacement of the ventilation unit for ITS in SX2
• Preparatory works for the replacement of the SR2 ventilation system (foreseen during EYETS). Intervention in the false floor: lockout required.
![Page 10: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/10.jpg)
Point 3 – additional works• PM32 consolidation phase two
• Tbc by the Consolidation (budget)• 6 weeks of work. Most of it in surface.
• Preparatory works for the replacement of the SR3 ventilation system (foreseen during EYETS). Intervention in the false floor: lockout required
![Page 11: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/11.jpg)
Point 4 – additional works• SU4 migration of the cooling control system → Unicos• 4 weeks of stop (+maintenance)
• SH 4 migration of the ventilation control system → Unicos (3 weeks)
• SHM 4 migration of the ventilation control system → Unicos (3 weeks)
![Page 12: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/12.jpg)
Point 5 – additional works• SUX5 migration of the cooling control system →
Unicos (tbc by CMS) • 3 weeks of stop (+maintenance)
• Mechanical maintenance on the ventilation in RR53 and RR57
• Modifications and repair of point 5 raw water in SD5. Raw water stopped and compensatory measure to discuss.
• Maintenance of Totem cooling plants in R532 and R571.
• Preparatory works for the replacement of the SR5 ventilation system (foreseen during EYETS). Intervention in the false floor: lockout required
• Fixed non-conformities in water connections on the cooled cables in RR53
![Page 13: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/13.jpg)
Point 6 – additional works• SH 6 migration of the ventilation control system → Unicos (3 weeks)
• SHM 6 migration of the ventilation control system → Unicos (3 weeks)
• Work in UW65 to replace flexible sleeves and modify pipework
• Preparatory works for the replacement of the SR6 ventilation system (foreseen during EYETS). Intervention in the false floor: lockout required
![Page 14: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/14.jpg)
Point 7 – additional works• Preparatory works for the replacement of the SR7 ventilation system (foreseen during EYETS). Intervention in the false floor: lockout required
![Page 15: EN-CV interventions during YETS 2015-2016 22-09-2015](https://reader036.vdocument.in/reader036/viewer/2022081822/5697bf771a28abf838c812e2/html5/thumbnails/15.jpg)
Point 8 – additional works• Cooling test plant for future datacenter• Modification for a backup of the LHCb control room racks
• Modification of the UAPE-831 and 832 installation of VSD.
• Point bas: replacement of the pumps.• UW85 : replacement of the flexibles sleeves and additional support
• SH 8 migration of the ventilation control system → Unicos (3 weeks)
• SHM 8 migration of the ventilation control system → Unicos (3 weeks)
• Work in UW85 to replace flexible sleeves and modify pipework