end the project death march: do more projects and boost team engagement!

25
PMI – Central Indiana Chapter Professional Development Day Joe Cooper, PMP, PMCP : 1joecooper

Upload: joe-cooper

Post on 30-Jun-2015

295 views

Category:

Business


1 download

DESCRIPTION

This presentation was given at the 2014 Project Management Institute - Central Indiana Chapter professional development day in Indianapolis on October 3rd, 2014. Venue: Wyndham Indianapolis West.

TRANSCRIPT

Page 1: End the project death march: do more projects and boost team engagement!

PMI – Central Indiana Chapter Professional Development Day

Joe Cooper, PMP, PMCP

: 1joecooper

Page 2: End the project death march: do more projects and boost team engagement!

PMI – Central Indiana Chapter Professional Development Day

Resolve crisis and high-stress in projects Significantly improve meeting delivery

commitments Simplify with pragmatic estimating Visually report project health early and

objectively

210/3/14

Page 3: End the project death march: do more projects and boost team engagement!

310/3/14

Wait a minute… Something feels wrong!!

Page 4: End the project death march: do more projects and boost team engagement!

410/3/14

In project management, a “death march” is a project where the team feels it is destined to fail, or requires periods of unsustainable work; frequent nights and weekends.

A project like this is usually filled with crisis and panic, particularly toward the end.

Photo from cover of book titled “Death March” by Edward Yourdon

Page 5: End the project death march: do more projects and boost team engagement!

510/3/14

Page 6: End the project death march: do more projects and boost team engagement!

610/3/14

Schedule overruns 74%, up from 71% in 2010

Budget overruns 59%, up from 46% in 2010

Features delivered 69%, down from 74% in 2010

Page 7: End the project death march: do more projects and boost team engagement!

710/3/14

Page 8: End the project death march: do more projects and boost team engagement!

810/3/14

Page 9: End the project death march: do more projects and boost team engagement!

910/3/14

Page 10: End the project death march: do more projects and boost team engagement!

1010/3/14

Schedules cut by sponsors or management Expecting every task to complete "on-time" Expecting later task owners to "make up time" when

earlier tasks slip Cutting testing when project commitment date is in

jeopardy Green to red status overnight Overtime required - nights and weekends Heroics needed to finish the project "No organization can possibly survive if it needs geniuses

to manage it" -Peter Drucker

Page 11: End the project death march: do more projects and boost team engagement!

1110/3/14

Yerkes-Dodson

Page 12: End the project death march: do more projects and boost team engagement!

1210/3/14

Page 13: End the project death march: do more projects and boost team engagement!

1310/3/14

Page 14: End the project death march: do more projects and boost team engagement!

1410/3/14

Page 15: End the project death march: do more projects and boost team engagement!

1510/3/14

10% confidence 50% confidence 95% confidence

2 days 5 days 12 days

.20

.40

.60

.80

1.0

Page 16: End the project death march: do more projects and boost team engagement!

1610/3/14

No progress Panic Work!

Start task Deadline

Page 17: End the project death march: do more projects and boost team engagement!

1710/3/14

Hidden

Padding

Hidden

Padding

Hidden

Padding

Hidden

Padding

Task 1 Task 2 Task 3 Task 4

Task 1 Task 2 Task 3 Task 4 Project BufferTime

Saved

Page 18: End the project death march: do more projects and boost team engagement!

1810/3/14

Hidden

Padding

Hidden

Padding

Hidden

Padding

Hidden

Padding

Task 1 Task 2 Task 3 Task 4

Task 1 Task 2 Task 3 Task 4 Project BufferTime

Saved

Page 19: End the project death march: do more projects and boost team engagement!

1910/3/14

Project Buffer

Page 20: End the project death march: do more projects and boost team engagement!

2010/3/14

Page 21: End the project death march: do more projects and boost team engagement!

2110/3/14

Buffer

consum

ed

.Project 1

.Project 2

.Project 3 .Project 4

.Project 5

.Project 6

Project duration

Page 22: End the project death march: do more projects and boost team engagement!

2210/3/14

Mazda using these methods.

Page 23: End the project death march: do more projects and boost team engagement!

2310/3/14

Chapter 17

www.tocico.org

Page 24: End the project death march: do more projects and boost team engagement!

PMI – Central Indiana Chapter Professional Development Day

Continually strive to create system harmony. Eliminate the stress that degrades performance.

Use 50/50 estimates to eliminate waste, boost team engagement, accelerate projects, and get more done.

Use a project buffer to avoid crisis, protect delivery commitments, and to enhance competitive advantage.

Create environments of FOCUS to eliminate the waste of rework and context switching.

2410/3/14

Page 25: End the project death march: do more projects and boost team engagement!

PMI – Central Indiana Chapter Professional Development Day

2510/3/14

Thank you!

Joe Cooper

email: [email protected]

phone: 309-212-6305

: joecooper1

www.Allegient.com

: 1joecooper

:slideshare.net/JosephCooperPMP