endcap signal feedthrough overview endcap signal feedthroughs are constructed and tested in victoria...

6
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit carries 1920 electrical channels. 50 feedthrough units in total (+5 spares) are required, 25 per endcap. There are 4 different kinds of signal feedthroughs on each endcap cryostat, due to the varied detectors they are servicing. In particular, low voltage is supplied to the HEC preamplifiers, located in the LAr, via signal feedthroughs. Close collaboration with colleagues from BNL (barrel signal feedthroughs) ATLAS reviews Project Review, BNL, Jun 12-13 1997 Baseline Design review CERN, Oct 13 th 1997 Production Readiness Review, CERN, Jan 29 th 1999 Activity/Systems Status Overview, CERN, Feb 11-12 2001 One endcap cryostat shown during assembly

Upload: august-hood

Post on 29-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Endcap Signal Feedthrough Overview

Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff.

Each feedthrough unit carries 1920 electrical channels.

50 feedthrough units in total (+5 spares) are required, 25 per endcap.

There are 4 different kinds of signal feedthroughs on each endcap cryostat, due to the varied detectors they are servicing. In particular, low voltage is supplied to the HEC preamplifiers, located in the LAr, via signal feedthroughs.

Close collaboration with colleagues from BNL (barrel signal feedthroughs)ATLAS reviews Project Review, BNL, Jun 12-13 1997 Baseline Design review CERN, Oct 13th 1997 Production Readiness Review, CERN, Jan 29th 1999 Activity/Systems Status Overview, CERN, Feb 11-12 2001

One endcap cryostat shown during assembly

Page 2: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Endcap Signal Feedthrough Overview

VCR Glands

Heater and T probes

Ambient Flange

Bolt Ring (not shown) to attach to warm vessel

Bellows Seal Ring

Pin Carriers

Bellows

Bellows Cuff Ring

Vacuum Cables

Cold Flange

Cold Box or Funnel

Pigtail Cables

1920 channels to detector patch panels in the cryostat

CF Flange for tests

Funnel cut here before welding on cold vessel bi-metallic junction

Seal ring OD = 326.4 mm

Total height = 699.9 mm

Page 3: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Production Status (as of June 10, 2002) 44 feedthrough units produced of which 29 at CERN and officially received. Production expected to end in August or September 2002

All units required for the endcap cryostat C are ready at CERN since March 2002

vacuum cable installation final cold tests

Page 4: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Shipment to CERN

crated feedthroughsfirst 4 HEC feedthroughs in shipping

container at the University of Victoria (November 2, 2001)

Each feedthrough has its own crate (they come in two sizes)

4 feedthrough crates are then packed together in a large container for shipment

Page 5: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Reception Tests at CERN

Feedthrough units are tested upon reception at CERN:

• visual inspection• leak test (ambient temperature)• electrical test (cross-talk)

The electrical testing equipment will also be used on the cryostat after feedthrough installation

electrical tests leak tests

Page 6: Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit

Quality Assurance / Quality

Control QA/QC is critical to the success of the project

Very detailed document released (QA/QC version 5, March 28, 2002)

procedures and documents have been updated after the experience gained from building the first feedthroughs

All TIS (CERN Safety) concerns have been addressed (Dec 00)

All information stored in a purpose-built database

material traceability production and reception test results available on the web:

http://particle.phys.uvic.ca/~web-atlas/atlas/feedthroughs/status/