energy audit & energy efficiency improvement program for...
TRANSCRIPT
1
Punjab Cities Governance Improvement Project
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
REPORT Islampura Subdivision, Lahore
September 2015
NEC Consultants (Pvt.) Ltd.
2
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
September 2015 NEC Consultants Pvt. Ltd Perfect SITE, 22 KM Ferozepur Road, Near Gujju Matta Metro Bus Station, Lahore +92-42-35273741-46, www.nec.com.pk [email protected] This study was assigned by The Urban Unit, Punjab
3
DISCLAIMER No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying, recording or information storage and retrieval system, without prior written permission of the USPMSU. A publication of the Urban Sector Planning and Management Services Unit (Private) Limited, the opinion expressed in the document are solely those of the authors and publishing them does not in any way constitute an endorsement of the opinion by the USPMSU.
ACKNOWLEDGEMENTS This report has been prepared by The Urban Unit (Urban Sector Policy & Management Unit), P&D Department, Government of Punjab. The Urban Unit, under the Punjab Cities Governance Improvement Project (PCGIP)-DLI-4 is supporting WASA Lahore for implementing Energy Audit Management Opportunities. Energy management opportunities have been extracted from the energy audits of WASA pumps. The Team Dr. Nasir Javed Engr. Abid Hussainy Engr. Ali Raza Shafqat Ullah Muhammad Rizwan Kashif Shaukat Adnan Khan Editing & Layout By: Ms. Madiha Qamar Printed in Pakistan Copyright: Urban Sector Planning and Management Services Unit (Private) Limited.
4
CONTENTS Contents 4 List of Annexure 4 List of Figures 4 List of Tables 4 List of Acronyms and Abbreviations 5 Glossary 5 1.0 Introduction 7
1.1 Background 7 1.2 Methodology 7 1.3 Scope 8
2.0 Energy Audit Findings 9 2.1 Pumping system efficiency 10 2.2 Electricity consumption trend 11 2.3 Pumping system efficiency improvement potential 12 2.4 Interventions for the improvement of WASA stations 13
LIST OF ANNEXURE
I Energy Audit Reports 2 Selected Pictures
LIST OF FIGURES
I Pumping system efficiency category 11 2 Unit electricity consumption trend 12
LIST OF TABLES
1 Detail of WASAs pumps 8 2 Detail of Islampura subdivision 9 3 Typical overall pumping system efficiency classification 10 4 Detail of motor loading and pumping system efficiency 10 5 Detail of water discharge and electricity consumption 11 6 System energy efficiency potential of pumps 13
7A Interventions & investment required in WASA stations-Islampura Subdivision 14
7B Interventions & investment required in WASA stations-Islampura Subdivision 16
5
LIST OF ACRONYMS AND ABBREVIATIONS
Bhp Brake Horsepower Cusec Cubic Feet per Second Ehp Electrical Horsepower Gpm Gallon Per Minute Hp Horsepower kVA Kilo Volt Ampere kW Kilo Watt kWh Kilo Watt Hour LESCO Lahore Electric Supply Company m/s Meter Per Second m3/hr Cubic Meter Per Hour MCB Fuses or Miniature Circuit Breaker Mm Millimeter MS Mild Steel Psig Pound Per Square Inch (Gauge) RPM Revolution Per Minute TDH Total Dynamic Head VFD Variable Frequency Drive WASA Water and Sanitation Agency Whp Water Horsepower
GLOSSARY
Discharge Pressure
The pressure obtained at center line of pump discharge pipe using a calibrated gauge (psig). Discharge pressure is converted to feet and expressed as “Discharge Head”.
Brake Horsepower
The output horsepower of a motor to a pump; may also be used to refer to the required input horsepower to the pump itself.
Deep Well Turbine Pump
A turbine pump installed inside a well casing below the pumping water level in the well.
Discharge Head Head measured above center line of pump discharge pipe.
Drawdown The measured distance that a well’s water level changes from standing/static level to operating pumping level during observed test conditions.
Dynamic Head The sum of the pressure and the pumping head developed by a pump
Friction Head The head required to overcome the fluid friction in a pipe or water system
Friction Losses
Energy losses associated with moving water against rough surfaces. In water pumping applications, it is the water pressure lost as a result of contact between moving water and a pipeline or open channel.
GPM per Foot Drawdown
The ratio of capacity (GPM) to drawdown feet is useful in determining the well’s performance.
Head Alternate term for pressure. One pound per square inch (psi) = 2.31 feet of water head
Overall Plant The ratio of the water horsepower (the overall output of the plant)
6
or Pumping System Efficiency
to input horsepower (the power input). The overall output can also be defined as the amount of horsepower required to deliver the measured capacity (water gallons per minute) and the measured total head.
Pumping Water Level
The well’s operating water level below center line of discharge pipe as observed during test condition
Static Water Level The well’s water level obtained when pumping plant is at rest.
Suction Head Head measured above center line of pump suction intake. Most often obtained with calibrated bourdon tube pressure gauge (suction pressure) and converted to feet by conversion factor 2.31 ft. water/psi
Suction Lift The distance between pump discharge head and water level.
Total Head
The sum of the water head above and below the center line of the pump discharge pipe. For well applications, the Total Head is the sum of the Discharge Head and the Pumping Water Level. Total head is used in determination of water horsepower and pump performance.
Water Horsepower
The output horsepower of a water pump. It is the combination of flow rate and pressure.
7
1.0 Introduction 1.1 Background Energy Audit & Energy Efficiency Improvement gram Government of the Punjab, Pakistan with financial assistance from the World Bank, is implementing “Punjab Cities Governance Improvement Project (PCGIP)” for strengthening systems for improved planning, resource management, and accountability in five large cities of Punjab i.e. Lahore, Faisalabad, Multan, Gujranwala and Rawalpindi. The project utilizes a result-based approach and, consistent with this focus, the disbursement decisions to the city and its entities are based on achievement of pre-specified results, referred to as Disbursement linked Indicators (DLIs) which reflect priority elements in furthering the Government’s urban agenda, critical at the provincial level, within the existing legislative, regulative and policy framework of the Government. DLIs includes intermediate outcomes, incremental steps and results contributing to improved efficiency, effectiveness, accountability and service delivery during and beyond the project life by building capacities , system and processes . Disbursement Linked Indicator 4 (DLI -4) aims for improvements in own source revenue collection system that encourages the City Local Government (CDGs), Development Authorities (DAs) and Service providers (WASAs) to bring improved systems for revenue enhancement. This DLI is linked with the initiative of WASAs to carry out the Energy Audit for resources conservation and efficiency to improved service delivery, accountability and own source revenue. One of the proposed actions & initiatives to enhance revenue was to conduct energy audit of WASAs to reduce the power cost by various systematic analysis of the energy use and finding out the energy management opportunities. WASAs each year incur significant cost. It was Rs. 4,697 million in 2014 year for energy/Electricity bills, with an installed capacity of approximately 131 MW for 5,663 Million Gallons per Day (water management), which can be reduced through detailed energy audit and implementing its findings. In the context of existing scenario energy audit of WASAs is a technical and efficient way to obtain energy analysis and savings through improvements that optimize pumping systems of tube well stations and disposal stations to operate efficiently with significant cost saving. The Urban Planning and Management Services Unit, Pvt. Ltd. has assigned NEC Consultants Pvt. Ltd to conduct energy audits of WASAs in Punjab in five major cities of Lahore, Rawalpindi, Faisalabad, Multan and Gujranwala. This is the energy audit report of Islampura Subdivision of Lahore city. 1.2 Methodology The primary and secondary sources were used to collect data for different WASAs and pumps installed there. The Urban Unit provided information and contact detail of all the WASAs. An energy audit report template was developed to collect field data from each WASA subdivision. Prior to start the on field measurements of each subdivision, meetings were conducted with the respective WASA management and briefed them about the activity. The technical team then collected data by on field measurements of each pump and recorded in their energy audit report template. On the basis of this energy audit report template, The Urban Unit also developed Android based software to record data of each pump online. This data was also recorded on line in this Android based application. On the basis of field measurements, efficiency of the pumping system was calculated and
8
energy efficiency opportunities were identified. 1.3 Scope The scope of the this assignment is to conduct energy audits of about 1,600 fresh water supply and wastewater disposal pumps installed at different WASA stations in five major cities of Lahore, Rawalpindi, Multan, Faisalabad and Gujranwala. The detail of these pumps is given in Table-1.
Table-1: Detail of WASAs Pumps
WASA Population
Served (Million)
Total Water Connections
Total Sewerage
Connections
Total Supply
Stations
Total Disposal Stations
Total No. of Pump
Sets WASA Lahore 5.48 587,595 583,532 491 99 776
WASA Gujranwala 0.54 29,375 97,236 66 23 112
WASA Faisalabad 1.55 110,452 217,002 87 43 222
WASA Multan 1.2 43,996 175,615 102 21 161
WASA Rawalpindi 1.17 92,468 38,437 362 - 362
Total 9.94 863,886 1,111,822 1,108 186 1,633 The efficiency of each pumping system was evaluated and energy efficiency improvement opportunities were identified for those pumping systems whose efficiencies were not at required level. The detail of reports prepared is as under:
- The energy audit report of each pump was prepared. - On the basis of each pump report, summary report of findings of each WASA
subdivision was prepared. - On the basis of each subdivision summary report, one consolidated report of each city
for energy efficiency improvement opportunities of the WASAs was prepared.
9
2.0 Energy Audit Findings There are 23 WASA water supply stations and 02 wastewater disposal pumps in Islampura Subdivision. The detail of these stations along with pumps installed capacity and actual discharge is given in Table-2:
Table-2: Detail of Islampura Subdivision
# WASA Station
No. of Water Supply Pumps
Installed
Installed Capacity (Cusec)
Actual Discharge (Cusec)
1 Rewaz Garden 01 4.0 3.91 2 Raj Garh Muslim Town 01 2.0 1.56 3 Bilal Park 01 4.0 2.35 4 Sodiwal Quarter 01 2.0 1.71 5 Rustam Park 01 4.0 3.43 6 Firdous Colony 01 4.0 2.30 7 Takia Mahmood Shah 01 2.0 2.60 8 E Block Gulshan Ravi 01 4.0 3.70 9 Moon Market 01 4.0 2.05 10 Sanda Patwar Khana 01 2.0 1.94 11 A Block Gulshan Ravi 01 4.0 2.74 12 Jahangir Park 01 4.0 3.87 13 Raffle Range 01 4.0 2.89 14 Zubair Park 01 4.0 2.64 15 B Block Gulshan Ravi 01 2.0 1.17 16 Malik Munir Park 01 4.0 3.57 17 Nonarian 01 4.0 3.67 18 Sodi Wal Park 01 4.0 1.91 19 Shaira Kot 01 2.0 1.56 20 Babu Sabu Dispensary 01 4.0 4.31 21 G Block Gulshan Ravi 01 4.0 2.89 22 Usman Park 01 4.0 4.06 23 Zubair Park Raj Garh 01 4.0 3.91 Total 23 80.0 64.74 Wastewater Disposal Pumps
24 Fazal Colony Disposal-01 01 2.0 1.96 25 Fazal Colony Disposal-02 01 2.0 2.0 Total 02 4.0 3.96
The installed capacity of WASA tube wells of Islampura Subdivision is 47.65 million m3 per annum whereas actual discharge is 38.56 million m3 per annum, for average 16 hours per day operation and 365 days per year. This actual discharge is about 19% lesser than the installed capacity. The installed capacity of WASA disposal pumps of Islampura Subdivision is 1.78 million m3 per annum whereas actual discharge is 1.76 million m3 per annum, for average 12 hours per day operation and 365 days per year. This actual discharge is about 1% lesser than the installed capacity.
10
2.1 Pumping System Efficiency Pumping plant performance can be classified as “Low”, “Fair”, “Good”, or “Excellent” by referring to the following table, which is based upon the results of thousands of pump tests conducted by Pacific Gas & Electric Company, USA. This classification is used to categorize WASA pumps.
Table-3: Typical Overall Pumping System Efficiency Classification
Motor HP Low Fair Good Excellent 3-7.5 <44.0 44-49.9 50-54.9 >54.9
10 <46.0 46-52.9 53-57.9 >57.9 15 <47.1 48-53.9 54-59.9 >59.9
20-25 <48.0 50-56.9 57-60.9 >60.9 30-50 <52.1 52.1-58.9 59-61.9 >61.9 60-75 <56.0 56-60.9 61-65.9 >65.9 100 <57.3 57.3-62.9 63-66.9 >66.9 150 <58.1 58.1-63.4 63.5-68.9 >68.9 200 <59.1 59.1-63.8 63.9-69.4 >69.4 250 <59.1 59.1-63.8 63.9-69.4 >69.4 300 <60 60-64.0 64.1-69.9 >69.9
Source: Pacific Gas & Electric Company, USA The detail of pumping system efficiency and motor loading of each WASA station is given in Table-4. The calculations for the efficiency determination are given in the energy audit report of each pump in Annexure-1.
Table-4: Detail of Motor Loading and Pumping System Efficiency
WASA Station Motor Load (%)
Pumping System Efficiency (%)
Pumping System Efficiency Rating
Rewaz Garden 83 73 EXCELLENT Takia Mahmood Shah 79 83 EXCELLENT A Block Gulshan Ravi 45 84 EXCELLENT B Block Gulshan Ravi 32 74 EXCELLENT Usman Park 85 71 EXCELLENT Jahangir Park 84 64 GOOD Babu Sabu Dispensary 88 67 GOOD Raj Garh Muslim Town 62 58 FAIR E Block Gulshan Ravi 88 56 FAIR Raffle Range 70 59 FAIR Nonarian 81 61 FAIR G Block Gulshan Ravi 67 60 FAIR Bilal Park 64 43 LOW Sodiwal Quarter 79 51 LOW Rustam Park 144 27 LOW Firdous Colony 57 50 LOW Moon Market 85 32 LOW Sanda Patwar Khana 88 52 LOW Zubair Park 79 48 LOW Malik Munir Park 89 47 LOW Sodi Wal Park 47 53 LOW Shaira Kot 85 42 LOW Zubair Park Raj Garh 87 54 LOW
11
Disposal Pumps Fazal Colony Disposal-02 74 59 GOOD Fazal Colony Disposal-01 78 53 FAIR About 30% of the tube wells are under excellent and good category of pumping system efficiency whereas 70% are under fair and low category as illustrated in Fig-1.
Figure-1: Pumping System Efficiency Category
About 50% each of all the operational disposal pumps are under good and fair category of pumping system efficiency. 2.2 Electricity Consumption Trend The detail of annual water discharge and correspondingly electricity consumption and unit electricity consumption of each WASA station is given in Table-5.
Table-5: Detail of Water Discharge and Electricity Consumption
# WASA Station Annual Water
Discharge (m3)
Annual Electricity Consumption
(kWh)
Unit Electricity Consumption
(kWh/m3) 1 Rewaz Garden 2,330,160 541,335 0.23 2 Raj Garh Muslim Town 934,400 220,174 0.23 3 Bilal Park 1,401,600 413,517 0.29 4 Sodiwal Quarter 1,022,000 277,713 0.27 5 Rustam Park 2,044,000 951,453 0.46 6 Firdous Colony 1,372,400 375,177 0.27 7 Takia Mahmood Shah 1,553,440 277,126 0.17 8 E Block Gulshan Ravi 2,069,550 549,885 0.26 9 Moon Market 1,303,050 599,498 0.46
10 Sanda Patwar Khana 1,011,780 273,310 0.27 11 A block Gulshan Ravi 1,533,000 280,722 0.18 12 Jahangir Park 2,306,800 544,271 0.23 13 Raffle Range 1,722,800 462,660 0.26 14 Zubair Park 1,773,900 585,884 0.33
Excellent 22%
Good 8%
Fair 22%
Low 48%
12
15 B Block Gulshan Ravi 657,000 106,234 0.16 16 Malik Munir Park 2,398,050 660,523 0.27 17 Nonarian 2,463,750 601,736 0.24 18 Sodi Wal Park 1,138,800 313,528 0.27 19 Shaira Kot 876,000 280,172 0.31 20 Babu Sabu Dispensary 2,730,200 617,963 0.22 21 G Block Gulshan Ravi 1,615,125 419,047 0.25 22 Usman Park 2,272,125 526,547 0.23 23 Zubair Park Raj Garh 2,330,160 571,279 0.24 Total 38,860,090 10,449,754 0.26 Disposal Pumps
24 Fazal Colony Disposal-01 1,314,000 76,621 0.05 25 Fazal Colony Disposal-02 1,340,280 73,054 0.05 Total 2,654,280 149,675 0.05 Total annual energy cost of Islampura subdivision is about Rs. 138 million. The unit electricity consumption trend for each WASA station is illustrated in Fig-2. From figure, it is clear that 0.20 kWh/m3 is considered to be optimum figure for water supply pumps. This figure is based on NEC experience of conducting water turbine audits of different industries. WASA audits also reflect the similar figure.
Figure-2: Unit Electricity Consumption Trend
About 87% of the tube wells consume electricity more than the 0.20 kWh/m3. In case if all the 23 tube wells consume optimum electricity, then annually Rs. 35 million (26%) can be saved. 2.3 Pumping System Efficiency Improvement Potential The 16 tube wells and 01 disposal pumps having system efficiency in the category of FAIR to LOW, as given in Table-4, have the potential of efficiency improvement into the GOOD category. Table-6 gives detail of this efficiency improvement potential.
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
kWh/m3
Optimum
13
Table-6: System Energy Efficiency Potential of Pumps
WASA Station Existing Pumping Efficiency
(%)
Improved Pumping Efficiency
(%)
Annual
(kWh)
Saving
(Rs)
Impeller
Adjustment /Repair &
Maintenance
Intervention
Motor Replace
Pump Replace
Raj Garh Muslim Town
58 65 23,061 299,789 ×
Bilal Park 43 65 139,698 1,816,075 × Sodiwal Quarter 51 65 60,878 791,418 × Rustam Park 27 65 557,507 7,247,597 × Firdous Colony 50 65 87,036 1,131,465 × E Block Gulshan Ravi
56 65 73,765 958,943 ×
Moon Market 32 65 304,122 3,953,591 × Sanda Patwar Khana
52 65 56,424 733,514 ×
Raffle Range 59 65 44,719 581,341 × Zubair Park 47 65 157,910 2,052,827 × Malik Munir Park
47 65 182,066 2,366,861 ×
Nonarian 61 65 35,448 460,821 × Sodi Wal Park 53 65 56,043 728,557 × Shaira Kot 42 65 98,721 1,283,374 × G Block Gulshan Ravi
60 65 30,634 398,238 ×
Zubair Park Raj Garh
54 65 93,793 1,219,306 ×
Fazal Colony Disposal-01
53 57 4,908 63,806 ×
Total 2,006,733 26,087,523 2.4 Interventions for the Improvement of WASA Stations Energy audit activity of Islampura subdivision revealed that there are certain areas of electrical, mechanical and housekeeping which needs improvement. Table-7 presents detail of interventions and investment requirement in each WASA station for better, efficient and safe operation of WASA station. About Rs. 19.73 million are required to improve WASA stations of Islampura subdivision, Lahore.
14
Table-7A: Interventions & Investment Required in WASA Stations- Islam Pura Subdivision
Intervention WASA Stations Rewaz Muslim
Town Bilal Park
Sodiwal Quart.
Rustom Firdous Takia Mahm.
E Block
Moon Sanda Patwar
G Block
A Block Jahangir
Electrical Install VFD × × × × × × × × × × × × × Install hour meter × × × × × × × × × × × × × Replace ampere meter × × × × × × Replace volt meter × × × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay Install/replace motor terminal box /Improve open and loose motor connection
× × × × × ×
Improve panel condition × × × × × × Improve wiring condition × × × × × × Replace de-rated capacitors Relocate panel away from bore hole × × × × × × × × × × Replace electrical motor Install fan in the panel Replace PFI HRC fuses Replace PFI display meter Correct date & time of electrical meter
Replace/correct electrical meter × Replace change over Replace main circuit breaker Mechanical Replace damaged/install new flow meter
× × × × × × × × × × × × ×
15
Intervention WASA Stations Rewaz Muslim
Town Bilal Park
Sodiwal Quart.
Rustom Firdous Takia Mahm.
E Block
Moon Sanda Patwar
G Block
A Block Jahangir
Replace damaged/install new digital pressure gauge
× × × × × × × × × × × × ×
Control gland leakage × × × × × × × × × × × × × Make operational/install new chlorinator
× × × × × × × × ×
Maintain ratchet plate × × × × × Adjust impeller × × × × × × × Repair & maintenance of pump × × Replace existing pumping system × Maintain/install new non return valve
×
Housekeeping Improve general housekeeping × × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline Maintain monthly record of fuel consumption
Station Wise Investment (M. Rs)
0.86 0.48 0.84 0.48 0.80 0.74 0.44 0.80 3.7 0.74 0.83 0.74 0.74
Annual Saving (M. Rs) 0.29 1.8 0.79 7.2 1.1 0.95 3.9 0.73 0.39 Payback (Year) 1.65 0.46 0.60 0.11 0.84 0.94 1.01 2.12
16
Table-7B: Interventions & Investment Required in WASA Stations- Islam Pura Subdivision Intervention WASA Stations Raffle Zubair
Park B
Block Malik Munir
Usman Nonarian Zubair Raj
Sodi Park
Shera Kot
Babu Sabu
Fazal Disp-
01
Fazal Disp-
02
Electrical Install VFD × × × × × × × × × × × Install hour meter × × × × × × × × × × × × Replace ampere meter × × × × × × × × × × Replace volt meter × × × × × × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay Install/replace motor terminal box /Improve open and loose motor connection
× × × × ×
Improve panel condition × × × × × Improve wiring condition × × × × × × × Replace de-rated capacitors Relocate panel away from bore hole × × × × × × × Replace electrical motor Install fan in the panel Replace PFI HRC fuses Replace PFI display meter Correct date & time of electrical meter
Replace/correct electrical meter Replace change over Replace main circuit breaker Mechanical Replace damaged/install new flow meter
× × × × × × × × × × × ×
Replace damaged/install new digital × × × × × × × × × × × ×
17
Intervention WASA Stations Raffle Zubair
Park B
Block Malik Munir
Usman Nonarian Zubair Raj
Sodi Park
Shera Kot
Babu Sabu
Fazal Disp-
01
Fazal Disp-
02
pressure gauge Control gland leakage × × × × × × × × × Make operational/install new chlorinator
× × × × × ×
Maintain ratchet plate × × × × × × × Adjust impeller × × × × × × × × Repair & maintenance of pump × × × Replace existing pumping system Maintain/install new non return valve
×
Housekeeping Improve general housekeeping × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline Maintain monthly record of fuel consumption
Station Wise Investment (M. Rs)
0.74 0.75 0.45 0.85 0.78 0.80 0.74 0.77 0.53 0.83 0.15 0.15
Annual Saving (M. Rs) 0.58 2.0 2.3 0.46 1.2 0.72 1.2 0.06 Payback (Year) 1.27 0.37 0.36 1.73 0.61 1.06 0.44 2.5 Total Investment of Subdivision (M.Rs) = 19.73
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station REWAZ GARDEN
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure NA psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 5020
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues fair
Gland Leakage YES
Non Return Valve faulty
Chlorinator Faulty
Flow Meter Installed but faulty
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Fair
Housekeeping Fair
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate faulty
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 399 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.19 m/sec
Pressure
i) Pressure at Discharge Side of Pump 22 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 386 385.5 387
ii) Ampere 150 175 149
iii) Power Factor 0.81 0.86 0.92
iv) Appearant Power (kVA) 101.4 100.6 98.8
v) Running Power (kW) 92.2
vi) Reactive Power (kVAr) 50.5 62 64
vi) Motor Working on Loading Basis 83 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 50.82 ft
vi) Discharge Side Frictional Head 11.76 ft
vii) Dynamic Discharge Head (v+vi) 62.58 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 203.62 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 109.31
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,128
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 90.33 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 123.59 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 72.50 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 73.09 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 6,384 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,330,160 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 541,335 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,037,357 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 73%. For pump attached with 150 HP motor, efficiency <69 is considered to be EXCELLENT. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 863,000 PKR
VFD is recommendedNo VFD installed
Attached water flow meter is faulty New water flow meter is recommended
No PFI pannel is installed PFI panel of 50 kVAR is recommended
Digital pressure guage is recommendedNo pressure guage is installed
Rectify the gland leakage issueLeakage at the pump gland
Chlorinator is not operational Attach chlorinator and make it operationalize
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station RAJ GHAR MUSLIM TOEN
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 8 psig
6 Motor Nameplate Data NA
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) Volts
iv) Current (Ampere)
v) Power Factor (Cos ɸ)
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency C/S
viii) Insulation Class
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 33224
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kVAr
Panel Condition/Issues Fair. Faulty A and V meter
Gland Leakage yes
Non Return Valve ok
Chlorinator No
Flow Meter No
Pressure Gauge No
Bore Hole in Front of PanYES
Wiring Fair
Housekeeping Fair
Motor Terminal Open connection without terminal box
Foundation/Civil work ok
Ratchet Plate Faulty
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter 638 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 160 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.37 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 353.6 362.2 373
ii) Ampere 79.2 68.7 77.5
iii) Power Factor 0.76 0.79 0.85
iv) Appearant Power (kVA) 50.7 42.8 47.3
v) Running Power (kW) 37.5
vi) Reactive Power (kVAr) 31 26.2 26.6
vi) Motor Working on Loading Basis 62 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 4.91 ft
vii) Dynamic Discharge Head (v+vi) 23.39 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 164.43 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 43.83
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 838
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 29.25 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 50.27 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 23.48 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.19 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.24 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 2,560 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 934,400 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 220,174 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,862,265 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 179 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 10.47 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 23,061 kWh/yr
xxxi) Annual Financial Saving on Pumping 299,789 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 58%. For pump attached with 80 HP motor, efficiency 56-60 % is considered to be fair. To improve its efficiency upto 65 % which is good , this pumping system requires ampeller adjustment. This intervention will save 299,789 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 484,000 PKR
Defective A and V meter Install new A and V meter
There is no pressure gauge installed at discahrge pipeline Digital pressure guage is recommended
No flow meter is available Water flow meter is recommended
No chlorinator is available Chlorinator is recommended
PFI panel control circuit is defective
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
Control leakageLeakage at the pump gland
No VFD installed VFD is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station BILAL PARK
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Picture
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 240 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 44717
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not Installed
Panel Condition/Issues Poor. ampere meter not working
Gland Leakage yes
Non Return Valve ok
Chlorinator Demaged
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Poor
Housekeeping Fair
Motor Terminal Open connections without terminal box
Foundation/Civil work ok
Ratchet Plate faulty
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter 797 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 240 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.32 m/sec
Pressure
i) Pressure at Discharge Side of Pump 3 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 383 378 377
ii) Ampere 161.5 175 174
iii) Power Factor 0.84 0.88 0.83
iv) Appearant Power (kVA) 105 99.6 107
v) Running Power (kW) 70.43
vi) Reactive Power (kVAr) 52.6 46.7 58.2
vi) Motor Working on Loading Basis 64 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 90.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 6.93 ft
vi) Discharge Side Frictional Head 4.31 ft
vii) Dynamic Discharge Head (v+vi) 11.24 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 152.28 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 65.75
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,087
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 40.64 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 94.41 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.61 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 43.04 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.30 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 3,840 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,401,600 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 413,517 kWh/yr
xxv) Annual Energy Expenditure on Pumping 5,375,716 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 362 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.20 kWh/m3
xxix) Potential of Energy Reduction 33.78 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 139,698 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,816,075 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 43%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment, maintenance and repair. This intervention will save 1,816,075 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 844,000 PKR
Control leakage for efficiency improvementLeakage at the pump gland was observed
No VFD installed VFD is recommended
There is no pressure gauge installed at discahrge pipeline Digital pressure guage is recommended
Water flowmeter is not available New water flow meter is recommended
NO PFI is available Install PFI of 50 kVAr
New A and V meter are recommendedDefective A and V meter
Improve wiring conditionElectrical wiring is poor
Chlorinator is demaged New chlorinator is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station SODIWAL QUARTER
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 100
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB12B/5
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 59.5
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-10291
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 175 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 20518.754
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kVAr
Panel Condition/Issues GOOD
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator NOT OPERATIONAL
Flow Meter Magnetic Type (Faulty)
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring fair
Housekeeping fair
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate ok
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter 683 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 175 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.50 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 390 390.9 387
ii) Ampere 89.2 91.6 84.7
iii) Power Factor 0.77 0.83 0.87
iv) Appearant Power (kVA) 56.7 62.3 59.8
v) Running Power (kW) 47.3
vi) Reactive Power (kVAr) 35.5 33.85 32.3
vi) Motor Working on Loading Basis 78.98 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,480 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 90
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 5.86 ft
vii) Dynamic Discharge Head (v+vi) 24.34 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 165.38 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 47.94
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 873
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 32.18 hp
xiv) Brake Horsepower (bhp) (OEM Data) 59.5 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 63.40 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 54.08 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 50.75 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 2,800 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,022,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 277,713 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,610,271 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 224 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 21.92 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 60,878 kWh/yr
xxxi) Annual Financial Saving on Pumping 791,418 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 50.7%. For pump attached with 80 HP motor, efficiency <58% is considered to be LOW. This pumping system requires impeler adjustment to increase its efficiency to 65% which is good. This intervention will save 791,418 rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 483,000 PKR
Rectify pump gland leakage issueLeakage at the pump gland
No VFD installed
There is no pressure gauge installed at discahrge pipeline Digital pressure guage is recommended
Magnetic flow meter was available but non operational New water flow meter is recommended
Defective PFI control unit
Chlorinator is not operational Attach new chlorinator
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station RUSTAM PARK (GR)
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Picture
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 200
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture1997
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 119
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209.5
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 2015.7
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues Poor. Faulty A and V meter
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator NOT OPERATIONAL
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring poor
Housekeeping fair
Motor Terminal Open motor connections without terminal box
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter 797 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 350 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.92 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 385 388.2
ii) Ampere 158.5 193.6
iii) Power Factor 0.83 0.8
iv) Appearant Power (kVA) 105.2 131.6
v) Running Power (kW) 162
vi) Reactive Power (kVAr) 73.5 58.2
vi) Motor Working on Loading Basis 144 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 95.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 0 ft
vi) Discharge Side Frictional Head 9.07 ft
vii) Dynamic Discharge Head (v+vi) 9.07 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 150.11 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 95.88
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,327
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 58.42 hp
xiv) Brake Horsepower (bhp) (OEM Data) 119 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 217.16 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 49.09 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 26.90 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.47 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 5,600 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,044,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 951,153 kWh/yr
xxv) Annual Energy Expenditure on Pumping 12,364,987 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 846 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.19 kWh/m3
xxix) Potential of Energy Reduction 58.61 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 557,507 kWh/yr
xxxi) Annual Financial Saving on Pumping 7,247,597 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 26%. For pump attached with 150 HP motor, efficiency <57% is considered to be LOW. This pumping system requires motor replacement. Also the motor is over loaded (144%). After this intervention 7,247,597 Rs annually will be saved
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 804,000 PKR
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Digital pressure guage is recommended
Control leakageLeakage at the pump gland
Its recommended tha to replace the Volt meterVolt meter not Operational
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
Motor is over loaded Replace motor
Improve wiring conditionWiring is poor. Flashed panel
Chlorinator is demaged Attach new chlorinator
No water flow meter is available New water flow meter is recommended
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station FIRDOUS COLONY GR
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture1991
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 119.59
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 10 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209.5
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 5505.63
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues Worst pannel,V & A meter not working
Gland Leakage moderate leakage
Non Return Valve
Chlorinator ok
Flow Meter no
Pressure Gauge no
Bore Hole in Front of Panno
Wiring open wiring
Housekeeping OK
Motor Terminal open and loose motor connections
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 235 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.29 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 387.4 386.7 385.9
ii) Ampere 160.4 184.5 94.5
iii) Power Factor 0.84 0.84 0.89
iv) Appearant Power (kVA) 79.23 123 61
v) Running Power (kW) 63.9
vi) Reactive Power (kVAr) 33.4 63.6 61.2
vi) Motor Working on Loading Basis 56.8 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1494 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 18.48 ft
vi) Discharge Side Frictional Head 4.13 ft
vii) Dynamic Discharge Head (v+vi) 22.61 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 163.65 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 64.38
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,050
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 42.76 hp
xiv) Brake Horsepower (bhp) (OEM Data) 119.59 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 85.66 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 35.76 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.92 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 3,760 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,372,400 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 375,177 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,877,300 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 306 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 23.20 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 87,036 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,131,465 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 49.92%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment, maintenance and repair. This intervention will save 1,131,465 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 743,000 PKR
Improve housekeepingHousekeeping is poor
Improve wiring conditionWiring is not in safe condition
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
Its recommended tha to replace the Volt meterVolt meter not Operational
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station TAKYA MEHMOOD SHAH
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB12B/5
Serial
iii) Certification Mark
iv) Year of Manufacture2009
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 59.5
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 8 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 21626
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kVAr
Panel Condition/Issues GOOD
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator
Flow Meter defective
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Good
Housekeeping OK
Motor Terminal OK
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 266 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.28 m/sec
Pressure
i) Pressure at Discharge Side of Pump 10 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 385.9 384.5 386
ii) Ampere 86.7 89.3 88.7
iii) Power Factor 0.8 0.79 0.8
iv) Appearant Power (kVA) 58 59.4 59.3
v) Running Power (kW) 47.2
vi) Reactive Power (kVAr) 34.8 35.7 35.1
vi) Motor Working on Loading Basis 78.7 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,475 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 88.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 23.1 ft
vi) Discharge Side Frictional Head 13.36 ft
vii) Dynamic Discharge Head (v+vi) 36.46 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 177.50 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 72.87
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,020
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 52.50 hp
xiv) Brake Horsepower (bhp) (OEM Data) 59.5 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 63.27 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 88.23 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 82.97 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.18 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 4,256 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,553,440 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 277,126 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,602,638 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 83%. For pump attached with 80 HP motor, efficiency of 83% is considered to be EXCELLENT. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 435,000 PKR
Control leakageLeakage at the pump gland
Improve housekeepingHousekeeping is poor
NO water flow meter Attach Water Flow meter and make it operationalize
No VFD installed Install VFD
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station E BLOCK GULSHAN RAVI
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2002
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 116.96
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 12 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 198633& 160632
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 30 kVAr not operational
Panel Condition/Issues Poor, ampere meter not working
Gland Leakage moderate leakage
Non Return Valve
Chlorinator No
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Poor
Housekeeping OK
Motor Terminal No terminal box
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 378 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.07 m/sec
Pressure
i) Pressure at Discharge Side of Pump 12 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 410.3 410.8 413
ii) Ampere 166 170 168.7
iii) Power Factor 0.78 0.8 0.8
iv) Appearant Power (kVA) 112 120 118
v) Running Power (kW) 99.9
vi) Reactive Power (kVAr) 71.2 64.4 69.4
vi) Motor Working on Loading Basis 88 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.25
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 27.72 ft
vi) Discharge Side Frictional Head 10.56 ft
vii) Dynamic Discharge Head (v+vi) 38.28 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 179.32 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 103.55
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,207
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 75.37 hp
xiv) Brake Horsepower (bhp) (OEM Data) 116.96 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 133.91 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 64.44 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 56.28 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 5,670 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,069,550 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 549,885 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,148,508 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 437 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
xxix) Potential of Energy Reduction 13.41 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 73,765 kWh/yr
xxxi) Annual Financial Saving on Pumping 958,943 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 56.285%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment. This intervention will save 958,943 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 803,500 PKR
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station MOON MARKET
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 17 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2009
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 14 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 52464.43
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr AND operational
Panel Condition/Issues GOOD
Gland Leakage moderate leakage
Non Return Valve
Chlorinator ok
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring OK
Housekeeping OK
Motor Terminal OK
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 210 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.15 m/sec
Pressure
i) Pressure at Discharge Side of Pump 14 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 405.9 401.2
ii) Ampere 185.8 197.7
iii) Power Factor 0.73 0.71
iv) Appearant Power (kVA) 129 135.6
v) Running Power (kW) 96.1
vi) Reactive Power (kVAr) 91.9 91.5
vi) Motor Working on Loading Basis 85.4 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 32.34 ft
vi) Discharge Side Frictional Head 3.31 ft
vii) Dynamic Discharge Head (v+vi) 35.65 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 176.69 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 57.53
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 910
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 41.26 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 128.82 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 33.11 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 32.03 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.46 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 17 hrs
xxi) Daily Pump flow 3,570 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,303,050 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 599,498 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,793,472 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 426 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
xxix) Potential of Energy Reduction 50.73 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 304,122 kWh/yr
xxxi) Annual Financial Saving on Pumping 3,953,591 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 32.03%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires pump to be replaced. This intervention will save Rs. 3,953,591 per year.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 3,743,000 PKR
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
No VFD installed Install VFD
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station SANDA PATWAR KHANA
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture1997
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 118.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 10 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 113
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,470 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 30082.79
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant
Panel Condition/Issues GOOD
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator No
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring OK
Housekeeping OK
Motor Terminal open and loose motor connections
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 198 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.09 m/sec
Pressure
i) Pressure at Discharge Side of Pump 10 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 388.4 381.9 381.4
ii) Ampere 95 117.4 110
iii) Power Factor 0.76 0.81 0.65
iv) Appearant Power (kVA) 69 79 73
v) Running Power (kW) 53.2
vi) Reactive Power (kVAr) 40.7 45.7 56.4
vi) Motor Working on Loading Basis 88.6 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,470 RPM
ii) Speed of Pump Impeller 1492 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 23.1 ft
vi) Discharge Side Frictional Head 2.95 ft
vii) Dynamic Discharge Head (v+vi) 26.05 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 167.09 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 54.24
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 948
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.78 hp
xiv) Brake Horsepower (bhp) (OEM Data) 118.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 71.31 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 31.02 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 51.58 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 2,772 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,011,780 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 273,310 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,553,025 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 250 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxix) Potential of Energy Reduction 20.64 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 56,424 kWh/yr
xxxi) Annual Financial Saving on Pumping 733,514 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 44.45% For pump attached with 80 HP motor, efficiency <58% is considered to be LOW. This pumping system requires impeller adjustment to increase its efficiency to 65% which is good. This intervention will save Rs. 733,514 annually.
12 Issues & Recommendations
ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
12 Financial Analysis / Indicators
Estimated Investment for Improvement Plan 743,000 PKR
Attach chlorinator and make it operationalize
Install digital pressure gauge at discahrge pipeline
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
No VFD installed Install VFD
Improve housekeepingHousekeeping is poor
There is no pressure gauge installed at discahrge pipeline
Chlorinator is not operational
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station G Block Gulshan Ravi
ii) Name of Subdivision Islam Pura , Lahore
iii) Operator Name & Contact N/A
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model B. 14 B/4 Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 119 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 13 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 25453.52
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Poor
Gland Leakage moderate leakage
Non Return Valve
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of Panno
Wiring Poor
Housekeeping Not good
Motor Terminal Open and lose motor connections
Foundation/Civil work ok
Ratchet Plate
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 295 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.53 m/sec
Pressure
i) Pressure at Discharge Side of Pump 13 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 365.3 369.5 377.5
ii) Ampere 150 132.2 133
iii) Power Factor 0.85
iv) Appearant Power (kVA) 88.73
v) Running Power (kW) 76.13
vi) Reactive Power (kVAr) 45.06
vi) Motor Working on Loading Basis 67.67 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1,467 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 30.03 ft
vi) Discharge Side Frictional Head 16.38 ft
vii) Dynamic Discharge Head (v+vi) 46.41 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 187.45 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 79.20
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,044
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 61.48 hp
xiv) Brake Horsepower (bhp) (OEM Data) 119 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 102.05 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 51.67 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 60.25 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.26 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 4,425 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,615,125 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 419,047 kWh/yr
xxv) Annual Energy Expenditure on Pumping 5,447,607 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 318 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.24 kWh/m3
xxix) Potential of Energy Reduction 7.31 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 30,634 kWh/yr
xxxi) Annual Financial Saving on Pumping 398,238 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 60.25%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment. This intervention will save 398,238 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 835,000 PKR
It is recommended to close motor connections in terminal box.Open and lose motor connections.
No flow meter install new flow meter
Attached water flow meter is not working
Attach new water flow meter and properly record 24 hour flow reading. In case of variation in the water flow, the resaons should be investigated and problems be rectified
PFI panel is not installed Install PFI panel
Control leakageLeakage at the pump gland
Provide proper support at the discahrge pipelineThere is no proper support for discahrge pipeline
No VFD installed Install VFD
Pump needs impeller adjustment to increase water flow rate Adjust impellers
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station A BLOCK GULSHAN RAVI
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2009
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 14 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 388 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.85
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues Execellent
Gland Leakage moderate leakage
Non Return Valve
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Ok
Housekeeping OK
Motor Terminal OK
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 280 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.53 m/sec
Pressure
i) Pressure at Discharge Side of Pump 17 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 376.9 374.4 383.4
ii) Ampere 95 110.4 96
iii) Power Factor 0.7 0.78 0.83
iv) Appearant Power (kVA) 62.8 71.9 63.4
v) Running Power (kW) 51
vi) Reactive Power (kVAr) 42.4 44.8 34
vi) Motor Working on Loading Basis 45.1 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 90.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 39.27 ft
vi) Discharge Side Frictional Head 5.84 ft
vii) Dynamic Discharge Head (v+vi) 45.11 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 186.15 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 76.71
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,010
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 57.95 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 68.36 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 46.51 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 84.77 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.18 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 4,200 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,533,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 280,722 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,649,388 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 84.77%. For pump attached with 150 HP motor, efficiency above 69% is considered to be EXCELLENT. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 735,000 PKR
Control leakageLeakage at the pump gland
No VFD installed Install VFD
Improve housekeepingHousekeeping is poor
NO water flow meter Attach Water Flow meter and make it operationalize
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station JAHANGIR PARK
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 300
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2007
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 117.8
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-11318
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 12 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 101662
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAr
Panel Condition/Issues Poor. Ampere not working
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator NOT OPERATIONAL
Flow Meter Yes
Pressure Gauge no
Bore Hole in Front of Panel
Wiring poor
Housekeeping poor
Motor Terminal OK
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 395 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.17 m/sec
Pressure
i) Pressure at Discharge Side of Pump 12 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 410.2 412.3 414.6
ii) Ampere 202.8 193 193.3
iii) Power Factor 0.69 0.65 0.71
iv) Appearant Power (kVA) 144 138 94.6
v) Running Power (kW) 92.7
vi) Reactive Power (kVAr) 104 104 67.5
vi) Motor Working on Loading Basis 84.2 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 95.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 27.72 ft
vi) Discharge Side Frictional Head 11.52 ft
vii) Dynamic Discharge Head (v+vi) 39.24 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 180.28 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 108.21
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,229
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 79.18 hp
xiv) Brake Horsepower (bhp) (OEM Data) 117.8 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 124.26 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 67.21 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 63.72 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.24 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 6,320 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,306,800 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 544,271 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,075,520 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 64%. For pump attached with 150 HP motor, efficiency of 64% is considered to be GOOD. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 743,000 PKR
Control leakageLeakage at the pump gland
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflectedPFI pannel not oprational
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station RAFFLE RANGE
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 10 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 388 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.85
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 38703
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAR non operational
Panel Condition/Issues Poor .V & A meter not working
Gland Leakage ok
Non Return Valve ok
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring poor .open wiring
Housekeeping OK
Motor Terminal No terminal box
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 295 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.62 m/sec
Pressure
i) Pressure at Discharge Side of Pump 18 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 385 387 389
ii) Ampere 143 161 167
iii) Power Factor 0.82 0.78 0.72
iv) Appearant Power (kVA) 106.3 100 100.2
v) Running Power (kW) 78.8
vi) Reactive Power (kVAr) 57.2 66.8 68.1
vi) Motor Working on Loading Basis 70.1 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1478 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 41.58 ft
vi) Discharge Side Frictional Head 6.47 ft
vii) Dynamic Discharge Head (v+vi) 48.05 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 189.09 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 80.82
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,045
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 62.02 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 105.63 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 105.63 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.72 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.27 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 16 hrs
xxi) Daily Pump flow 4,720 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,722,800 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 462,660 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,014,574 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 327 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.24 kWh/m3
xxix) Potential of Energy Reduction 9.67 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 44,719 kWh/yr
xxxi) Annual Financial Saving on Pumping 581,341 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 58%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment. This intervention will save Rs. 581,341 annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 735,000 PKR
Control leakageLeakage at the pump gland
No VFD installed Install VFD
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station ZUBAIR PARK
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 300
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 388 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 40025 & 5986
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues Good ,Ampere meter not working
Gland Leakage moderate leakage
Non Return Valve not working
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring ok
Housekeeping fair
Motor Terminal OK
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 270 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.48 m/sec
Pressure
i) Pressure at Discharge Side of Pump 18 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 413.2 408.7 409
ii) Ampere 182.2 199 182
iii) Power Factor 0.7 0.66 0.62
iv) Appearant Power (kVA) 130 140 130
v) Running Power (kW) 88.7
vi) Reactive Power (kVAr) 92.5 105 101
vi) Motor Working on Loading Basis 78.8 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 95.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 41.58 ft
vi) Discharge Side Frictional Head 5.44 ft
vii) Dynamic Discharge Head (v+vi) 47.02 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 188.06 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 73.97
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 984
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 56.46 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 118.90 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 45.31 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 47.48 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.33 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 4,860 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,773,900 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 585,884 kWh/yr
xxv) Annual Energy Expenditure on Pumping 7,616,488 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 370 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.24 kWh/m3
xxix) Potential of Energy Reduction 26.95 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 157,910 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,052,827 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 47.48%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment, maintenance and repair. This intervention will save 2,052,827 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 755,500 PKR
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Control leakageLeakage at the pump gland
Its recommended tha to replace the Ampere meterAmpere meter not Operational
No VFD installed Install VFD
Improve housekeepingHousekeeping is poor
replace NRV non return valve not operational
NO water flow meter Attach Water Flow meter and make it operationalize
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station B BLOCK GULSHAN RAVI
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 58.6
BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig check
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 115
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,470 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 5866.28
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kVAr
Panel Condition/Issues Fair
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator No
Flow Meter no
Pressure Gauge no
Bore Hole in Front of Panel
Wiring Poor
Housekeeping Poor
Motor Terminal open motor cables
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 120 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.03 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 394.7 388 397
ii) Ampere 42.4 53.5 42.4
iii) Power Factor 0.48 0.62 0.72
iv) Appearant Power (kVA) 20.9 36 29.2
v) Running Power (kW) 19.3
vi) Reactive Power (kVAr) 25.3 28.2 19 101
vi) Motor Working on Loading Basis 32.1 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,470 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 0 ft
vi) Discharge Side Frictional Head 2.79 ft
vii) Dynamic Discharge Head (v+vi) 2.79 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 143.83 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 32.87
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 803
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 19.19 hp
xiv) Brake Horsepower (bhp) (OEM Data) 58.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 25.87 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.75 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 74.18 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.16 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 1,800 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 657,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 106,234 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,381,043 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 74.18%. For pump attached with 80 HP motor, efficiency above 65.9% is considered to be EXCELLENT. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 473,500 PKR
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
Its recommended tha to replace the Ampere meterAmpere meter not Operational
No VFD installed Install VFD
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station MALIK MUNIR PARK
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 300
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 116.96
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 209
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,480 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 6969.56
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues Fair,Ampere meter not working
Gland Leakage
Non Return Valve
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring poor
Housekeeping fair
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 365 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.00 m/sec
Pressure
i) Pressure at Discharge Side of Pump 2 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 397 398.5 397
ii) Ampere 175 173 166
iii) Power Factor 0.85 0.86 0.89
iv) Appearant Power (kVA) 110.2 118.3 114.2
v) Running Power (kW) 100
vi) Reactive Power (kVAr) 57.6 60.4 53.8
vi) Motor Working on Loading Basis 88.8 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,480 RPM
ii) Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 90.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 4.62 ft
vi) Discharge Side Frictional Head 9.86 ft
vii) Dynamic Discharge Head (v+vi) 14.48 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 155.52 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 99.99
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,320
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 63.11 hp
xiv) Brake Horsepower (bhp) (OEM Data) 116.96 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 134.05 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 53.96 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 47.08 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.28 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 6,570 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,398,050 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 660,523 kWh/yr
xxv) Annual Energy Expenditure on Pumping 8,586,796 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 65 %
xxvii) Water Flow after Efficiency Improvement 504 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.20 kWh/m3
xxix) Potential of Energy Reduction 27.56 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 182,066 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,366,861 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 47.08%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment, maintenance and repair. This intervention will save 2,366,861 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 845,500 PKR
Improve housekeepingHousekeeping is poor
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
Its recommended tha to replace the Ampere meterAmpere meter not Operational
No VFD installed Install VFD
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Usman Park
ii) Name of Subdivision Islam Pura , Lahore
iii) Operator Name & Contact N/A
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model B. 14 B/4 Serial
iii) Certification Mark
iv) Year of Manufacture 2009
v) Flowrate (Q) 4 Cusec 408 m3/hr
vi) Head (H) 210 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6 BHP
ix) Speed (n) 1,450 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 5080.61
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50kvar(operational)
Panel Condition/Issues Average
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of Panno
Wiring Fair
Housekeeping
Motor Terminal
Foundation/Civil work ok
Ratchet Plate ok
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 415 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 3.55 m/sec
Pressure
i) Pressure at Discharge Side of Pump 10 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 388.5 389.5 387.2
ii) Ampere 177 168 170.2
iii) Power Factor 0.83
iv) Appearant Power (kVA) 115.5
v) Running Power (kW) 95.66
vi) Reactive Power (kVAr) 64.59
vi) Motor Working on Loading Basis 85.03 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller 1,467 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 16.4 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 23.1 ft
vi) Discharge Side Frictional Head 32.10 ft
vii) Dynamic Discharge Head (v+vi) 55.20 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 196.24 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 111.42
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,196
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 90.55 hp
xiv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 128.23 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 72.67 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 70.61 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 15 hrs
xxi) Daily Pump flow 6,225 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,272,125 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 526,547 kWh/yr
xxv) Annual Energy Expenditure on Pumping 6,845,108 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 70.61%. For pump attached with 150 HP motor, efficiency <69 is considered to be EXCELLENT. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 785,500 PKR
Voltmeter is malfunctioning Replace voltmeter meter
Control leakageLeakage at the pump gland
Provide proper support at the discahrge pipelineThere is no proper support for discahrge pipeline
No VFD installed Install VFD
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Chlorinator is not avaialble Attach chlorinator and make it operationalize
Attached water flow meter is not working Attach new water flow meter
1 Pumping Station Information
Picture
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station NONARIA
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 200
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 1704.84
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr
Panel Condition/Issues GOOD,Volt meter not working
Gland Leakage moderate leakage
Non Return Valve
Chlorinator
Flow Meter
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring ok
Housekeeping Fair
Motor Terminal ok
Foundation/Civil work ok
Ratchet Plate
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 375 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.06 m/sec
Pressure
i) Pressure at Discharge Side of Pump 12 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 357.2 356.7 344.4
ii) Ampere 164 195 185.7
iii) Power Factor 0.8 0.76 0.85
iv) Appearant Power (kVA) 101.3 120.4 116.7
v) Running Power (kW) 91.1
vi) Reactive Power (kVAr) 59.9 75.6 58.2
vi) Motor Working on Loading Basis 81 %
Oversize Undersize Properly Sized
i) Speed
ii) Speed of Motor 1,488 RPM
Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.8
i) Thermal Imaging
Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Calculat Electric Panels
10 i)
ii) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
iii) Static Suction Head (Only for WW Pump) ft
iv) Suction Side Frictional Head (Only for WW Pump) ft
v) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
vi) Discharge Head (Pressure Gauge) 27.72 ft
vii) Discharge Side Frictional Head 10.40 ft
viii) Dynamic Discharge Head (v+vi) 38.12 ft
ix) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 179.16 ft
x) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 102.73
xi) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,203
500-10,000, standard, 2,000-3,000 high efficiency
xii) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xiii) Deviation of actual flow from the pump curve flow %
xiv) Water Horsepower (whp) (TDH x Actual Measured Flow) 74.70 hp
xv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xvi) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 122.12 hp
xvii) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 59.95 %
Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 61.17 %
xviii)
xix) Existing Specific Pumping Energy (En(pumping01)) 0.24 kWh/m3
xx) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xxi) Daily Operational Time of Pump 18 hrs
xxii) Daily Pump flow 6,750 m3/day
xxiii) Annual working days 365 days
xxiv) Annual Pump flow 2,463,750 m3/yr
xxv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 601,736 kWh/yr
xxvi) Annual Energy Expenditure on Pumping 7,822,571 PKR/Yr
xxvii) Pumping System Efficiency after Improvement 65 %
xxviii) Water Flow after Efficiency Improvement 398 m3/hr
xxix) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
xxx) Potential of Energy Reduction 5.89 %
xxxi) Reduced Annual Energy Consumption at Improved Efficiency 35,448 kWh/yr
Annual Financial Saving on Pumping 460,821 PKR/Yr
Summary of Findings11
Issues & Recommendations
The pumping efficiency is in the range of FAIR. This system needs impeller adjustment.
12 i) ISSUES RECOMMENDATIONS
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia
12 Estimated Investment for Improvement Plan 800,500 PKR
Control leakageLeakage at the pump gland
Its recommended tha to replace the volt metervolt meter not Operational
No VFD installed Install VFD
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station ZUBAIR PARK RAJGHAR
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 200
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
NOT OPERATIONAL
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-11318
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 3 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 61467
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 KVAR
Panel Condition/Issues Good/Faulty A meter
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator NOT OPERATIONAL
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Good
Housekeeping Fair
Motor Terminal open motor connection
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 399 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.19 m/sec
Pressure
i) Pressure at Discharge Side of Pump 3 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 396.6 392.4 389.2
ii) Ampere 191 193.4 179.4
iii) Power Factor 0.75 0.75 0.77
iv) Appearant Power (kVA) 130.1 132.5 121.5
v) Running Power (kW) 97.3
vi) Reactive Power (kVAr) 85.85 87.1 80
vi) Motor Working on Loading Basis 86.5 %
Oversize Undersize Properly Sized
i) Speed
ii) Speed of Motor 1,488 RPM
Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.4
i) Thermal Imaging
Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Calculat Electric Panels
10 i)
ii) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
iii) Static Suction Head (Only for WW Pump) ft
iv) Suction Side Frictional Head (Only for WW Pump) ft
v) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
vi) Discharge Head (Pressure Gauge) 6.93 ft
vii) Discharge Side Frictional Head 11.76 ft
viii) Dynamic Discharge Head (v+vi) 18.69 ft
ix) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 159.73 ft
x) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 109.31
xi) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,353
500-10,000, standard, 2,000-3,000 high efficiency
xii) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xiii) Deviation of actual flow from the pump curve flow %
xiv) Water Horsepower (whp) (TDH x Actual Measured Flow) 70.86 hp
xv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xvi) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 130.43 hp
xvii) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 56.87 %
Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 54.33 %
xviii)
xix) Existing Specific Pumping Energy (En(pumping01)) 0.25 kWh/m3
xx) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xxi) Daily Operational Time of Pump 16 hrs
xxii) Daily Pump flow 6,384 m3/day
xxiii) Annual working days 365 days
xxiv) Annual Pump flow 2,330,160 m3/yr
xxv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 571,279 kWh/yr
xxvi) Annual Energy Expenditure on Pumping 7,426,625 PKR/Yr
xxvii) Pumping System Efficiency after Improvement 65 %
xxviii) Water Flow after Efficiency Improvement 477 m3/hr
xxix) Specific Energy Consumption at New Efficiency 0.20 kWh/m3
xxx) Potential of Energy Reduction 16.42 %
xxxi) Reduced Annual Energy Consumption at Improved Efficiency 93,793 kWh/yr
Annual Financial Saving on Pumping 1,219,306 PKR/Yr
Summary of Findings11
Issues & Recommendations
Pumping system efficiency is 54%. For pump attached with 150 HP motor, efficiency <58.1% is considered to be (LOW). To improve its efficiency upto 65 % (GOOD) This pumping system requires impeler adjustment. This intervention will save 1,219,306 Rs annually.
12 i) ISSUES RECOMMENDATIONS
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia
12 Estimated Investment for Improvement Plan 743,500 PKR
Install A meter Faulty A meter
Defective chlorinator Replace Chlorinator
No flow meter available Install flow meter
No VFD installed Install VFD
Control leakageLeakage at the pump gland
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station SODIWALL PARK
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 16 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture118.6
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 14 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,488 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 2100.17
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 50 kVAr non operational
Panel Condition/Issues Execellent
Gland Leakage moderate leakage
Non Return Valve
Chlorinator
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring ok
Housekeeping OK
Motor Terminal open motor connection
Foundation/Civil work ok
Ratchet Plate
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 195 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 1.07 m/sec
Pressure
i) Pressure at Discharge Side of Pump 14 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 423 426 425
ii) Ampere 146.5 116.8 116.4
iii) Power Factor 0.57 0.65 0.54
iv) Appearant Power (kVA) 85.5 96.7 85.6
v) Running Power (kW) 53.4
vi) Reactive Power (kVAr) 79 65.5 71.5
vi) Motor Working on Loading Basis 47.7 %
Oversize Undersize Properly Sized
i) Speed
ii) Speed of Motor 1,488 RPM
Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max:
i) Thermal Imaging
Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Calculat Electric Panels
10 i)
ii) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
iii) Static Suction Head (Only for WW Pump) ft
iv) Suction Side Frictional Head (Only for WW Pump) ft
v) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
vi) Discharge Head (Pressure Gauge) 32.34 ft
vii) Discharge Side Frictional Head 2.86 ft
viii) Dynamic Discharge Head (v+vi) 35.20 ft
ix) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 176.24 ft
x) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 53.42
xi) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 878
500-10,000, standard, 2,000-3,000 high efficiency
xii) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xiii) Deviation of actual flow from the pump curve flow %
xiv) Water Horsepower (whp) (TDH x Actual Measured Flow) 38.21 hp
xv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xvi) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 71.58 hp
xvii) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 30.67 %
Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 53.38 %
xviii)
xix) Existing Specific Pumping Energy (En(pumping01)) 0.28 kWh/m3
xx) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xxi) Daily Operational Time of Pump 16 hrs
xxii) Daily Pump flow 3,120 m3/day
xxiii) Annual working days 365 days
xxiv) Annual Pump flow 1,138,800 m3/yr
xxv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 313,528 kWh/yr
xxvi) Annual Energy Expenditure on Pumping 4,075,866 PKR/Yr
xxvii) Pumping System Efficiency after Improvement 65 %
xxviii) Water Flow after Efficiency Improvement 237 m3/hr
xxix) Specific Energy Consumption at New Efficiency 0.23 kWh/m3
xxx) Potential of Energy Reduction 17.87 %
xxxi) Reduced Annual Energy Consumption at Improved Efficiency 56,043 kWh/yr
Annual Financial Saving on Pumping 728,557 PKR/Yr
Summary of Findings11
mping syste
Issues & Recommendations
Pumping system efficiency is 53.38%. For pump attached with 150 HP motor, efficiency <58 % is considered to be LOW. To improve the efficiency to 65% which is GOOD this pumping system requires impeller adjustment. This intervention will save 728,557 Rs annually.
12 i) ISSUES RECOMMENDATIONS
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia
12 Estimated Investment for Improvement Plan 770,000 PKR
Control leakageLeakage at the pump gland
No VFD installed Install VFD
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
Improve housekeepingHousekeeping is poor
Its recommended tha to replace the Ampere meterAmpere meter not Operational
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station SHERA KOT
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 15 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 200
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 5
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB12B/5
Serial
iii) Certification Mark
iv) Year of Manufacture2004
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 62.74
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 12 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 80 hp 60 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 113
v) Power Factor (Cos ɸ) 0.8
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 250 M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 88658.7
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant 25 kVAr non operational
Panel Condition/Issues Poor ,volt &Ampere meter not worknig
Gland Leakage moderate leakage
Non Return Valve
Chlorinator no
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Poor
Housekeeping OK
Motor Terminal open motor connection
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 160 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 0.88 m/sec
Pressure
i) Pressure at Discharge Side of Pump 8 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 375.6 399.5 395.8
ii) Ampere 98.3 92 90.6
iii) Power Factor 0.83 0.8 0.85
iv) Appearant Power (kVA) 63.1 59.3 60.5
v) Running Power (kW) 50.9
vi) Reactive Power (kVAr) 31.6 35.4 35.05
vi) Motor Working on Loading Basis 84.8 %
Oversize Undersize Properly Sized
i) Speed
ii) Speed of Motor 1,475 RPM
Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91
i) Thermal Imaging
Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Calculat Electric Panels
10 i)
ii) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
iii) Static Suction Head (Only for WW Pump) ft
iv) Suction Side Frictional Head (Only for WW Pump) ft
v) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
vi) Discharge Head (Pressure Gauge) 18.48 ft
vii) Discharge Side Frictional Head 1.94 ft
viii) Dynamic Discharge Head (v+vi) 20.42 ft
ix) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 161.46 ft
x) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 43.83
xi) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 850
500-10,000, standard, 2,000-3,000 high efficiency
xii) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xiii) Deviation of actual flow from the pump curve flow %
xiv) Water Horsepower (whp) (TDH x Actual Measured Flow) 28.72 hp
xv) Brake Horsepower (bhp) (OEM Data) 62.74 hp
xvi) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 68.23 hp
xvii) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 45.78 %
Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 42.10 %
xviii)
xix) Existing Specific Pumping Energy (En(pumping01)) 0.32 kWh/m3
xx) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xxi) Daily Operational Time of Pump 15 hrs
xxii) Daily Pump flow 2,400 m3/day
xxiii) Annual working days 365 days
xxiv) Annual Pump flow 876,000 m3/yr
xxv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 280,172 kWh/yr
xxvi) Annual Energy Expenditure on Pumping 3,642,233 PKR/Yr
xxvii) Pumping System Efficiency after Improvement 65 %
xxviii) Water Flow after Efficiency Improvement 247 m3/hr
xxix) Specific Energy Consumption at New Efficiency 0.21 kWh/m3
xxx) Potential of Energy Reduction 35.24 %
xxxi) Reduced Annual Energy Consumption at Improved Efficiency 98,721 kWh/yr
Annual Financial Saving on Pumping 1,283,374 PKR/Yr
Summary of Findings11
mping syste
Issues & Recommendations
Pumping system efficiency is 42.12%. For pump attached with 80 HP motor, efficiency 56-60 % is considered to be fair. To improve its efficiency upto 65 % which is good , this pumping system requires ampeler adjustment and repair and maintenance. This intervention will save 1,283,374 Rs annually.
12 i) ISSUES RECOMMENDATIONS
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia
12 Estimated Investment for Improvement Plan 534,000 PKR
Improve housekeepingHousekeeping is poor
Its recommended tha to replace the Ampere meterAmpere meter not Operational
Chlorinator is not operational Attach chlorinator and make it operationalize
NO water flow meter Attach Water Flow meter and make it operationalize
Control leakageLeakage at the pump gland
Its recommended tha to replace the Volt meterVolt meter not Operational
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Babu sabu dispensry
ii) Name of Subdivision ISLAM PURA
iii) Operator Name & Contact
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 17 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details 200
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Pumps Country Pakistan
ii) ModelB14B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec 408 m3/hr
vi) Head (H)210
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 124.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve 1
Bends
Strainer 1
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-11318
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check 1
Bends Elbow 1
Strainer
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 12 psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 150 hp 112.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 214
v) Power Factor (Cos ɸ) 0.84
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 315 S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 8122
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Installed but non operational
Panel Condition/Issues Poor ,volt &Ampere meter not worknig
Gland Leakage moderate leakage
Non Return Valve ok
Chlorinator NOT OPERATIONAL
Flow Meter no
Pressure Gauge no
Bore Hole in Front of PanYES
Wiring Poor
Housekeeping OK
Motor Terminal open motor connection
Foundation/Civil work ok
Ratchet Plate no
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches (on which flowmeter is clamped)
v) Pipe Perimeter mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 440 m3/hr (Through Transit Time Ultrasonic Flowmeter)
Velocity in Pipe 2.41 m/sec
Pressure
i) Pressure at Discharge Side of Pump 12 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
iii) Water Shutoff Head
Levels
i) Static Water Level 38 meter Estimated
ii) Pumping Water Level 43 meter (estimated due to gland leakage and catching of wire by suction)
Electric Measurements
i) Voltage 375.5 378.1 376
ii) Ampere 218 193 151.1
iii) Power Factor 0.83 0.79 0.79
iv) Appearant Power (kVA) 141.9 126.2 98.2
v) Running Power (kW) 99.06
vi) Reactive Power (kVAr) 86.9 77.1 56
vi) Motor Working on Loading Basis 88 %
Oversize Undersize Properly Sized
i) Speed
ii) Speed of Motor 1,485 RPM
Speed of Pump Impeller 1450 RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91.3
i) Thermal Imaging
Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Calculat Electric Panels
10 i)
ii) Drawdown of Pump (Pumping water level - Static Water Level) 16.072 ft
iii) Static Suction Head (Only for WW Pump) ft
iv) Suction Side Frictional Head (Only for WW Pump) ft
v) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
vi) Discharge Head (Pressure Gauge) 27.72 ft
vii) Discharge Side Frictional Head 14.26 ft
viii) Dynamic Discharge Head (v+vi) 41.98 ft
ix) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 183.02 ft
x) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 120.54
xi) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 1,283
500-10,000, standard, 2,000-3,000 high efficiency
xii) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xiii) Deviation of actual flow from the pump curve flow %
xiv) Water Horsepower (whp) (TDH x Actual Measured Flow) 89.54 hp
xv) Brake Horsepower (bhp) (OEM Data) 124.6 hp
xvi) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 132.79 hp
xvii) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 71.86 %
Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 67.43 %
xviii)
xix) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3
xx) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xxi) Daily Operational Time of Pump 17 hrs
xxii) Daily Pump flow 7,480 m3/day
xxiii) Annual working days 365 days
xxiv) Annual Pump flow 2,730,200 m3/yr
xxv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 617,963 kWh/yr
xxvi) Annual Energy Expenditure on Pumping 8,033,520 PKR/Yr
11
Issues & Recommendations
Pumping system efficiency is 67.43%. For pump attached with 150 HP motor, efficiency of 67% is considered to be GOOD. This pumping system requires no intervention.
12 i) ISSUES RECOMMENDATIONS
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financia
12 Estimated Investment for Improvement Plan 834,000 PKR
Control leakageLeakage at the pump gland
Its recommended tha to replace the Volt meterVolt meter not Operational
No VFD installed Install VFD
Ampere meter not Operational Its recommended tha to replace the Ampere meter
PFI pannel not oprational
It is recommended to change the control circuity of the panel which is included HRC fuses ,current transformer,magnatic connector,and control terminals for the control cct.Also reactive power factor regulator relay for auto swicting needs to reflected
Improve housekeepingHousekeeping is poor
Chlorinator is not operational Attach chlorinator and make it operationalize
There is no pressure gauge installed at discahrge pipeline Install digital pressure gauge at discahrge pipeline
NO water flow meter Attach Water Flow meter and make it operationalize
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Fazal Colny Disposal pump no 1
ii) Name of Subdivision Islam Pura / Lahore
iii) Operator Name & Contact NA
iv) Total Number of Pumps Installed 2
v) Total Number of Pumps in Operation 2
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 2
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 2
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day Estimated
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details Not Available
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / BrandKSB
Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP Estimated
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 6
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 6
ii) Length of Discharge Pipe (ft) 15 Estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 25 ft
Suction Side Elevation 11 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 20 hp 15 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant not installed
Panel Condition/Issues poor
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring poor
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 6 inches
v) Pipe Perimeter 479 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 200 m3/hr 3.3333 m3/min Estimated
Velocity in Pipe 3.05 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 11 meter
Electric Measurements Volt 370.8 377.9 372.6
Ampere 20.9 19.9 21.6
kW 11.6 Power Factor 0.84 0.89 0.87
vi) Motor Working on Loading Basis 78 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 11 ft
v) Static Discahrge Head 25 ft
vi) Frictional Head (Suction and Discahrge) 23.30 ft
viii) Total Dynamic Head of Pump (TDH) 37.30 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 8.30 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 15.55 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 53.35 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 3,600 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,314,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 76,621 kWh/yr
xxv) Annual Energy Expenditure on Pumping 996,068 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 57 %
xxvii) Water Flow after Efficiency Improvement 214 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3
xxix) Potential of Energy Reduction 6.41 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 4,908 kWh/yr
xxxi) Annual Financial Saving on Pumping 63,806 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 53.35%. For pump attached with 20 HP motor, efficiency in between 50 to 57 is considered to be fair (> 60.9 is excellent). This pumping system requires impeller adjustment. It is estimated that this impeller adjustment would increase pumping efficiency from 53.35% to 57% which is in the range of GOOD efficiency. This efficiency improvement will save about Rs. 63,506 per year.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 145,500 PKR
Adjust impellerPumping system need impeller adjustment
install ammeterAmmeter not working
No pressure gauge Install digital pressure gauge
no PFI plant installed Install PFI plant
No water flow meter Install water flow meter
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station Fazal Colny Disposal pump no 2
ii) Name of Subdivision Islam Pura / Lahore
iii) Operator Name & Contact NA
iv) Total Number of Pumps Installed 2
v) Total Number of Pumps in Operation 2
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 2
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 2
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day Estimated
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary LESCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details Not Available
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 02
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / BrandKSB
Country Pakistan
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 204 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP Estimated
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 6
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 6
ii) Length of Discharge Pipe (ft) 15 Estimated
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 25 ft
Suction Side Elevation 11 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer Siemens
ii) Rated kW / hp 20 hp 15 kW
iii) Voltage Range Volts
iv) Current Amperes
v) Power Factor (Cos ɸ)
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant not installed
Panel Condition/Issues poor
Gland Leakage
Non Return Valve
Flow Meter Not installed
Pressure Gauge Not installed
Wiring poor
Housekeeping
Motor Terminal
Foundation/Civil work
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 6 inches
v) Pipe Perimeter 479 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 204 m3/hr 3.4 m3/min Estimated
Velocity in Pipe 3.11 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 11 meter
Electric Measurements Volt 376.1 370.2 368
Ampere 19.2 20 21.9
kW 11.06 Power Factor 0.85 0.76 0.84
vi) Motor Working on Loading Basis 74 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 0 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max:
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 11 ft
v) Static Discahrge Head 25 ft
vi) Frictional Head (Suction and Discahrge) 24.24 ft
viii) Total Dynamic Head of Pump (TDH) 38.24 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 8.67 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 14.83 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.51 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 3,672 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,340,280 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 73,054 kWh/yr
xxv) Annual Energy Expenditure on Pumping 949,700 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 58.51%. For pump attached with 20 HP motor, efficiency abov 57% is considered to be Good. This pumping system does not require any intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 145,500 PKR
Install VoltmeterVoltmeter not available
install ammeterAmmeter not working
No pressure gauge Install digital pressure gauge
no PFI plant installed Install PFI plant
No water flow meter Install water flow meter
Gland leakage at Riwaz Garden Open motor connections at Raj Garh Muslim
Park
Poor and flashed panel at Bilal park Faulty chlorinator at Bilal Park
No terminal box at Riffle Range Defective chlorinator at Riffle range
Faulty flowmeter at Zubair Park View of motor at B Block Qadaffi Park
Discharge pipeline at Qadaffi Park Poor panel at Qadaffi Park
View of installed flowmeter at Jahangir Park
Defective flowmeter at Moon market
Poor motor connections at E Block Poor and flashed panel at E Block
Poor house keeping at E Block
Poor panel at Firdous Colony