energy efficiency in electrical networks challenges ahead · energy efficiency in electrical...

49

Upload: others

Post on 20-Apr-2020

5 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE
Page 2: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

Energy Efficiency in Electrical Networks Challenges Ahead

Prof. Peter KircheschVice President R&D AREVA T&D

2009 IEEE Bucharest PowerTechBucharest/ROM, June 29 th, 2009

Page 3: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20093 3

Opening statement (1/2)

Improved Energy Efficiencymeans the more efficient (better) use of energy through energy savings and reduction of losses.

It is seen as the quickest, most effective and most cost-effective manner for reducing greenhouse gas emissions (CO2, others).

T&D contributions to Energy Efficiency will be discussed in this presentation

ChallengesAnswers (Technical solutions)

Page 4: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20094 4

Opening statement (2/2)

Electrical networks have to be prepared to accommodate the change in generation mix and load profiles considering:

Reliability

Efficiency

Sustainability

Affordability

This is not a new message, it will however remain valid for the future

Page 5: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20095 5

Challenges ahead

Page 6: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20096 6

World Electricity Generation (by Energy Source), 1990 - 2030

TWh

0

5000

10000

15000

20000

25000

30000

35000

40000

1990 2000 2010 2020 2030

Coal Oil Gas Nuclear Hydro Other renewables

27000

12000

15000

21000

Source: IEA 2007

RES (w/o hydro) will increase from 3 % to 14 % (2010 to 2030)

37000

Page 7: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20097 7

2600

3400

4200

210 280

950

50180

2500

60 80 160 15010

0

500

1000

1500

2000

2500

3000

3500

4000

4500

2000 2010 2030

Hydro Biomass Wind Geothermal Solar

World Electricity Generation from Renewable Sources, 2000 to 2030

TWh

Massive increase of wind power and biomass

Source: IEA World Energy Outlook

Page 8: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20098 8

Massive Integration of Wind Power (12.2008)

Wind generation is expected to grow to 240 GW by 2012 and to 1000 GW by 2020

< 1 GW

1 – 10 GW

> 10 GW

25 170 MW

16 754 MW

23 903 MW

12 210 MW

Source: Global Wind Energy Council 2008

Page 9: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.20099 9

Onshore and Offshore

Alpha Ventus/GERoffshore

Studland Bay/AUS onshore

Page 10: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200910 10

Interconnect Regions, Countries, NetworksAvoid Congestions

Enable Trading

European Priority Projects Main AxesSource: EU – TEN-E Priority Projects

Page 11: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200911 11

Some facts

Page 12: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200912 12

Some facts

Generation of electricityWorldwide 19 000 TWh (2006)

EU 27 3 500 TWh (2006)

EfficiencyEnergy consumption worldwide:

10 900 Mtoe equivalent to 127 000 TWh

About 40 % of the primary energy (50 800 TWh) is used to generate the electrical energy (19 000 TWh)

Efficiency 19 000/50 800 = 37.4 %

Source: EU Electra Sherpa WG 1 04.09.2007

About 60 % of the primary energy is lost and released to the atmosphere

Page 13: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200913 13

Energy efficiency – full chain

►Supply side (loss reduction)

►Demand side (energy savings)

Primary energy Electrical energy

60 %*

Transmission Distribution

Lighting systemsProcess automationMotors Drives

5 - 6 %***3 - 4 % **Losses:

* Mean value. Old: 70 %; CHP: 15 %*** Transformers 3 %, Cables 3%** depending on line length and voltage level up to 20 – 25 %

Page 14: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200914 14

Economics

Energy lossesDepending on network structure 7 % to 30 % (incl. non technical losses)

In Europe about 7 % to 8 %

CostsTotal consumption Europe (EU 27) about 3 500 TWhp.a.

1 MWh is about 40 € (average market clearing price) i.e. 1 TWh is worth 40 M€

Losses: 7 % of 3 500 TWh = 245 TWh are equ. to 9.8 b€

A loss reduction of 1 % is worth 1.4 b€ p.a.

Page 15: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200915 15

However

Page 16: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200916 16

Contribution of fuel type to electricity generation 2007

North America

Each region/country has its own needs

IEA 2008

67%

13% 19%1%

Thermal HydroNuclear Renewables

40%57%

2% 1%

Thermal HydroNuclear Renewables

59%

17% 21%3%

Thermal HydroNuclear Renewables

Latin America

Europe

80%

18%2% 0%

Thermal HydroNuclear Renewables

Africa

89%

9% 0% 2%

Thermal HydroNuclear Renewables

80%

14% 5% 1%

Thermal HydroNuclear Renewables

Asia

Pacific

Page 17: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200917 17

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 18: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200918 18

Multi-Terminal HVDC Solutions

Source: Airtricity/Riso lab/DK

Connect off-shore wind parks

European wind atlas off-shore

Page 19: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200919 19

Offshore versus Onshore

More wind Less visual impact

AccessibilityNetwork connectionCosts

Robin Rigg/UK Studland Bay, Tasmania/AUS

Page 20: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200920 20

Challenges

Bring the energy to the consumerRespect grid codesReal time network mgt

ForecastingGeneration mix mgtReserve mgt

..the high pressure area will move from the Azores to the North Sea...

Source: EWEA, Wind Energy –The Facts March 2009 (left)

All hardwareTurbinesPlatformsElectrical equipment etc.

Page 21: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200921 21

Robin Rigg UK (Irish Sea)

► Commissioned: 07.2009► Power: 60 x 3 MW = 180 MW► AC connection► Cable length: 12 km (9 km

submarine cable)► Water depth: about 30 m

Page 22: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200922 22

Alpha Ventus GER (North Sea)

► Commissioned: 2009► Power: 12 x 5 MW = 60 MW► AC connection► Cable length: 45 km► Water depth: about 40 m

Page 23: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200923 23

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 24: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200924 24

Bulk Power Transmission HVDC Prospects 600kV-800kV

In-service dates

+600kV/4000MW+1000kV/9500MW

Yunnan-Guangdong: 2009Xiangliaba-Shanghai: 2011Jingping-East China: 2012Xiluodu-Hunan: 2014Humeng-Shandong: 2015Nuozhadu-Guangdong: 2015Xiluodu-Hanzhou: 2015Humeng-Tianjing: 2016Jinsha River I-East China: 2016Humeng-Liaoning: 2018Jinsha River II-Fujian: 2018Hami-Central China: 2018Jinsha River II-East China: 2019

Irkutsk (Russia)-Beijing 2015Chicken Neck

4 terminal 800kVAgra 1: 2009Agra 2: 2011Bangalore 1 2013Bangalore 2 2015

WestCoreach 3 terminal

South W 2012South E 2013

WestCor4 terminal

North 2018

Northern Lights600kV 2014-2020

Madeira 600kV2012

Melo 600kV2011

Page 25: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200925

Challenge: UHVDC Products 800 kV 6400 MW

Converter transformer

Bushings

Valve

ProductsValveConverter transformerBushings

TransformerWall bushing

u-i measurementBy-pass switchControls

By-pass switch

Massive R&D investment 6“ Thyristors

Page 26: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200926

Bulk power transmission 1100 kV AC in China

Nanyang S/sShunt reactor: 3 x240 Mvar

Jindongnan S/sTransfo: 3000 MVA

Shunt reactor: 3x320 Mvar

Jinmen S/sTransfo: 3000 MVA

Shunt reactor: 3x320 Mvar

Nanyang

Jindongnan

Jingmen

Jincheng

Wuhan

Douli

Guangzhou

GIS and H-GIS Technology are in use

Source: Y.Shu Electra Nr. 242 February 2009

359 km

281 km

Energized in 01/2009

500 kV1100 kV

Jiuan

Page 27: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200927

1100 kV in China

Page 28: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200928 28

DC systems embedded in AC networks (Supergrids)

AC

Grid

AC

Grid

AC

Reactive power compensation on both ends

More transmission capacity via the AC line

DC

AC

Page 29: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200929 29

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 30: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200930

More utilization of FACTS devices

STATCOM GlenbrookUSA

Dynamic control of voltage, impedance and phase angle of high voltage AC transmission lines. Better utilization of existing and new oh-linesIncrease power qualityImproved dynamic stability

SVC St.Johns Wood UK

Stability, Energy efficiency

Page 31: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200931 31

Total SVC Rating5.6 GVar (2008)

Installations by competitors:Thyristor Controlled Reactor (TCR)Thyristor Switched Capacitors (TSC)

AREVA T&D Installations:Saturated Reactor (SR)Thyristor Controlled Reactor (TCR)Thyristor Switched Capacitors (TSC)Relocatable Static Var Compensation

(RSVC)STATCOM

DC

Iron Acton

DC

SVC (UK network)

Page 32: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200932 32

Iron Acton RSVCs

Page 33: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200933 33

Iron Acton RSVCs

Page 34: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200934 34

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 35: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200935 35

1973 100 %

1985 26 %

1999 17 %

Reduction in footprint 245 kV GIS

Volume reduction by a factor of 6 in 32 years

2005 16 %,but for 300 kV

Reduction of losses by bringing thehighest possible voltage close to theconsumer

Page 36: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200936 36

Low loss transformers

TransformersLow-loss transformers

Amorphous core materials

Design modifications- high quality GOS

- copper wires

- lower magnetic induction

The efficiency is 97.5% to 99.4 % at 40% to 50% loading. The transformer is not always operated at maximum efficiency, therefore the overall efficiency is about 90 %.

Use of amorphous steel instead of GOS reduces the no-load losses by 70 - 80 %.

Distribution transformer

Page 37: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200937 37

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 38: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200938

Dynamic loading/monitoring

Dynamic loading/monitoringIncrease utilisation of existing transmission capacity through real-time information

Monitoring systems to deliver exact statements of operating conditions of assets

Power transformer

Overhead line

Monitoring system

Page 39: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200939

Network management solutionsDecentralised generation issues (millions of sources)

Fast changing generation and load profilesReversal of power flowForecasting, risk assessment

Real-time data management and visualisationDemand side management

Smart metering- Transparent information to

customer (tariffs etc.)

Congestion management

More intelligent networks

Control room

ICT will allow real time management of the full chain

Page 40: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200940 40

Visualisation and Decision Support

Situation Awareness with WAMS

World map with voltage contour

Visualization for Wide Area SecurityGuide operator with re-despatching actions

Page 41: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200941 41

Some technical answers (not exhaustive)

Integration of wind energyBulk power transmissionReactive power compensationPrimary products

Substations (smaller footprint)Increase transformer efficiency

More network intelligenceNetwork reinforcement

Page 42: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200942 42

Back-to-BackHVDC

ERCOT

Central/EasternSeaboard

Quebec

West Coast

Canada

USA

Long distance DC transmission

Nelson River

Pacific Intertie

Neptune projectLong Island – New Jersey660 MW 105 km

Transbay cableSan Francisco400 MW 88 km

Under construction

Intermountain

Quebec – New England

USA/Canada network structure and b-t-b links

Page 43: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

HVDC links in Europe

1. Gotland link (1954/70/83/87)2. Cross Channel (1961/86)3. SACOI (1965/93)4. Konti-Skan (1965/88/2007)5. Skagerrak (1976/77/93/2012)6. FennoSkan (1989/2010)7. Baltic Cable (1994)8. Kontek (1995)9. SwePol (1999)10. GRITA Italy-Greece (2000)11. Moyle (2001)12. Estlink (2006)13. NorNed (2008)14. SAPEI (2008)15. BritNed (2010)16. Storebælt (2010)17. COMETA (2010)

..... not yet commissioned

..... under study

1

2

Madrid

Paris

Berlin

Brussels

London

Dublin

Lisbon

Reykjavik

Bern

Praha

Wien

Rome

Zagreb

Bratislava

Budapest

Sarajevo

Belgrade

Podgorica

Bucharest

Sofia

Skopje

Athens

Warsaw

Minsk

Vilnius

Riga

StockholmOslo

16

Helsinki

3

14

10

17

15

13

54

12

6

9

7 8

11

Libya

Tirana

Kiev

Ankara

UCTE

IPS/UPS

Nordel

UKTSOA

ATSOI

Page 44: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200944 44

European Priority Projects EL 8

Source: EU – TEN-E Priority Projects

Page 45: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200945 45

UCTE Central East/IPS_UPS

Source: UCTE IPS/UPS Feasibility study November 2008

Nine lines exist, no longer in use

Page 46: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200946 46

Conclusion

Page 47: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200947 47

Conclusion

Further improvement of Energy Efficiency at the level of generation, transmission, distribution and also final use of energy will certainly be dependent on technological evolution

Only through joint forces of politics, power sector, industry and the academic world sustainable energy systems can become reality

Page 48: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200948 48

There is still a lot to do...

Puffing Billy 1825 24 km/h

Maglev 2003 501 km/h

TGV 2007575 km/h

The limits of technical developments are not predictable

Page 49: Energy Efficiency in Electrical Networks Challenges Ahead · Energy Efficiency in Electrical Networks Challenges Ahead Prof. Peter Kirchesch Vice President R&D AREVA T&D 2009 IEEE

IEEE Bucharest 29.06.200949 49

AREVA T&D

Thank you Mulţumesc