eneva corporate presentation

Upload: mpxeri

Post on 18-Oct-2015

4 views

Category:

Documents


0 download

TRANSCRIPT

  • April, 2014

  • Investment Thesis

    1

  • Investment Thesis

    One of the largest private sector power generators in Brazil

    ENEVA currently operates 2.4GW in coal and gas-fired power plants (2.9 GW until the end of year)

    Integrated energy platform, with privileged access to natural resources

    Only private power generator in Brazil with access to onshore gas

    Short-term value triggers

    - Reorganization of the companys structure and continuous TPPs operation stabilization

    - Stronger role of E.ON, bringing technical expertise and cost discipline to ENEVA

    Competitive greenfield portfolio

    Licensed coal, gas and wind power generation projects

    3

  • A Brazilian thermal generator with asset exposure to energy fossil fuels (natural gas and coal)

    ENEVA at a Glance

    2.9GW inflation-protected, long-term PPAs

    o 2.4GW in operation

    o 517MW under construction

    Long-term PPAs guarantee R$2.2 billion in annual inflation-adjusted

    capacity payments

    PPAs provide hedge against commodity price exposure

    Integrated gas E&P assets supply up to 8.4MM m/day to ENEVAs power

    plants

    Competitive portfolio of licensed greenfield wind, coal and gas fired

    capacity

    Company Description

    4

    ENEVA ownership structure

    Geographic Footprint

    Parnaba I ENEVA 70% / Petra 30% Natural Gas - 676MW

    Amapari Energia ENEVA 51% / Eletronorte 49% Diesel - 23MW

    Itaqui ENEVA 100% Coal - 360MW

    Natural Gas Exploratory

    blocks Contracted production

    of 8.4MM m3/day

    Pecm I ENEVA 50% / EDP 50% Coal - 720MW

    Pecm II ENEVA 100% Coal - 365MW

    Parnaba II ENEVA 100% Natural Gas - 517MW

    Parnaba III ENEVA 70% / Petra 30%

    Natural Gas - 176MW

    Parnaba IV ENEVA 70% / Petra 30% Natural Gas - 56MW

    Free Float (38.2%)

    37.9% 23.9%

    Other

    MPX / E.ON Partipaes Joint Venture

    50%

    50%

    BNDES

    10.3%

    Eike Batista

    Controlling Block

    27.9%

    Solar Tau ENEVA 100% Solar - 1MW

    Note: 1) Ownership structure assumes future MPX / E.ON Participaes JV incorporation, as disclosed on the Material Fact Notice as of July 3, 2013

  • Company Overview

    2

  • 6

    Creation of MPX (2007)

    1,080MW in the A-5 (2007)

    IPO (USD1.1BN)

    365MW in the A-5 (2008)

    Parnaba Basin onshore exploratory blocks (2009)

    Successful closing of E.ON partnership

    Acquisition of greenfield projects

    Beginning of commercial operations at Pecm I

    Waivers received from the Regulatory Agency

    Operational capacity reaches 2.4GW

    E.ON stake increase to 36%, joining controlling block

    Name changed to ENEVA

    Signing of E.ON / Cambuhy recapitalization of Parnaba Gs Natural to secure gas delivery

    Asset stabilization plan developed with very good imminent results

    ICB Online criteria from the Regulatory Agency achieved

    Asset stabilization ongoing, further improvements on availability in Jan, 2014

    Successful injunction halting ADOMP in Jan, 2014

    Recapitalization efforts

    Balance Sheet strengthening

    Further cost reduction measures

    Successful start of drilling campaign in Parnaba (2010)

    Parnaba II 517MW contracted in A-3 auction

    Power supply contracts for Parnaba I secured (676MW), start of Parnaba complex development

    2 fields in Parnaba declared commercial

    Gavio Real and Gavio Azul with estimated production of up to 6MM m3/day

    Unique Development Track, overcoming its Short Term Challenges

    Key Milestones, Challenges & Outlook

    2007 - 2009 2010 - 2011 2012

    2013

    2014

  • 2.4GW of coal and gas-fired power plants in operation

    Operational Assets (1)

    7

    Pecm I

    Energy Source: Coal

    ENEVA Stake: 50%

    Installed Capacity: 720MW

    Sold Energy: 615MW

    Fixed Revenue: R$600.3MM p.a.

    Start-up: May, 13

    Energy Source: Coal

    ENEVA Stake: 100%

    Installed Capacity: 360MW

    Sold Energy: 315MW

    Fixed Revenue: R$317.3MM p.a.

    Start-up: Feb, 13

    Itaqui

    Note: 1) Fixed revenues are indexed to inflation index IPCA (Database: Nov, 2013)

    Energy Source: Coal

    ENEVA Stake: 100%

    Installed Capacity: 365MW

    Sold Energy: 276MW

    Fixed Revenue: R$284.9MM p.a.

    Start-up: Oct, 13

    Pecm II

  • 8

    Parnaba I (OCGT)

    Energy Source: Natural Gas

    ENEVA Stake: 70%

    Installed Capacity: 676MW

    Sold Energy: 450MW

    Fixed Revenue: R$445.9MM p.a.

    Start-up: Apr, 13

    Energy Source: Natural Gas

    ENEVA Stake: 70%

    Installed Capacity: 176MW

    Sold Energy: 98MW

    Fixed Revenue: R$99.0MM p.a.

    Start-up: Oct, 13

    Parnaba III (OCGT)

    Energy Source: Natural Gas

    ENEVA Stake: 70%

    Installed Capacity: 56MW

    Sold Energy: 46MW (Free Market)

    Fixed Revenue: R$54.0MM p.a.

    Start-up: Dec, 13

    Parnaba IV

    2.4GW of coal and gas-fired power plants in operation

    Operational Assets (2)

    Notes: 1) Fixed revenues are indexed to inflation index IPCA (Database: Nov, 2013); 2) 169MW already in operation

  • 9

    Energy Source: Natural Gas

    ENEVA Stake: 100%

    Installed Capacity: 517MW

    Sold Energy: 450MW

    Fixed Revenue: R$373.7MM p.a.

    Start-up: 2H14

    Parnaba II (CCGT)

    Note: 1) Fixed revenues are indexed to inflation index IPCA (Database: Nov, 2013)

    Additional 517 MW under construction

    Power Plant with COD in 2014

  • Outstanding management capabilities

    Financial strength and discipline

    Sector know-how: E.ON E&P looks at a volume delivery of +170k

    barrels/day and +60 licenses in GB and Norway

    Tried and tested Parnaba experience, know-how of Parnaba Complex

    rooted within PGN

    Strong Shareholders

    All Parnaba gas-fired power plants are supplied by Parnaba Gs Natural,

    owner and operator of 8 onshore exploration blocks

    ENEVA has a direct interest in PGN as key supplier of its TPPs

    Declaration of commerciality with Development Plan for 3 gas fields:

    Gavio Real, Gavio Branco and Gavio Azul

    Gas supply agreements secured for 8.4MM m/day

    R$250 million capital injection concluded in Feb, 2014

    Highlights

    10

    Integrated Natural Gas E&P

    Strong competitive position in gas-fired generation

    Parnaba Gs Natural

    18.2% 9.1% 72.7%

    Geographic Footprint

    Note: (1) Ownership structure after execution of the sale and purchase agreement between OGP and Cambuhy, subject to approval by OGPs creditors, under its judicial recovery procedure, and authorization by ANP

  • 37 wells drilled, of which 26 have gas indications

    o 18 wells with discoveries

    o 8 wells with gas indications

    Declaration of commerciality with Development Plan for 3 gas fields:

    o Gavio Real

    o Gavio Azul

    o Gavio Branco

    Gavio Real field is producing since Jan, 2013:

    o 16 producing wells out of 5 clusters

    o Daily Production: 6.6MM m/day of natural gas

    o Connected to a 6.6MM m/day GTU Gas Treatment Unit (as of

    today)

    o All gas dedicated to ENEVAs Parnaba TPPs

    Exploration Campaign

    11

    Integrated Natural Gas E&P

    2014 / 2015:

    o Connection of 3 additional production wells and GTU expansion to

    8.4MMm/day

    o Gavio Branco production development and submission to ANP of

    assessment plan for new discoveries (Mar, 2014)

    Upcoming Events

    Power Plant Parnaba I, Parnaba III

    and Parnaba IV Parnaba II

    Wells 16 19

    Production Ramp-up (MM m/day)

    6.6

    8.4

    Current 2H14

  • Short-Term Value Triggers

    3

  • 13

    Operational Performance (Itaqui)

    EBITDA (R$MM)

    Availability

    1st quarter of positive EBITDA since COD, due to increased

    availability and reduced operating costs

    EBITDA amounted R$24.2MM (EBITDA mg: 16.1%), mostly

    attributable to:

    o ICB Online reimbursement (R$17.2MM);

    o Lower unavailability costs despite higher spot prices, as a result of

    improved operational performance

    o Reduction in variable cost per MWh (-18.7% QoQ)

    Variable Revenue X Variable Cost (R$/MWh)

    -95.3

    -31.3

    -5.9

    24.2

    1Q13 2Q13 3Q13 4Q13

    Sources: ONS, Company estimates

    Positive EBITDA driven by increased availability but also one-time events. Variable costs covered

    by variable revenues

    63%

    83% 84% 87%

    75%

    1Q13 2Q13 3Q13 4Q13 1Q14

    261

    232

    144 159

    128 149

    112

    141

    108 103 115

    107 106 103 102 102 100 104 108 107 113 116

    Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

    Variable Cost Variable Revenue

    COD: Feb 5, 2013

  • 14

    Operational Performance (Pecm II)

    Startup on October 18, 2013

    EBITDA amounted R$55.4MM (EBITDA mg: 37.8%) in the 4Q13,

    mostly attributable to:

    o Injunction granting Fixed Revenues from September until

    commercial startup (R$31MM);

    o Unavailability costs impacted by higher spot prices (R$22.3MM);

    o ICB Online reimbursement (R$6.1MM).

    Variable Revenue X Variable Cost (R$/MWh) Availability

    Sources: ONS, Company estimates

    Availability in the first 3 months higher than international benchmark. Recurring positive margin

    on dispatch

    N.A. N.A. N.A.

    85%

    96%

    1Q13 2Q13 3Q13 4Q13 1Q14

    92 99 111

    114 118 122

    Jan-13...Set-13 Oct-13 Nov-13 Dec-13

    Variable Cost Variable Revenue

    EBITDA (R$MM)

    -10.7 -6.1 -8.3

    55.4

    1Q13 2Q13 3Q13 4Q13

    COD: Oct 18, 2013

  • 15

    Operational Performance (Parnaba I)

    EBITDA (R$MM)

    Availability

    EBITDA amounted R$32.0MM (EBITDA mg: 14.9%), mostly

    attributable to:

    o Higher unavailability costs (R$17.5MM), primarily due to

    stoppages to allow Parnaba III and Parnaba IV to be connected

    to the grid (R$6MM);

    o Variable cost control;

    o Stable operations.

    Variable Revenue X Variable Cost (R$/MWh)

    Sources: ONS, Company estimates

    -5.9

    28.2

    58.8

    32.0

    1Q13 2Q13 3Q13 4Q13

    OBS: Dispatch margin captured by Parnaba Gs Natural

    Unavailability costs impacted EBITDA, despite plants full capacity and stable operations

    96% 91%

    96% 96% 99%

    1Q13 2Q13 3Q13 4Q13 1Q14

    77 74 65

    75 80 68 77 78 74 79

    90

    80 82 94 99 100 96 93 99 95 92

    104

    Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

    Variable Cost Variable Revenue

    COD: Feb 1st, 2013 to

    Apr 12, 2013

  • 16

    Operational Performance (Pecm I)

    EBITDA (R$MM)

    Availability

    NOTE: 1) Figures consider 100% of Pecm I.

    EBITDA amounted R$61.7MM (EBITDA mg: 18.5%), mostly

    attributable to:

    o Lower Variable Revenue due to outage of Turbine #1 throughout

    4Q13;

    o Higher Unavailability Costs (R$83.9MM), despite accounting in

    December in accordance with 60-month rolling average

    unavailability (R$3.2MM);

    o ICB Online reimbursement (R$107.8MM);

    o Higher Fuel Costs (Coal: R$56.6MM; Diesel: R$12.3MM), inflated

    due to shutting down and restarting processes from stoppages

    o Lower variable cost (-7.0% QoQ)

    Variable Revenue X Variable Cost (R$/MWh)

    -143.4

    -63.8

    40.1 61.7

    1Q13 2Q13 3Q13 4Q13

    EBITDA benefited by one-time items, despite outage of Turbine #1 in December

    Sources: ONS, Company estimates

    70%

    39%

    64%

    47%

    70%

    1Q13 2Q13 3Q13 4Q13 1Q14

    151 127 118

    318

    154

    117 139 138

    109 119

    107

    134

    111 105 104 100 99 99 97 102 105 106 110 114

    Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

    Variable Cost Variable Revenue

    In 4Q13 and Jan, 14, Turbine #1 was 2,327 hours unavailable

    primarily due to shaft maintenance and hydrogen seal replacement

    COD: Dec 1st, 2012 May 10, 2013

  • 17

    Operational Performance (Parnaba III)

    NOTE: 1) Figures consider 100% of Parnaba III

    Availability

    Start of commercial operations on October 22, 2013

    EBITDA amounted R$1.1MM, impacted by R$37.9MM of net energy

    acquisition costs incurred to meet contractual obligations

    Variable Revenue X Variable Cost (R$/MWh)

    Sources: ONS, Company estimates

    OBS: Dispatch margin captured by Parnaba Gs Natural

    High availability since COD

    N.A. N.A. N.A.

    100% 94%

    1Q13 2Q13 3Q13 4Q13 1Q14

    75 71

    161 161

    Jan-13...Out-13 Nov-13 Dec-13

    Variable Cost Variable Revenue

    N.A. N.A. N.A.

    1.1

    1Q13 2Q13 3Q13 4Q13

    EBITDA (R$MM)

    COD: Oct 22, 2013

  • 5,195

    5,933 357

    278

    3Q13 4Q13

    Net Debt Cash and Cash Equivalents

    5,551

    6,211

    18

    Refinancing of Holding Debt Successful short-term debt refinance and additional credit lines secured

    Consolidated Debt (R$MM)

    Total Gross Debt R$6,211MM

    Consolidated Gross Debt Profile (R$MM)

    R$845.9MM out of the total debt balance of short-term debt is

    allocated in the projects, as follows:

    o R$280.4MM: Current portion of the long-term debts of Itaqui,

    Pecm II and Parnaba I;

    o R$85.3MM: Bridge loans to Parnaba I, maturing in December,

    2014 and April, 2015. The outstanding balance will be paid-off in

    installments, which started in October, 2013;

    o R$480.3MM: Bridge loans to Parnaba II, which should be paid-

    off with the disbursement of the long-term financing packages.

    +14.2% (net debt)

    Gross Short-Term Debt R$2,408MM

    2,408 39%

    3,802 61%

    Short Term Long Term

    1,562 65%

    846 35%

    Hold Co. Project Related

    Consolidated Short-Term Debt (R$MM)

  • Regulatory Update Positive outcomes in 4Q13 and early 2014

    ADOMP Downtime/Unavailability Charges

    Pecm I and Itaqui filed in Jan, 2014 a lawsuit against Aneel questioning hourly-based unavailability charges;

    On Jan 24, 2014, a Federal Court granted an injunction halting unavailability charges as measured, establishing the methodology provided

    for in PPAs (60-month rolling average);

    The lawsuit also claims the reimbursement of amounts paid since PPAs beginning;

    Request for revision for ADOMP methodology presented to Aneel last week

    ICB Online Pass-through criteria for power purchase in case of startup delay

    Aneel approved a revised reimbursement criteria for energy acquisition costs;

    New criteria establishes that reimbursement be based on the current ("online") cost of the plant to the system (ICB Online), in case it was

    operating commercially;

    The decision was retroactive to the PPA start dates.

    Pecm II Fixed Revenue Reimbursement

    Pecm II filed a lawsuit claiming for fixed revenues of Jul, 2013 and Aug, 2013 (R$48MM). Decision pending;

    Already received R$31MM from Sept, 2013 up to plants COD (Oct 18, 2013), as granted by an injunction

    19

  • 20

    Cost Reduction Program

    ENEVA developed a Medium Term Plan 2014-2016 aimed at achieving significant cost reduction at

    holding and project level through:

    Leaner organizational structure

    Headcount reduction

    Decrease in third-party services

    Reduction of fixed costs at project level

  • Brazilian Power Market and Greenfield Portfolio

    4

  • Southeast Reservoirs

    ~70% of total storage capacity

    Source: ANEEL

    Brazils Generation Capacity: 131 GW

    Breakdown by source 2012

    68.7%

    9.9%

    2.2%

    1.6%

    1.6%

    16.0%

    Hydro Gas Coal Nuclear Wind Others

    Brazil is highly dependent on hydro generation with increasingly faster depletion of reservoirs

    Brazilian Energy Matrix

    22

    Dry Season

    67% 56%

    76%

    29%

    38%

    46%

    54%

    62% 63% 64% 61%

    55%

    49% 45%

    42% 43%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Average 2007-2011 2012 2013

  • Source: ONS

    Autonomy = Storage Capacity / (Load Thermal Generation)

    Economic growth will boost power demand

    leading to a supply deficit in 2016

    Water storage capacity has stagnated,

    leading to decreased system autonomy

    65

    86

    65

    78

    60

    65

    70

    75

    80

    85

    90

    2013 2014 2015 2016 2017 2018 2019 2020

    GW

    avg

    ENERGY DEMAND

    PHYSICAL GUARANTEE

    (with signed PPAs)

    2016-on: New generation required ~8 GWavg required until 2020

    23

    Electric System Reliability

    New thermal plants are necessary to guarantee reliable power supply

    0

    5

    10

    15

    20

    25

    30

    1970

    1972

    1974

    1976

    1978

    1980

    1982

    1984

    1986

    1988

    1990

    1992

    1994

    1996

    1998

    2000

    2002

    2004

    2006

    2008

    2010

    2012

    Reservo

    irs A

    uto

    no

    my (

    Mo

    nth

    s)

    2013

    Current reservoir autonomy ~6 months

  • Parnaba Complex

    Integrated to natural gas resources

    Located in a tax-advantaged region

    Ventos Wind Complex

    Located in one Brazils best wind resource areas

    Attractive load factor

    Just 30km from grid connection

    Land ownership assured

    Au (Coal + Gas)

    Located at a port with a regasification terminal build license

    150km from Campos Basin natural gas accumulations

    Environmental licensed to both coal and gas operations

    Sul & Seival Integrated to the Seival Mine (proven reserves: 152 M ton)

    Low operation costs

    Power

    supply-demand

    unbalanced

    Hydropower

    concentrated

    matrix

    Spot prices at

    historical highs

    Demand for base-

    load generation

    Opportunities

    for ENEVAs

    growth 2 3 4 5 1

    Sul 727 MW

    Parnaba Complex 2,166 MW

    Seival 600 MW

    Au 2,100 MW Coal 3,300 MW Natural Gas

    Solar Tau 1 MW

    Ventos Wind Complex 600 MW

    Seival Mine License granted 152 M ton in proven reserves

    ENEVAs Greenfield Portfolio

    24

    Attractive licensed greenfield projects in various development stages

  • Appendix | Images

    5

  • Pecm I & II

    26

  • Itaqui

    27

  • Parnaba Complex

    28

  • Natural Gas: Parnaba E&P

    29

  • Disclaimer

    The material that follows is a presentation of general background information about ENEVA S.A. and its subsidiaries (collectively, ENEVA or the Company) as of the date of the presentation. It is information in summary form and does not purport to be complete. No representation or warranty, express or implied, is made

    concerning, and no reliance should be placed on, the accuracy, fairness, or completeness of this information.

    This presentation may contain certain forward-looking statements and information relating to ENEVA that reflect the current views and/or expectations of the

    Company and its management with respect to its performance, business and future events. Forward looking statements include, without limitation, any statement

    that may predict, forecast, indicate or imply future results, performance or achievements, and may contain words like may, plan, believe, anticipate, expect, envisages, will likely result, or any other words or phrases of similar meaning. Such statements are subject to a number of risks, uncertainties and assumptions. We caution you that a number of important factors could cause actual results to differ materially from the plans, objectives, expectations, estimates

    and intentions expressed in this presentation. In no event, neither the Company, any of its affiliates, directors, officers, agents or employees nor any of the

    placement agents shall be liable before any third party (including investors) for any investment or business decision made or action taken in reliance on the

    information and statements contained in this presentation or for any consequential, special or similar damages.

    This presentation does not constitute an offer, or invitation, or solicitation of an offer, to subscribe for or purchase any securities.

    Neither this presentation nor anything contained herein shall form the basis of any contract or commitment whatsoever.

    Recipients of this presentation are not to construe the contents of this summary as legal, tax or investment advice and recipients should consult their own advisors

    in this regard.

    The market and competitive position data, including market forecasts, used throughout this presentation were obtained from internal surveys, market research,

    publicly available information and industry publications. Although we have no reason to believe that any of this information or these reports are inaccurate in any

    material respect, we have not independently verified the competitive position, market share, market size, market growth or other data provided by third parties or

    by industry or other publications. ENEVA, the placement agents and the underwriters do not make any representation as to the accuracy of such information.

    This presentation and its contents are proprietary information and may not be reproduced or otherwise disseminated in whole or in part without ENEVAs prior written consent.

  • Thank you. www.eneva.com.br